Monday, 13, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Pinaki Infrastructures Private ... vs M/S. Vasishta Mantena Nh4 Jv
2026 Latest Caselaw 237 Tel

Citation : 2026 Latest Caselaw 237 Tel
Judgement Date : 1 April, 2026

[Cites 2, Cited by 0]

Telangana High Court

M/S. Pinaki Infrastructures Private ... vs M/S. Vasishta Mantena Nh4 Jv on 1 April, 2026

Author: P.Sam Koshy
Bench: P.Sam Koshy
     IN THE HIGH COURT FOR THE STATE OF TELANGANA
                     AT HYDERABAD

       THE HONOURABLE SRI JUSTICE P.SAM KOSHY

           ARBITRATION APPLICATION No.83 of 2025

                           DATE: 01.04.2026

Between:
M/s. Pinaki Infrastructure Private Limited.
                                                            ...Applicant
                                  AND

M/s. Vasishta Mantena NH4 JV.
                                                          ...Respondent


ORDER:

Heard Mr. Bhaskar Muthyala, learned counsel for the applicant;

and Mr. Naumene Suraparaj Karlapalem, learned counsel for the

respondent.

2. The instant Arbitration Application under Section 11 (5) & (6) of

the Arbitration and Conciliation Act, 1996 (for short the 'Act') has been

filed by the applicant seeking for appointment of an Arbitrator to

adjudicate upon the disputes that have arisen between the applicant and

the respondent as per clause 16 of both the sub-contract agreements

dated 07.01.2019.

3. The facts of the case in nutshell are that the applicant is a company

incorporated under the provisions of Companies Act, 1956 and carries

out a wide range of infrastructure and engineering activities. Its core

business includes executing civil and electrical engineering projects such

as construction of transmission and distribution lines, substations, and

turnkey power projects and is also involved in manufacturing

components for power infrastructure. The applicant company also has its

business in renewable and conventional energy sectors (solar, wind,

thermal, etc.), industrial electrification, and automation and also

undertakes water infrastructure projects like dams, reservoirs, pipelines,

and distribution systems. Further, the applicant company is also engaged

in housing and development projects (independently or through joint

ventures) and deals in generation, distribution, supply, import, export,

and trading of electricity and energy-related products in various forms.

On 07.01.2019 both the parties entered into two sub-contract

agreements; one for construction / shifting of electrical utilities along

ongoing widening and construction work of NH-4 in Andaman and

Nicobar Islands and rehabilitation and another for upgradation of section

from Km 206.00 to Km 239.425 of NH-4 (total length 33.405 Km) of

NH-4 to 2 lane with hard shoulder in the Union Territory in Andaman &

Nicobar Islands on EPC basis.

4. Learned counsel for the applicant submits that quality work was

carried out by the applicant until oral instructions were received from the

respondent directing cessation of the work, for reasons best known to the

respondent. It is further submitted that the applicant has raised invoices

timely, but the respondent failed to clear the same in a time-bound

manner and the applicant also approached the respondent to clear the

same in time but the respondent failed in doing so.

5. It was submitted by the learned counsel for the applicant that in

terms of clause 16 of the sub-contract agreements, dated 07.01.2019, the

applicant sent a notice to the respondent for settlement of disputes by

appointment of Mr. Mohammed Imran Khan, Senior Advocate as a sole

Arbitrator, however the respondent rejected the said proposal stating that

since they have failed in giving consent regarding appointment of

Mr. Mohammed Imran Khan, Senior Advocate as a sole Arbitrator, they

do not intend to proceed with arbitration on the said terms.

6. On the other hand, the learned counsel for the respondent

opposing the instant Arbitration Application submits that the respondent

has never instructed the applicant to stop the work either orally or in

writing. However, the learned counsel for the respondent does not

dispute the existence of the arbitration clause in sub-contract agreements,

dated 07.01.2019, which provides a mechanism for resolving disputes

through the appointment of an Arbitrator.

7. Having heard the contentions put forth on either side and on

perusal of records, undisputedly there is an arbitration clause in the

agreement dated 07.01.2019to resolve the dispute by way of arbitration.

It would be trite at this juncture to take note of the arbitration clause

which is reflected in the agreement dated 07.01.2019. For ready

reference, the arbitration clause i.e. clause 16 of the agreement dated

07.01.2019 is reproduced hereunder, viz.,

"16. Arbitration:

Any dispute resulting from this agreement shall be settled amicably by mutual consultation. In the event if amicable settlement is not reached in any particular case, the dispute shall be referred to arbitration to a Sole Arbitrator to be mutually agreed by and between PIPL and the NH4 JV. The venue for arbitration shall be at Hyderabad and each party shall bear its expenses. The decision of the majority of the arbitrators shall be final and binding on both the parties. Subject to the above, the courts in the city of Hyderabad shall alone have jurisdiction to entertain any litigation relating to or arising out of this agreement."

8. A plain reading of the aforesaid clause makes it amply clear that

any dispute arising out of or relating to the agreement, has to be resolved

by way of negotiations and still if the dispute stands unresolved, the

same has to be referred to arbitration. Furthermore, all the objections that

the respondent have can be raised before the Arbitrator, which the

Arbitrator is expected to take note of, and decide the same after hearing

both the sides in accordance with law.

9. In the given factual circumstances of the case, this Court is

inclined to appoint an arbitrator who shall in turn decide the grievances

and the claims raised by the applicant. In the course of the deliberation,

learned counsel for the parties accepted the suggestion of Hon'ble Sri

Justice P.Naveen Rao, former judge of this High Court to be appointed as

an Arbitrator and adjudicate the claim raised by the applicant.

Accordingly, this Court appoints Hon'ble Sri Justice P.Naveen Rao,

former Judge of this High Court (#3001, My Home Bhooja, Block-A,

Plot Nos.22-24 & 31-33, Rayadurgam, Ranga Reddy District, Mobile

No.8374012311) to act as an Arbitrator and to pass appropriate award in

terms of the provisions of the Act. The venue of the arbitration shall be

decided mutually by the parties subject to the consultation and

agreement of the learned Arbitrator. The fees of the learned Arbitrator

also be decided mutually by the parties again in consultation and

agreement with the learned Arbitrator and the arbitration proceedings

shall be governed in accordance with the provisions of the Act.

10. The instant Arbitration Application accordingly stands allowed.

11. As a sequel, miscellaneous petitions pending if any, shall stand

closed. However, there shall be no order as to costs.

________________ P.SAM KOSHY, J Date: 01.04.2026 Note: Office to communicate a copy of this order to the learned Arbitrator.

(B/o)GSD

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Media

 
 
Latestlaws Newsletter