Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Papineni Venkateswarlu vs The Union Of India
2026 Latest Caselaw 434 Tel

Citation : 2026 Latest Caselaw 434 Tel
Judgement Date : 7 April, 2026

[Cites 13, Cited by 0]

Telangana High Court

Papineni Venkateswarlu vs The Union Of India on 7 April, 2026

Author: Nagesh Bheemapaka
Bench: Nagesh Bheemapaka
IN THE HIGH COURT OF JUDICATURE FOR THE STATE OF
                    TELANGANA
     HON'BLE SRI JUSTICE NAGESH BHEEMAPAKA

             WRIT PETITION No. 20230 OF 2024

                        07.04.2026
Between:

Papineni Venkateshwarlu & others
                                                     ..... Petitioners
And

The Union of India,
Ministry of Road Transport & Highways,
New Delhi & others.
                                                ..... Respondents

O R D E R:

Petitioners contend that as per the letter of the

NHAI Project Implementation Unit-1, Khammam dated

08.02.2024, the impugned Nagpur to Vijayawada NH-163G

Greenfield Highway alignment was initially approved on

03.01.2019 by NHAI and subsequently approved by the Land

Acquisition Committee on 20.08.2020, and thereafter successive

notifications have been issued under Section 3A(1) of the

National Highways Act, 1956, culminating in Notification No.

S.O. 4407(E) dated 21.09.2022 and the declaration under

Section 3D(1) vide Notification No. S.O. 3928 dated 04.09.2023

for a stretch of 16.6 km, thereby subjecting the Petitioners to

prolonged uncertainty and mental agony from 2019 till date.

1.1. Petitioners further contend that repeated re-

issuance of notifications after lapse of earlier notifications is

arbitrary, unjust and contrary to the intent of the National

Highways Act, 1956, and that such reissuance cannot be

mechanical but must be justified by taking into account

changes that occurred during the intervening period, including

stakeholder concerns, and must necessarily be preceded by

fresh surveys and meaningful public consultations.

1.2. It is also contended that the District Collector,

Khammam, by letter dated 17.05.2022 addressed to the

authorities concerned through the Chief Secretary, Government

of Telangana, had specifically pointed out that the impugned

alignment was finalized without consultation with local bodies

such as Khammam Municipality, R&B Department and Gram

Panchayats, and further highlighted that the State Government

had paid Rs.1 crore per acre in 2018 for construction of the new

Collectorate, thereby rendering the cost of acquisition for the

impugned alignment exorbitantly high, and also pointed out

that the State Government had planned a ring road for

Khammam with allocation of Rs 200 crores for land acquisition.

1.3. The District Collector, in the said letter dated

17.05.2022, further stated that the entire city of Khammam falls

within 15 km aerial distance from the project boundary, thereby

adversely affecting nearly 5 lac population, and that the area

has already undergone urbanization due to the construction of

Collectorate near V. Venkatayapalem and the proposed ring

road, resulting in severe loss of commercial house plots to the

affected persons. Petitioners further contend that the Member of

Parliament, Lok Sabha, Sri Nama Nageswara Rao, addressed

representation to the Union Minister for Road Transport and

Highways requesting that the impugned alignment be shifted by

at least 5 km in view of the State's master plan for Khammam

ring road and the consequent urbanization, and that two

Members of the Rajya Sabha also addressed similar

representations seeking change of alignment.

1.4. Petitioners also contend that several similarly-

situated land losers approached this Court by filing W.P. Nos.

3921 of 2023, 20359 of 2023, 9109 of 2024 and 14632 of 2024

and obtained interim orders, thereby demonstrating the

widespread grievance against the impugned alignment. It is

further contended, the impugned Gazette Notification issued

under Section 3A(1) of the National Highways Act, 1956 is in

clear violation of Section 3A(2) of the Act, inasmuch as it does

not contain proper and sufficient particulars of the lands

proposed to be acquired, and only vague and misleading

particulars were furnished so as to deprive the affected persons

of an effective and meaningful opportunity to object.

1.5. Respondents, it is stated, deliberately published the

impugned notifications in newspapers such as Hans India and

Mana Telangana, which have limited circulation, with the

intention of avoiding public notice and preventing affected

persons from raising objections. The impugned action is in

derogation of the Manual of Guidelines on Land Acquisition for

National Highways under the National Highways Act, 1956,

particularly the requirement that the DPR consultant or

concerned officer must provide an indicative assessment of the

tentative cost of land acquisition based on prevailing rates prior

to issuance of notification under Section 3D, and that if such

cost is prohibitively high, appropriate changes in alignment

ought to be considered, which was not done in the present case.

1.6. Petitioners contend that Respondents have violated

the guidelines relating to segmentation of project length, which

mandate issuance of composite notifications for the jurisdiction

of one competent authority, and Respondents have deliberately

bifurcated the project into stretches of less than 30 km to

circumvent legal requirements and avoid proper scrutiny,

without consulting the District Collector on the issue of land

acquisition cost, despite the Collector having indicated the high

cost of land at Rs.1 crore per acre. It is also contended, the

impugned alignment passes within a few feet of the newly

constructed Collectorate, and despite the District Collector's

recommendation for change of alignment, in view of exorbitant

costs and public impact, the Respondents failed to consider the

same.

1.7. Petitioners also contend that the impugned

notification is in violation of the guidelines relating to Greenfield

Highways, which emphasize the possibility of adopting

alternative alignments a few kilometers away so as to achieve

better outcomes with reasonable cost. The width of the project

at 45 meters near V. Venkatayapalem is contrary to the

prescribed norms of NHAI, which require a minimum Right of

Way of 60 meters for a 4/6/8 lane Greenfield Highway and 90

meters for an expressway, and that such deviation renders the

project illegal and contrary to long-term planning requirements

for accommodating traffic growth for the next 30 to 40 years.

1.8. Petitioners further contend that the guidelines

mandate acquisition of entire Right of Way of 60 to 70 meters

for Greenfield Highways to ensure provision for upgradation and

service roads, which has not been adhered to in the present

case. The impugned alignment does not follow the crow-flight

route principle as required under the guidelines, which stipulate

that Greenfield alignments should, as far as possible, maintain

a straight route with minimal deviation and adequate distance

from existing habitations. Petitioners contend that the

impugned Greenfield Highway alignment is in violation of the

Environmental Impact Assessment Guidelines dated 14.09.2006

and amended on 01.12.2009, inasmuch as the project was

wrongly categorized as Category 'B' instead of Category 'A' and

that Environmental Clearance was obtained under mistaken

identity, rendering the same illegal.

1.9. Petitioners further contend that as per the EIA

Guidelines, projects with Right of Way exceeding 30 km in

length and more than 20 meters in width and involving inter-

state connectivity fall under Category 'A' requiring extensive

stakeholder consultations both prior to and after Environmental

Clearance and Respondents have deliberately segmented the

project into stretches of less than 30 km, including the present

stretch of 16.6 km, to circumvent these requirements. It is also

contended, such segmentation is impermissible in law in view of

the judgment of the Hon'ble Supreme Court in Civil Appeal Nos.

4035-4037 of 2020 (National Highways Authority of India v.

Pandarinathan Govindarajulu).

1.10. Petitioners further contend that the impugned

alignment is in violation of the EIA Guidelines relating to project

description, which mandate consideration of existing

development plans, alternative alignments, land acquisition

details and overall suitability of the project, and that the

alignment was finalized without consulting local authorities, as

specifically pointed out by the District Collector in his letter

dated 17.05.2022. The impugned alignment violates EIA

Guidelines relating to land use and environmental sensitivity,

which require assessment of master plans, identification of

sensitive areas such as hospitals, schools, places of worship

and community facilities within 15 km, and that the entire

Khammam city falls within such radius affecting nearly 5 lakh

population.

1.11. Petitioners also contend that the impugned

alignment is contrary to the mitigation measures prescribed

under the EIA Guidelines for air pollution, which require

selection of alignments avoiding proximity to residential areas,

schools and hospitals. The impugned alignment is also in

violation of mitigation measures relating to noise pollution,

which require development of bypasses to avoid noise-sensitive

areas, and that a bypass road or selection of alternative

alignments 'B' or 'C' would have addressed these concerns. The

impugned alignment passes within a few feet of the District

Collectorate, which houses revenue courts, and also near

Harvest Public School, Government Medical College and V.

Venkatayapalem Village, all of which are noise-sensitive and

critical establishments.

1.12. Petitioners also contend that the impugned

alignment is mala fide in its directional planning, as instead of

following a shorter crow-flight route from the western side of

Khammam, Respondents have chosen to deviate towards the

eastern side and take a turn, unnecessarily crossing the

Muneru river and increasing the length of the highway. Such

deviation is intentional and aimed at benefiting certain

influential persons at the cost of public interest and public

exchequer, as demonstrated in the pictorial representation filed

as Ex.P3. It is further contend that Respondents acted in haste

and in a clandestine manner to avoid objections from the public,

by issuing notifications in lesser-known newspapers, without

informing local government departments, public representatives

or the general public, and without providing adequate

particulars as required under Section 3A(2).

1.13. Petitioners also contend that several Gram

Panchayats adjacent to Khammam city have passed resolutions

opposing the impugned alignment, and have also issued letters

stating that they were unaware of the Environmental Clearance

obtained by NHAI, thereby demonstrating absence of public

consultation. Respondents have acted in willful violation of

norms, as evident from the reply under the Right to Information

Act dated 08.02.2024, wherein it was stated that alignment had

been finalized after deliberations between the Chairman of NHAI

and the State Government and that no change would be made,

without disclosing the date of such decision, which could not

have preceded the District Collector's letter dated 17.05.2022.

1.14. Petitioners further contend that approvals dated

03.01.2019 and 20.08.2020 are liable to be held illegal in light

of subsequent developments and objections raised. The

information sought under the Right to Information Act was

denied by reply dated 26.10.2021 citing an Office Memorandum

dated 04.08.2021 and a High Court judgment dated

09.07.2021, without furnishing copies thereof, indicating mala

fide intention to suppress relevant information. Respondents

acted mala fide as the Executive Summary dated November

2021 submitted by ENVIRO INFRA SOLUTIONS PVT. LTD.

states that baseline study was conducted between April 2021

and June 2021, whereas notifications had already been issued

earlier in 2019 and on 17.05.2021, indicating premeditated and

perfunctory action.

1.15. Petitioners further contend that selection of

alignment "A" Over alternatives 'B' and 'C' is arbitrary and mala

fide, as the consultant failed to conduct proper comparative

analysis, provided vague observations regarding tree felling

without quantitative data, and failed to consider other

parameters under the guidelines. Respondents failed to consult

the District Collector, local authorities, public representatives

and affected landowners, and failed to consider EIA Guidelines,

Land Acquisition Guidelines and mitigation measures.

Respondents are not respecting the judicial process, as despite

interim orders passed by this Court in respect of certain lands,

they continue to issue notifications and finalize alignment in

adjacent lands, which would create complications in the event of

success of the Petitioners. As per the judgment of the Hon'ble

Supreme Court in Union of India vs. Dr. Kushala Shetty in

Civil Appeal Nos. 2866-2880 of 2011, highway alignments can

be interfered with in cases of mala fides and statutory

violations, both of which are present ex facie in the present

case.

2. Respondents submit that Writ Petition is not

maintainable either in law or on facts and is based on incorrect,

misleading and untenable allegations and Petitioners have not

made out any case warranting interference under Article 226 of

the Constitution. Respondent No.3 - NHAI is a statutory

authority constituted under an Act of Parliament and is

entrusted with the responsibility of development, maintenance

and management of National Highways and matters incidental

thereto. It is also stated, the present project forms part of

Nagpur-Vijayawada Corridor undertaken under Bharatmata

Pariyojana Phase-1, which has been approved by the Ministry of

Road Transport and Highways NHAI in the larger national

interest, for promoting regional development and improving

inter-State connectivity, and that Khammam-Vijayawada

section of NH-163G is an integral part of the said corridor.

2.1. Respondents state that due care and diligence was

exercised while finalizing the alignment which was determined

after reconnaissance surveys, technical evaluation and detailed

deliberations, ensuring that alignment avoids existing

habitations, settlements, water bodies and religious structures

to the extent feasible, and that the alignment so finalized was

approved by the competent authority. In a meeting held on

03.01.2019, under the Chairmanship of the Secretary (RT&H),

New Delhi, the alignment options proposed by the DPR

Consultant for Nagpur-Vijayawada Corridor were deliberated,

and Option-I, being the present alignment bypassing hills and

forest areas, was approved, and thereafter the Land Acquisition

Committee of NHAI Headquarters, in its meeting dated

20.08.2020, accorded approval for the present alignment of

Mancherial-Vijayawada Corridor with a Right of Way of 45

meters.

2.2. Respondents also submit that earlier notifications

issued under Section 3A of the 1956 Act lapsed due to various

reasons, and therefore a fresh notification bearing No. S.O.

4407(E) dated 21.09.2022 was issued covering an extent of

82.79 hectares, duly providing brief particulars of the land as

required under Section 3A(2) of the Act. The format adopted for

publication of notifications under Section 3A is standardized

and uniformly followed across the country for all projects, and

that detailed particulars including names of landowners and

exact extents of land are provided at the stage of notification

under Section 3D.

2.3. At the stage of Section 3A notification, only

preliminary assessment based on available revenue maps is

undertaken without entering into the land, and that after

publication of the said notification, the authority is empowered

under Section 3B to enter upon the land for survey, and only

after completion of Joint Measurement Survey with revenue

authorities, detailed survey number-wise particulars and names

of landowners are ascertained. It is stated, after completion of

Joint Measurement Survey, Notification No. S.O. 3928(E) dated

04.09.2023 was issued under Section 3D of the Act, providing

complete details of affected farmers and extent of land required

for the project.

2.4. Respondents also state that the allegation regarding

improper segmentation is incorrect, and division of the project

into stretches or packages is only for the convenience of

construction, tendering and implementation, whereas the

Environmental Clearance as well as notifications under Sections

3A and 3D have been issued for larger stretches such as

Warangal-Khammam and Khammam-Vijayawada, and not in

the fragmented manner alleged by the Petitioners. It is also

stated, notifications issued under Sections 3A and 3D were also

made available in the public domain, including on the Bhoomi

Rashi Portal and the Government of India e-Gazette website,

thereby ensuring transparency and public access. The proposed

alignment does not obstruct or interfere with the proposed

Khammam Ring Road of the State Government and does not

create any impediment to the same.

2.5. Though the District Collector, Khammam, vide

letter No. Rc.No. G1/2771/2018 dated 17.05.2022, requested

change of alignment, the said request was duly considered and

a reply was issued by Respondent No.4 vide letter No. NHAI/RO-

HYD/11025/NH-163G/Man-Vij/2022/764 dated 13.06.2022,

clearly stating that change of alignment at that stage was not

feasible in view of the status of land acquisition, environmental

clearance and other factors involved in execution of the project.

Respondents further state that the State Government itself, vide

letter dated 01.02.2024, conveyed its concurrence for the

original alignment finalized by NHAI, pursuant to which a fresh

notification dated 26.02.2024 was issued. With regard to

environmental aspects, all procedures prescribed under the EIA

Notification, 2006 have been strictly followed, and that requisite

documents and reports were submitted to the competent

authority. It is also stated, the Terms of Reference for the

project were approved by the Ministry vide letter dated

16.08.2021.

2.6. Respondents further state that, in compliance with

the approved Terms of Reference, public hearings were

conducted after due notice in newspapers and in the respective

villages, namely at Raghunadhapalem village in Khammam

District and Ayyagaripalle village in Mahabubabad District,

under the supervision of the Additional District Collectors and

Additional District Magistrates of the respective districts, in the

presence of Environmental Engineers. The environmental

concerns raised by the public during such hearings were duly

considered and addressed, and thereafter, the Ministry of

Environment, Forest and Climate Change granted

Environmental Clearance on 16.02.2023 bearing identification

No. EC23A034TG157248 for the development of a 4-lane

access-controlled Greenfield Highway from Warangal to

Khammam covering a length of 108.240 km.

2.7. The Environmental Clearance was duly published

in newspapers, namely "The Hindu" and "Mana Telangana" on

18.02.2023, and was also communicated to all the Tahsildar

offices of the mandals concerned vide letter dated 23.02.2023

with instructions to display the same on notice boards for

public access. The District Collector, Khammam by letter dated

02.10.2022 addressed to the Member Secretary, MoEF&CC,

Government of India, has also stated that there would be no

major impact on forest and environment in Khammam District

due to the project.

2.8. Respondents also state that project has been

treated as Category 'A' for the purpose of Environmental

Clearance, therefore, the contention of Petitioners that it was

wrongly treated as Category "B" is factually incorrect and liable

to be rejected. The Environmental Clearance has been obtained

for the entire Warangal-Khammam stretch, and that

segmentation into three packages was only for the purpose of

competitive bidding and ease of execution, and not to

circumvent any statutory requirement.

2.9. Respondents further submit that land acquisition

for the project is being carried out strictly in accordance with

the provisions of the National Highways Act, 1956 read with the

Right to Fair Compensation and Transparency in Land

Acquisition, Rehabilitation and Resettlement Act, 2013, and

that compensation will be paid to affected landowners in

accordance with law. The Writ Petition is therefore, liable to be

dismissed, and the interim order of status quo granted on

30.07.2024 deserves to be vacated to enable Respondents to

proceed with land acquisition and implementation of the

project.

3. Heard Sri V. Rajeshwar Rao, learned counsel for

petitioners, Sri N. Bhujanga Rao, learned Deputy Solicitor

General, Sri Padma Rao Lakkaraju, learned Standing Counsel

for NHAI.

4. The challenge in the present writ petition is directed

against the Gazette (Extraordinary) Notification No. S.O. 4407(E)

dated 21.09.2022 issued under Section 3A(1) of the National

Highways Act, 1956 and the consequential Notification No. S.O.

3928 dated 04.09.2023 issued under Section 3D(1) of the said

Act, in respect of acquisition of land for the purpose of

formation of NH-163G Greenfield Highway in the stretch from

Km 203.8 to Km 220.48.

5. At the outset, it is to be noted that the 1956 Act is

a self-contained code providing a comprehensive statutory

mechanism governing acquisition of land for national highway

projects. The scheme of the Act contemplates issuance of a

preliminary notification under Section 3A(1), inviting objections

from interested persons, consideration of such objections under

Section 3C by the competent authority, followed by a

declaration under Section 3D(1) upon satisfaction of the

requirements of the Act. Section 3C of the Act confers a specific

statutory right upon any person interested in the land to raise

objections to the use of such land for the purpose specified in

the notification issued under Section 3A(1) and casts a

corresponding duty upon the competent authority to give an

opportunity of hearing and pass a reasoned order dealing with

such objections.

6. In the present case, petitioners raised a multitude

of contentions touching upon various aspects including, inter

alia, the selection of alignment, feasibility of alternative routes,

cost implications of land acquisition, alleged non-compliance

with the Manual of Guidelines on Land Acquisition,

environmental impact and compliance with Environmental

Impact Assessment Guidelines, adequacy of particulars in the

notifications issued under Section 3A(1), alleged lack of public

consultation, and purported mala fides in the decision-making

process. These contentions, by their very nature, involve

detailed examination of factual aspects, technical

considerations, policy choices and expert assessments,

including comparative evaluation of alternative alignments,

environmental consequences, engineering feasibility, and

economic viability.

7. On the other hand, Respondents have placed on

record that the alignment was finalized after due deliberations

at multiple levels, including the meeting held on 03.01.2019

under the Chairmanship of the Secretary (RT&H) and approval

by the Land Acquisition Committee of NHAI on 20.08.2020, and

that the notifications under Sections 3A(1) and 3D(1) have been

issued in accordance with the statutory scheme. They further

asserted that environmental clearance for the project was

obtained after following due procedure prescribed under the EIA

Notification, 2006, including approval of Terms of Reference,

conduct of public hearings and consideration of environmental

concerns by the competent authority.

8. In this context, this Court finds that the issues

raised by the Petitioners, particularly those relating to adequacy

of particulars in the Section 3A notification, objections to

alignment, alleged procedural irregularities, environmental

concerns and non-compliance with guidelines, fall squarely

within the scope of objections contemplated under Section 3C of

the National Highways Act, 1956.

9. The statutory mechanism under Section 3C is

specifically designed to address such grievances by providing an

opportunity to affected persons to place their objections before

the competent authority, which is vested with the jurisdiction to

examine such objections and take an informed decision in

accordance with law. It is well settled that when a statute

provides an efficacious alternative remedy, particularly one

involving adjudication of factual disputes and technical matters

by a competent authority, the writ jurisdiction under Article 226

ought not to be invoked as a matter of course.

10. The Hon'ble Supreme Court has consistently held

that writ courts should refrain from entertaining petitions

involving disputed questions of fact or matters requiring

technical expertise, especially when an adequate statutory

remedy is available, unless exceptional circumstances such as

patent lack of jurisdiction, violation of fundamental rights, or

manifest arbitrariness are demonstrated.

11. In the case on hand, although allegations of mala

fides and violation of statutory provisions have been made, the

same are intertwined with disputed factual issues requiring

detailed examination of records, technical data and expert

inputs, which cannot be effectively adjudicated in summary

proceedings under Article 226. This Court is of the considered

view that determination of issues such as suitability of

alignment, comparative merits of alternative routes, compliance

with technical guidelines, environmental impact and adequacy

of surveys necessarily require evaluation by specialized

authorities equipped with requisite expertise and access to

primary data.

12. Further, the question as to whether the particulars

furnished in the notification under Section 3A(1) satisfy the

requirement of Section 3A(2), and whether adequate opportunity

has been afforded to the affected persons, are matters which

can be effectively urged before the competent authority in

proceedings under Section 30. It is also relevant to note that the

statutory scheme does not render petitioners remediless, but

rather provides a specific forum and procedure for ventilating

their grievances, including the right to be heard and to place all

the relevant material before the authority. In such

circumstances, entertaining the present Writ Petition, at this

stage, would amount to bypassing the statutory mechanism and

prematurely invoking the extraordinary jurisdiction of this

Court, which is not warranted in the facts and circumstances of

the case.

13. This Court is therefore, of the opinion that

petitioners ought to have availed the alternative statutory

remedy available under Section 3C of the 1956 Act, by

submitting their objections before the competent authority and

raising all contentions, including those urged in the present

Writ Petition. In view of the foregoing discussion, this Court

finds no ground to entertain the writ petition at this stage in

exercise of its jurisdiction under Article 226 of the Constitution

of India.

14. Accordingly, the Writ Petition is disposed of, leaving

it open to Petitioners to avail the statutory remedy by filing

appropriate objections before the competent authority under

Section 3C of the National Highways Act, 1956, and to raise all

contentions as urged in the present writ petition. It is made

clear that if such objections are filed, the competent authority

shall consider the same independently, objectively and in

accordance with law without being influenced by any

observations made in this order and shall afford due

opportunity of hearing to petitioners. No costs.

15. Consequently, the miscellaneous Applications, if

any shall stand closed.

-------- -----------------------------

NAGESH BHEEMAPAKA, J

07th April 2026

ksld

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter