Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Prashant Poultry Private Limited vs State Of Telangna
2025 Latest Caselaw 15 Tel

Citation : 2025 Latest Caselaw 15 Tel
Judgement Date : 1 May, 2025

Telangana High Court

M/S Prashant Poultry Private Limited vs State Of Telangna on 1 May, 2025

          THE HON'BLE SRI JUSTICE PULLA KARTHIK

                    WRIT PETITION No.11034 of 2025
ORDER:

This Writ Petition is filed seeking the following relief:

"... declaring the action of the respondents, particularly respondent No.2 in issuing the proceedings bearing No.4879/SNP-3/2024, dated 28.03.2025, by blacklisting the poultry firm of the petitioner i.e., M/s.Prashant Poultry Private Limited with immediate effect as being illegal, arbitrary, contrary to law, violative of principles of natural justice, without notice and set aside the same and consequently direct respondents to receive and process the same as per the tender uploaded on the website of the respondent department dated 30.03.2025, inviting online tenders for State Level Zonal Tender for procurement and supply of Eggs (hen) as per the AGMARK specifications and other processing/grading conditions as mentioned in the tender for a period of one year (April 2025-March, 2026) to the beneficiaries under the flagship of Arogya Lakshmi and Supplementary Nutrition Program for Zone-1, 2, 3, 4, 5, 6 & 7, approve the tender subject to terms of tender conditions as per law ...."

2) Heard Mr. E. Madan Mohan Rao, learned senior counsel,

representing Sri M.Srinivas, learned counsel for the petitioner, and

learned Advocate General appearing for the respondents.

3) Learned senior counsel appearing for the petitioner has submitted

that the petitioner has participated in State Level Zonal Tender for

Procurement and Supply of Eggs (Hen) along with other tenderers in the

month of November, 2022 and tender has been approved in favour of the

petitioner Company for a period of 2 years for Zone-6 (Charminar Zone).

PK, J

Accordingly, respondents 2 and 3 entered into an agreement on

07.02.2023 with petitioner Company for supply of eggs, as per the terms

of the agreement, for a period of two years commencing from 01.03.2023

in the Districts of Medchal-Malkajgiri, Ranga Reddy, Sangareddy and

Vikarabad in Zone-VI Charminar. In pursuance thereof, the petitioner

Company has been supplying the eggs as per the terms and conditions

of the agreement without any delay. Learned senior counsel further

submitted that inspite of the petitioner Company maintaining quality

and quantity, the respondents have started issuing show cause notices

to the petitioner Company from the beginning itself, with malafide

intention and for extraneous reasons, complaining that the eggs

supplied are delayed and delivered at late hours and not in working

hours and that the eggs are rotten and the eggs are being supplied in

the month end leading to THR distribution and the supply of quantity

was 89% instead of 100%, though the petitioner supplied as per the

terms and conditions of the agreement.

3.1) Learned senior counsel has further contended that on one hand

the respondents continued to issue notices and on the other they

received the supplies, till the end of expiry of contract by the end of

February, 2025. Further, in spite receiving the supply, bills are not

being paid and nearly five months payment is due from the Government.

PK, J

While so, during first week of April, 2025, the petitioner was issued with

the impugned proceedings dated 29.03.2025 referring to show cause

notices earlier issued to the petitioner and stating that the petitioner

failed to submit explanation to the said notices. Learned senior counsel

has vehemently contended that vide impugned proceedings, the

respondents have blacklisted the petitioner Company with immediate

effect and barred from participating in the future contracts, tenders,

procurement process and immediately on 30.03.2025 a fresh

notification calling for tenders for the year 2025-2026 has been issued,

in order to give contract to other tenderers malafidely and further

without any notice proposing to blacklist, the impugned proceedings

dated 28.03.2025 are issued by respondent No.2, arbitrarily and in

colourable exercise of power and contrary to the agreement. Further,

during the period of agreement dated 07.02.2023, despite issuance of

show cause notices, no action was taken for either termination or

imposition of penalty, as provided in paragraph V of the agreement.

3.2) Learned senior counsel has further contended that in the show

cause notices, it was alleged about default in supply, delay, less

quantity, smell, etc., but in none of the show cause notices, there was

any mention of threat of blacklisting not only to the petitioner but also

to other contractors in other zones and said show cause notices were

PK, J

issued only for statistical purpose. Learned senior counsel further

contended that though similar show cause notices were issued to seven

other approved contractors of notification 12.08.2024, but no action is

taken to blacklist any of them but the petitioner alone was blacklisted

inspite of receiving supplies from the petitioner till the end of the

contract and the same amounts to discrimination and favoritism and

therefore prayed this Court to set aside the impugned order. Reliance

has been placed on M/s.Erusian Equipment and Chemicals Ltd. v.

State of West Bengal 1, Raghunath Thakur v. State of Bihar 2 and

Gorkha Security Services v. Govt. Of NCT of Delhi 3.

4) Per contra, the learned Advocate General has submitted that as

the petitioner was L1 bidder under the State-Level Zonal Tender floated

in November, 2022, he was awarded the contract in Zone-6 for supply of

eggs (hen) subject to compliance of tender terms. However, its bid for

Zone-7 was rejected due to non-fulfillment of eligibility conditions. The

petitioner, having voluntarily executed the agreement, dated

07.02.2023, is abide by the terms relating to supply, grading, quality

and delivery, including clause-V(7) thereof, which deals with Blacklisting

and clause-XI which deals with arbitration. Several complaints were

1 AIR 1975 SC 266 2 AIR 1989 SC 620 3 AIR 2014 SC 3371

PK, J

received against the petitioner from Zone-6 regarding delay in deliveries

and deficient quantity. Therefore, show cause notices were issued to the

petitioner citing the contractual breaches and intimating that such

continued negligent conduct would result in termination and

blacklisting, as per the terms of the agreement. But, the petitioner has

not responded to any notice. Clause-V(7) of the agreement dated

07.02.2023 empowers the Department to blacklist the defaulting

contractors. Despite of existence of such agreement condition, the

petitioner was reluctant in submitting its explanation/remedial plan to

the Department. Learned Advocate General has contended that the

petitioner does not qualify as per clause 2.12 of the new tender dated

30.03.2025 and corrigendum dated 08.04.2025, as it lacks a valid

AGMARK grading certificate from the Directorate of Marketing and

Inspection. The Department has acted only to protect the interest of the

beneficiaries, who are children aged between 7 months - 6 years,

pregnant and lactating mothers. Further, the blacklisting was

necessitated solely due to persistent non-performance and failure on the

part of the petitioner to respond to the repeated notices issued to it.

Further, the multiple opportunities given by the Department to the

petitioner to rectify the deficiencies and to submit a detailed

reply/defense were not utilized by the petitioner.

PK, J

4.1) Learned Advocate General has strenuously contended that in

three show cause notices dated 25.05.2024, 15.07.2024 and

04.09.2024, it was clearly stated that continued non-compliance and

negligence would consequently result in termination and blacklisting,

however, the same were suppressed by the petitioner before this Court.

A party who seeks equity must do equity and cannot be allowed to

mislead the Court by concealing material particulars. Such conduct

strikes at the very foundation of equitable relief under Article 226 of the

Constitution of India. Therefore, the writ petition is liable to be

dismissed in limine on this ground alone. While specifically pointing out

of the supply failures on the part of the petitioner during the months of

November-2024, December-2024 and January-2025, it is contended

that such default has caused anguish to the beneficiaries as well as the

Department. It is specifically alleged that the petitioner has diverted

supplies from Anganwadi Centers to the open market whenever the cost

of eggs increased in the open market to make more profits, at the cost of

health of the beneficiaries. Petitioner has also not made bonafide effort

to compensate the shortfall in its subsequent consignments. Such

conduct not only amounts to breach of contractual obligations but also

undermines the core objectives of supplementary nutrition program and

Aarogya Lakshmi scheme.

PK, J

4.2) Insofar as discrimination alleged by the petitioner is concerned,

learned Advocate General has contended that other suppliers of other

Zones including M/s.Rajitha Poulty Farm and Feeds were also issued

show cause notices during their tenure for non-compliance or

rectification of deficiencies, to which, they have submitted replies and

taken adequate remedial measures, whereas, the petitioner has failed

even to respond to the notices issued to it and therefore the case of the

petitioner cannot be equated with other suppliers.

4.3) It is further contended that the contractual period with the

petitioner was ended by 28.02.2025 and the temporary extension

granted thereafter was not an endorsement of its performance, but a

necessary administrative measure compelled by the food supply

disruption and due to enforcement of Model Code of Conduct the fresh

tenders could not be floated. It is further asserted that the name of the

petitioner does not find place in the 'List of Poultry Farmers issued with

replica numbers for eggs for the past two years' dated 08.04.2025,

issued by the Department of Marketing and Inspection, Ministry of

Agriculture & Farmers Welfare, Government of India. Thus, finally, it is

contended that the respondents are justified in passing the impugned

order blacklisting the petitioner Company as the same was preceded by

persistent defaults on the part of the petitioner and sufficient show

PK, J

cause notices by the respondents. Hence, it is prayed to dismiss the

writ petition.

5) In reply, the learned Senior Counsel appearing for the petitioners

has contended that the allegations made against the petitioner are

vague and do not refer to specific lapses and therefore the same cannot

form basis for passing the impugned order. Further, the officials of the

petitioner Company have personally visited the authorities and the

officials have explained about the quality and quantity of the supply and

also requested the authorities to state as to which consignment contain

the low quality of eggs etc, to which the authorities have submitted no

information and therefore the petitioner Company was not in a position

to submit effective explanation as the petitioner has been supplying the

eggs as per the terms and conditions accepted from time to time.

Learned senior counsel has further contended that inspite of issuing

notices, the respondents received the supply till the expiry of contract

period i.e. by the end of February 2005 and also continued to receive the

supply even thereafter. In fact, in the show cause notices dated

25.05.2024, 15.07.2024, 25.07.2024, 04.09.2024 and 07.03.2025, only

the violations were pointed out and observed that if explanation is not

submitted, further action will be initiated as per the records and none of

the notices specifically stated about particular penalty/action which has

PK, J

to be taken as proposing to blacklist for a period. Therefore, the notices

issued to the petitioner are clearly contrary to the law laid down by the

Hon'ble Supreme Court in Gorkha Security Services and Erusian

Equipments and Chemicals (referred supra) and also UMC

Technologies v. Food Corporation of India 4 wherein it was clearly

held that notice specifically proposing the penalty should be issued. It

is further contended that all the notices relate to the allegations of

performance of the contract and those notices were not acted upon and

the last notice being dated 29.01.2025 only speaks of the action to be

taken as per the Rules with reference to low deficit supply of eggs in

January, 2025. As such the continuation, caution presumption cannot

be urged by the respondents with reference to the show cause notice

unless it is specifically proposed preceding the show cause notice before

passing the impugned order dated 28.03.2025.

5.1) While denying the submission made by the learned Advocate

General that the petitioner had no locus standi to question or seek

permission to participate in the tender agreement dated 30.03.2025 or

do not have the requisite eligibility qualifications to participate in the

tender, the learned senior counsel has contended that the petitioner has

the requisite eligibility qualifications to participate in the tender. As

4 (2021) 2 SCC 551

PK, J

regards clause 2.12 is concerned, it is contended that as the petitioner

has not yet submitted its tender, the contention of the respondents that

the petitioner does not qualify under clause 2.12 is untenable and

misconceived.

5.2) Further, the show-cause notices only state that further action will

be initiated to keep the firm in blacklisting but does not specify the

principle of law on blacklisting. As regards submission of

reply/explanation to the show cause notices, it is submitted that the

officials of the petitioner's Company have clarified to the authorities and

they stated that the said notices were issued to all the contractors

mechanically and routinely in view of certain incidents reported in

newspaper and only to overcome the criticism against the Government.

It is further contended that the notices were issued without specifying

the nature of allegations with reference to a particular incident or

particular batch supplied, the quality or quantity supplied. Learned

senior counsel has strenuously contended that though similar notices

were issued other contractors, no action is taken against them and

action is taken only against the petitioner by passing the impugned

order dated 28.03.2025, served on the petitioner on 30.03.2025, only to

see that the petitioner shall not participate in the fresh tender notified

on 30.03.2025 that too without terminating the contract and even

PK, J

during the extended period after the expiry of the contract period.

Further, if the allegations leveled in the show cause notice are serious in

nature, the authorities ought to have resorted for immediate action as

per clause-V of the agreement dated 07.02.2023 imposing penalty/

termination during the contract period. Further, while denying the

allegations of diverting the supplies from Anganwadi Centers to open

market whenever the cost of eggs is increased in the open market, it is

contended none of the correspondence had a mention of the above

allegations and for the first time the said allegation was made before this

Court without any details/proofs. With reference to the alleged

shortfall/failure to replenish the deficit, it is alleged that they are with

reference to the existing contract and the same are nothing to do with

the issuance of proper show cause notice and following procedure in the

nature of punishment of blacklisting and the conduct of not submitting

the explanation do not absolve imposition of penalty by State without

following the procedure of law. In fact, after issuance of show cause

notices, the officials of the petitioner Company met the authorities and

explained that there are no deficiencies and the same is borne out by

the conduct of the respondents as no action has been initiated

thereafter.

PK, J

5.3) It is further contended that the impugned order is passed only to

exclude the petitioner from participating in the tender and to favour

other tenderers. Further, clause 2.12 will not apply at this stage. No

notice specifically proposing to blacklist was issued and the show cause

notices issued are only to rectify the alleged irregularities during the

subsistence of contract. Further, the petitioner possess the requisite

qualifications to participate in the fresh contract and the impugned

order dated 30.03.2025 is passed only to prejudice the petitioner.

Further, it is settled by the Hon'ble Supreme Court that blacklisting has

a serious consequence on fundamental right to trade with the

Government and blacklisting cannot be for indefinite period and shall

depend on gravity. Hence, it is contended that imposition of

punishment of blacklisting without specifying the period is illegal and

arbitrary. Reliance has been placed on Kulja Industries Limited v.

Chief General Manager, Western Telecom Project Bharat Sanchar

Nigam Limited 5.

6) This Court has taken note of the submissions made by respective

parties and gone through the material on record.

7) A perusal of the material on record reveals that after approval of

the tender in favour of the petitioner Company for supply of eggs (hen)

5 (2014) 14 SCC 731

PK, J

for a period of two years in respect of Zone-VI i.e. Charminar Zone, the

petitioner entered into an agreement with respondents 2 and 3 on

07.02.2023 and the agreement period commenced from 01.02.2023.

Further, though the petitioner received the show cause notices issued by

the authorities on 25.05.2024, 15.07.2024, 25.07.2024 and 04.09.2024,

wherein the respondents have proposed to initiate action against the

petitioner, admittedly, the petitioner has not responded to any of the

said show cause notices.

8) Before dealing with the contention of the petitioner, precisely, as

regards non-submission of its explanation, this Court deems it apt to

reproduce the relevant contents of the said show cause notices.

a) Show cause Notice dated 25.05.2024 mentions as under:

"...

Vide reference 5th cited, Adverse news published in Velugu News paper with caption "Anganwadi Centre ki Kullina Gudlu supply" at "Yellamkonda village, Nawabpet Mandal, ICDS Vikarabad project, Vikarabad District, dt:23.05.2024, stating that eggs which were supplied to the beneficiaries were not good quality and getting bad odur at Yellamkonda village, Nawabpet Mandal, ICDS Vikarabad project which comes under Zone-6.

.....

Hence, the proprietor is directed to submit the explanation to the show Cause notice within 3days on receipt of this notice. If failing with it will be

PK, J

presumed that there is nothing to say in your defence and further action will be initiated to keep the firm in black list as per rules in force."

b) Similarly, Show Cause Notice dated 15.07.2024 mentions as

under:

" .... Vide reference 5th cited, Adverse news published in Sakshi Newspaper with caption "Anganwadilo Kullina Gudlu" at "Udanraopally village, Doma Mandal, ICDS Parigi project, Vikarabad District, dt:05.07.2024, stating that eggs which were supplied to Anganwadi centres were rotten at Udanraopally village, Doma Mandal, ICDS Parigi project, Vikarabad District which comes under Zone-6.

......

Hence, the proprietor is directed to submit the explanation to the Show Cause notice within 3days on receipt of t his notice. If failing with it will be presumed that there is nothing to say in your defence and further action will be initiated to keep the firm in black list as per rules in force."

c) Likewise, the show cause notice dated 25.07.2024 mentions the

following:

".. Vide reference 6th cited, the collector, Vikarabad District has visited AWCs on 12.07.2024 and informed that no eggs stock is available in 382 AWCs of Vikarabad dist.

Further, it is to inform that, the eggs supplies to Vikarabad district in the month of June, 2024 was 83% only and supplies in the month of July'2024 was 31% only till 12.07.2024 against the indent placed in CSTS app on 04.07.2024.

Further it is inform that, vide reference 5th cited this office has already issued show cause notice to the firm on Adverse News published in Velugu Newspaper with caption "Anganwadi Centre ki Kullina Gudlu supply" at

PK, J

"Yellamkonda village, Nawabet Mandal, ICDS Vikarabad project, Vikarabad District, dt:23.05.2024 with instructions to submit the reply/explanation with in 3days. But, whereas the explanation for said show cause notice is not yet received from the concerned firm.

In this connection, it reveals that the lapses and allegations mentioned in the show cause notice are true and you are accepted the allegations made on your firm and the explanation is still not furnished by you as there is nothing to say in your defence.

Hence, in view of the above circumstances you are instructed to show cause why the contract should not be terminated duly forfeiting the bank guarantee for the above lapses for violating terms and conditions as per clause 17&19 laid in the egg tender document and SOP guidelines supplying rotten eggs and delay in supplies to the AWCs.

Hence, the proprietor is directed to submit the explanation to the Show Cause notice within 3days on receipt of this notice, failing which it will be presumed that there is nothing to say in your defence and further action will be initiated as per the record materials, evidences and records available with the office."

d) Similarly, the show cause notice dated 04.09.2024 contains the

following:

"... In this connection, to the above recent adverse issues reported regarding the supply of eggs to the Anganwadi Centers (AWCs) under the ICDS Project Maheshwaram. The enquiry report dated 03.09.2024 highlights severed serious concerns about the quality and condition of the eggs provided by Prashanth Poultry Pvt. Ltd.

Observations on enquiry:

1. Quality and Weight Discrepancies: The eggs received on 28.08.2024 were found to be of inferior quality, with discrepancies in weight and spoilage issues reported.

PK, J

2. Complaints and Actions Taken: Complaint was lodged, leading to the replacement of 205 eggs on 03.09.2024. Further dissatisfaction from the ward member and beneficiaries has been noted.

Violation of Agreement and Guidelines:

As per the agreement terms and conditions specified in Class 3 and 5.1 of the tender document, any deviations in the process, handling, and storage activities render the bidder liable for penalization. The Standard Operative Procedures (SOP) clearly mandate that eggs supplied must conform to AGMARK specifications and meet required quality standards.

The following points have been violated as per the terms of the agreement and SOP guidelines:

(i) Deviation from Agreement Terms: The supply of spoiled eggs constitutes a breach of the agreement.

(ii) Violation of SOP Guidelines: The supplied eggs failed to meet the AGMARK specifications, reflecting non-compliance with the quality standards set forth.

(iii) Failure to submit explanation: Through the Ref 5th cited, the Poultry firm has not submitted explanation for the 2 Show Cause notices issued on adverse News & District collector, Vikarabad Visit to AWCs. This shows negligence towards the addressing the issue.

In the light of these circumstances, it is hereby directed to provide a written explanation, addressing the following:

1) Explanation for Deviations: Provide a detailed explanation for the supply of inferior quality eggs not as per the terms and conditions of tender.

2) Lab Reports: The lab reports of the eggs for this particular batch should be provided by the Laboratory submitted as per the bid documents.

PK, J

3) A Status certificate from Animal Husbandry Dept. on the production capacity on AGMARK Graded eggs weighing 45-52 gms of the Poultry Firm.

Failure to submit a satisfactory explanation within the stipulated time of three (3) Days from the date of this notice may result in the following actions:

Contract Termination: Consideration for termination of the contract.

Forfeiture of Bank Guarantee: Action for forfeiting the bank guarantee as per Clause 17 and 19 of the agreement.

Blacklisting: Blacklisting of the firm as per the rules in force."

9) In all the above referred show cause notices, while pointing out

the lapses on the part of the petitioner, the respondents have specifically

stated to submit its explanation within a stipulated time. In spite of

such specific directions, the petitioner failed to submit its explanation to

any of the above referred show cause notices. Though the learned

senior counsel has contended that the officials of the petitioner

Company have visited the authorities and asked them to provide details

as to which consignment was of inferior quality, for which, the

authorities have informed that the notices were issued for statistical

purpose and therefore the petitioner had not submitted its explanation,

but, the said contention cannot be countenanced as it is common

prudence that when a series of show cause notices are issued, the same

PK, J

shall not be remained unanswered. Hence, an adverse inference has to

be drawn against the petitioner for not submitting its explanation.

10) Further, Para-V of the Agreement dated 07.02.2023 entered

between the parties, speaks of Penalties and clause (7) thereof reads as

under:

"It is to be ensured that the stocks are supplied as per the indented quantity. If the ordered quantity is not supplied in full, within the stipulated time, the EMD & Security Deposit may be forfeited besides blacklisting. Further for any defaults in supplies either wholly or partially on account of quality aspect (or) quantity aspect the delay in supply, apart from forfeiture of security deposit, further action may also be initiated as per terms and conditions mentioned in the tender document and Acts/rules in vogue.

(emphasis added)

11) Similarly, in AIR INDIA LTD. v. COCHIN INTERNATIONAL

AIRPORT LTD. 6, the Hon'ble Supreme Court has summarized the scope

of interference as enunciated in several earlier decisions thus:

"7. The award of a contract, whether it is by a private party or by a pubic body or the State, is essentially a commercial transaction. In arriving at a commercial decision considerations which are paramount are commercial considerations. The State can choose its own method to arrive at a decision. It can fix its own terms of invitation to tender and that is not open to judicial scrutiny. It can enter into negotiations before finally deciding to accept one of the offers made to it. Price need not always be the sole criterion for awarding a contract. It is free to grant any relaxation, for bona fide reasons, if the tender conditions permit such a

2000 (2) SCC 617

PK, J

relaxation, for bona fide reasons, if the tender conditions permit such a relaxation. It may not accept the offer even though it happens to be the highest or the lowest. But the State, its corporations, instrumentalities and agencies are bound to adhere to the norms, standards and procedures laid down by them and cannot depart from them arbitrarily. Though that decision is not amenable to judicial review, the Court can examine the decision-making process and interfere if it is found vitiated by mala fides, unreasonableness and arbitrariness. The State, its Corporations, instrumentalities and agencies have the public duty to be fair to all concerned. Even when some defect is found in the decision-making process the Court must exercise its discretionary power under Article 226 with great caution and should exercise it only in furtherance of public interest and not merely on the making out of a legal point. The Court should always keep the larger public interest in mind in order to decide whether its intervention is called for or not. Only when it comes to a conclusion that overwhelming public interest requires interference, the Court should intervene."

(Emphasis added)

12) In Assn. of Registration Plates v. Union of India 7, the Hon'ble

Supreme Court has held as under:

"43... Article 14 of the Constitution prohibits the Government from arbitrarily choosing a contractor at its will and pleasure. It has to act reasonably, fairly and in public interest in awarding contract. At the same time, no person can claim a fundamental right to carry on business with the Government. All that he can claim is that in competing for the contract, he should not be unfairly treated and discriminated, to the detriment of public interest."

7 (2005) 1 SCC 679

PK, J

13) From the above, it is clear that the Courts shall not interfere in

the decision-making process unless the same is found to be vitiated by

unreasonableness, mala fides and arbitrariness.

14) Admittedly, in the present case, the petitioner itself failed to

submit its explanation to any of the notices, referred supra, wherein it

was specified that in case of failure to submit its explanation, the

respondents will initiate further action. Further, the show-cause notice

dated 04.09.2024 clearly specifies that Failure to submit a satisfactory

explanation within the stipulated time of three (3) days from the date of

the notice may result in termination/forfeiture/blacklisting. Therefore,

the action of the respondents in blacklisting the petitioner's Company

cannot be interfered with. Further, the judgments relied by the learned

senior counsel in Erusian Equipment and Chemicals Ltd.,

Raghunath Thakur, Gorkha Security Services and UMC

Technologies (referred supra) are not applicable to the case on hand

and are distinguishable, as the petitioner has not submitted its

explanation to the show cause notices issued to it by the respondent

authorities.

15) Insofar as the contention of the petitioner as regards black listing

the petitioner's Company permanently is concerned, it is apt to refer to

the judgment in State of Odisha v. Panda Infra Projects (India)

PK, J

Private Limited 8, wherein the Hon'ble Supreme Court has held as

under:

"29. In the instant case, it might be true that the offence was the first offence committed by the contractor. However, considering the seriousness of the matter that due to the omission and commission on the part of the contractor a serious incident had occurred as there was a collapse of a ten metre slab while constructing a flyover in which one person died and eleven others injured, as such the contractor does not deserve any leniency. However, to debar him permanently can be said to be too harsh a punishment. But considering the subsequent OM dated 26-11-2021 reproduced hereinabove (to which as such we do not agree as observed hereinabove), we are of the opinion that if the blacklisting is restricted to five years, it may be in the fitness of things."

16) in the instant case, the impugned order dated 28.03.2025 is

passed blacklisting the petitioner's Company for the lapses of deficit

supply, delay in supply, late hours supply, supply not in working hours,

rotten and small eggs (less than 45 grams), etc. however, without

specifying the period of blacklisting, which in the considered view of this

Court is too harsh for the alleged lapses and therefore needs to be

interfered with.

17) For the aforementioned reasons, while confirming the action of the

respondents in blacklisting the petitioner's Company, the impugned

order dated 28.03.2025 is set aside to the extent of not indicating the

period of blacklisting and the matter is remanded to the authorities for

taking appropriate decision on the period for which the petitioner's

Company is to be blacklisted duly considering the law laid down by the

8 (2022) 4 SCC 393

PK, J

Hon'ble Supreme Court in Panda Infra Projects (India) Private

Limited (referred supra) as well as the gravity of lapses on the part of

the petitioner. The entire exercise shall be completed within a period of

four weeks from the date of receipt of a copy of this order.

18) Accordingly, the Writ Petition is allowed in part.

Miscellaneous applications, if any, pending in this writ petition,

shall stand closed. No costs.

___________________________ PULLA KARTHIK, J Date : 01.05.2025.

sur Issue C.C. by 03.05.2025

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter