Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Ira Square Township Llp vs Sri Amir Shareef
2025 Latest Caselaw 3287 Tel

Citation : 2025 Latest Caselaw 3287 Tel
Judgement Date : 21 March, 2025

Telangana High Court

M/S. Ira Square Township Llp vs Sri Amir Shareef on 21 March, 2025

Author: P.Sam Koshy
Bench: P.Sam Koshy
             THE HON'BLE SRI JUSTICE P.SAM KOSHY
                                      AND
 THE HON'BLE SRI JUSTICE NAMAVARAPU RAJESHWAR RAO

         CIVIL MISCELLANEOUS APPEAL No.318 of 2024


JUDGMENT:

(per the Hon'ble Sri Justice P.Sam Koshy)

The instant is an appeal filed under Section 39 of the

Arbitration and Conciliation Act, 1996 (for short, 'the Act')

assailing the order dated 11.01.2024, in Arb.O.P.No.184 of 2022,

passed by the XI Additional Chief Judge, City Civil Courts,

Hyderabad.

2. Heard Mr. Dama Seshadri Naidu, learned Senior Counsel

representing Ms. Madhavi Priya Mantena, learned counsel for the

appellants, and Mr. A. Venkatesh, learned Senior Counsel

representing Mr. G. Kalyan Chakravarthy, learned counsel for the

respondents.

3. Vide the impugned order, the Trial Court allowed the

petition filed under Section 9 of the Act by granting an ad-

interim injunction in favour of respondent Nos.1 to 4 herein, who

are the petitioners before the Trial Court, and had passed the

order restraining the appellants and respondent Nos.5 to 7

herein from alienating the property covered under Memorandum

of Understanding (for short, 'MoU') dated 08.09.2021 and also

the property covered under Development Agreement-cum-

General Power of Attorney (for short, 'DAGPA') dated 03.12.2021

i.e. schedule 'A' property and further interfering with the

possession of respondent Nos.1 to 4 herein over the schedule 'B'

property.

4. The facts which led to filing of the instant appeal are that

the respondent Nos.1 to 3 herein are the owners of the land

admeasuring Ac.0.39 guntas in Survey No.64/A/E out of Acs.4-

00 guntas in Survey No.61. So also Ac.0.39 guntas in Survey

No.64/A/E out of Acs.4-00 guntas in Survey No.61/AA/2, total

admeasuring Ac.1.08 guntas out of Acs.4-00 guntas in Survey

No.61 and the land admeasuring Ac.0.36 guntas in Survey

No.61/U/2 and Ac.0.37 guntas in Survey No.61/UU/1 out of

Acs.4-00 guntas in Survey No.61; all of which situates at

Kongarkalan Village, Imbrahimpatnam Mandal, Ranga Reddy

District.

5. All the aforesaid properties were purchased by the

respondent Nos.1 to 3 herein respectively vide registered sale

deeds separately executed on 25.07.2019. The respondent No.4

herein Mr. Syed Usman was the vendor of the property sold to

the respondent Nos.1 to 3. The said sale deeds executed on

25.07.2019 have gone unchallenged till date. Meanwhile, the

respondent Nos.1 to 4 entered into a MoU on 08.09.2021 with

appellant No.1. As per the said MoU, the appellant No.1

(respondent No.1 before the Trial Court) had agreed for payment

of ₹8,50,00,000/- as full and final consideration for surrender

and title over the land purchased by the respondent Nos.1 to 3

vide registered sale deeds dated 25.07.2019, those which are

reflected in the preceding paragraphs.

6. It was agreed that as part consideration of the transaction,

the appellant No.1 would pay an amount of ₹2,50,00,000/-by

way of cheque and cash to the respondent Nos.1 to 3 herein,

who in turn, have agreed to handover the possession of the

property and relinquish their claims and rights over the said

property. It was further agreed between the parties that they

shall pay the balance ₹6,00,00,000/- as agreed in terms of the

MoU on the date of the execution of DAGPA. However, even

before the MoU could be finalized, the appellant No.1 and

respondent Nos.5 to 7 herein entered into a DAGPA on

03.12.2021 entrusting the aforementioned subject land to be

developed by constructing residential villas with a recreation

facility center. The DAGPA was executed without fulfilling the

further consideration that was to be paid by appellant No.1 to

respondent Nos.1 to 4 and the appellant No.1 and respondent

Nos.5 to 7 were planning to raise constructions on the said

subject land. It was in this context that a petition under Section

9 of the Act was filed by respondent Nos.1 to 4 for an injunction

against the appellant No.1 and respondent Nos.5 to 7 herein and

also restraint from alienating the property covered under the

MoU i.e. schedule 'A' property and also from interfering with the

possession of the respondent Nos.1 to 4 in respect of schedule

'B' property.

7. Subsequently, the Section 9 petition filed before the Trial

Court was registered as Arb.OP.No.184 of 2022. Notices were

issued and since there was no representation on behalf of the

appellants herein, the Trial Court proceeded to decide the

petition and allowed the same vide the impugned order dated

11.01.2024 restraining the appellants as also respondent Nos.5

to 7 herein from alienating the property covered under MoU

dated 08.09.2021 and also the property covered under the

DAGPA dated 03.12.2021 i.e. schedule 'A' property and also

restrained the aforesaid parties from interfering with the

possession of respondent Nos.1 to 3 herein over the suit

schedule property.

8. It is this order which has been challenged by the appellants

herein who are the respondent Nos.1 and 2 before the Trial

Court.

9. The grounds on which the present appeal has been filed is,

firstly the notices have not been effectively served upon the

appellants i.e. the addresses provided in the Section 9 petition

and the addresses in the notices issued were insufficient.

Secondly, the notices so issued are contrary to the provisions of

Section 9(2) of the Act.

10. It was the contention of the learned Senior Counsel for the

appellants that the notices which were issued to the appellants

have not been effectively served can also be established from

the fact that there was a clear infraction of all the procedures so

prescribed under Order V Rules 17, 18, 19 and 20 of the Civil

Procedure Code, 1908 (for short, the 'CPC'). It was the further

contention of the learned Senior Counsel for the appellants that a

plain reading of the impugned order would show that the Trial

Court has not given any reasons which led to passing of the

interim injunction order. According to the learned Senior Counsel

for the appellants, the entire impugned order is only a narration

of facts and is abruptly passing of the interim injunction order

without discussing the principles which are required to be fulfilled

before an order of injunction is passed. It is by now well settled

that while granting an order of injunction the concerned Court

has to mandatorily consider the prima facie establishment of a

case, the balance of convenience and the irreparable loss caused

in the event if injunction order is passed. The impugned order

lacks these basic ingredients required while allowing the

injunction petition, and for the said reason also the same

deserves to be set aside / quashed.

11. The learned Senior Counsel for the appellants has also

challenged the impugned order on the ground highlighting the

conduct of the appellants inasmuch as the appellants earlier have

filed a writ petition i.e. W.P.No.2164 of 2020 before the High

Court challenging the action on the part of the Tahasildar /

respondent No.2 in the writ petition so far as mutating the

names of the third parties by removing the names of the

petitioners from the revenue records. The learned Single Judge

initially vide order dated 21.06.2023 disposed of the writ petition

directing respondent Nos.1 and 2 i.e. the State of Telangana as

also the Tahasildar, Imbrahimpatnam, to implement the

proceedings issued by the Tahasildar vide order dated

25.04.2019 within a period of four (04) weeks from the date of

receipt of a copy of the order. Subsequently, a Review Petition

was filed i.e. Review I.A.No.1 of 2024 in W.P.No.2164 of 2020.

The said I.A. came up for hearing on 16.04.2024 and the learned

Singh Judge after hearing the parties, directed the respondents

to maintain status quo in all aspects so far as the suit schedule

property is concerned, and also so far as the interference of the

possession over schedule 'B' property is concerned. In the teeth

of all such developments, there could not have been yet another

arbitration proceedings initiated by the respondent Nos.1 to 4

herein.

12. Thus, for all the aforesaid grounds and reasons, the

learned Senior Counsel for the appellants contended that the

order of interim injunction granted by the Trial Court deserves to

be vacated and the appellants be granted liberty to proceed with

the developments on the suit schedule property in accordance

with the MoU as also in accordance with the DAGPA.

13. Per contra, the learned Senior Counsel for the respondents

contended that it is a case where admittedly an MoU was entered

into between the parties on 08.09.2021 and in the MoU itself the

details of the transaction as consideration for transfer of the

property and the rights over the said property was reflected.

However, except for signing amount of ₹.2,50,00,000/- that was

to be paid was made, thereafter there has been no further

payment made by the appellants towards the balance of

payment agreed upon. Meanwhile, according to the respondents,

the appellants further entered into a DAGPA, and in terms of

DAGPA, the appellants started the development activities at the

suit schedule property much to the detriment of the respondents

entitlement of the consideration agreed upon as per the MoU. It

was in this context that the respondents in addition to moving a

petition under Section 11(6) of the Act before the High Court for

appointment of an Arbitrator, also moved a petition under

Section 9 of the Act before the Trial Court seeking for an interim

injunction atleast till the arbitration proceedings conclude.

14. During the course of arguments, the learned Senior

Counsel for the respondents informed the Court that the High

Court has already allowed the Section 11(6) petition and an

Arbitrator has also been appointed and the arbitration

proceedings have already been commenced between the parties.

Thus, according to the learned Senior Counsel for the

respondents, now that the arbitration proceedings have

commenced, let the Arbitrator itself conclude the proceedings

and pass the Award at the earliest which would be in the interest

of all the parties, rather than considering vacating of the interim

injunction at this juncture which may put the respondents in an

disadvantageous position.

15. However, the learned Senior Counsel for the appellants

contended that since they are into the business of development

of the suit schedule property, huge amounts of money has been

taken as loan from the Bank and they have to pay monthly EMIs

along with high rate of interest. Now that the arbitration

proceedings have commenced, let the Arbitrator take a call in

respect of the entitlement of the respondents and the Award

would be binding upon the parties. Till then, let the

developments on the suit schedule property be not stalled, as

that would put the appellants to a substantial financial burden

and the cost of the development work would get substantially

increased in due course of time unless it is executed at the

earliest.

16. Having heard the learned counsel for the parties and on

perusal of records, some of the admitted factual matrix of the

case are that respondent Nos.1 to 3 being the actual owners of

the property which they had purchased from respondent No.4.

The other admitted position is that of the execution of MoU on

08.09.2021 between the respondent Nos.1 to 4 on one side and

the appellants herein on the other side. There is also no dispute

so far as the initial payment of ₹2,50,00,000/- by the appellants

to respondent Nos.1 to 3 as the signing amount at the time of

signing of the MoU. However, there is no prima facie strong

material to show the payment of the balance of amount by the

appellants in terms of the MoU.

17. Clauses 6 and 12 of the MoU entered into between the

parties, reads as under, viz.,

"6. That the parties also agree and undertake that payment of consideration is a pre-condition for giving effect to all the covenants contained in this Memorandum of Understanding and the Development Agreement cum General Power of Attorney. In case of failure to honour any of the cheques above mentioned, the money already paid

shall be forfeited and the parties of the First Part shall be entitled to seek cancellation of the Development Agreement cum General Power of Attorney.

12. In case of any dispute arising out of or in connection with this agreement shall be dealt with by way of arbitration. The place, seat and venue of arbitration shall be at Hyderabad. The courts at Hyderabad shall have exclusive jurisdiction. The language of arbitration shall be English. The proceedings of arbitration shall be governed by the provisions of The Arbitrator and Conciliation Act, 1996 along with any other statutory amendments already made or to be made. The decision of the arbitrator shall be final and binding on the parties."

A plain reading of clause 6, would go to show that there

was some pre-condition already narrated in the MoU, which

otherwise becomes binding upon the parties. Likewise,in clause

12 there is a specific provision for redressal of disputes by way of

arbitration.

18. Admittedly there seems to be some disputes between the

appellants as also the respondent Nos.1 to 3 herein so far as the

payment of the balance of amount for relinquishing their rights

over the subject land in dispute. Further, respondent Nos.1 to 4

having resorted the provision of MoU for redressal of their

disputes invoking the arbitration clause is also an admitted

position. The request for appointment of an Arbitrator stands

allowed by the High Court and the Arbitrator has been appointed

and who has now seized of the proceedings. There is also no

quarrel so far as respondent Nos.1 to 4 having approached the

Trial Court for interim protection invoking Section 16 of the Act.

The said Section 9 proceedings were initiated way back in the

year 2022 i.e. three years back and the said Section 9 petition

stood allowed as early as on 11.06.2024. While allowing the

Section 9 petition, the Trial Court made the following

observations, which for ready reference is reproduced hereunder,

viz.,

"...On the other hand petitioners filed the relevant documents to establish their case. Since the respondents remained exparte an adverse inference can be drawn against them that the plea of petitioners is correct. If the respondents continued with the development work, pending disposal of writ petition filed by the petitioners, it will cause huge loss to the petitioners. More over the consideration amount which was admitted by the respondent No.1 and 2 was not paid to the petitioners according to petitioners. Prima facie case, and balance of convenience is in favour of petitioners. If injunction is not granted the petitioners will sustain loss. In these circumstances this court feels it is just an proper to grant ad interim injunction against the respondent from alienating the property covered under Memorandum of understanding, I.e 'A' and 'B' schedule property, and also

from interfering with the possession of petitioners in respect of 'B' schedule property.

In the result this petition is allowed restraining the respondents 1 to 5 by way of ad-interim injunction from alienating the property covered under MOU dt 8-9-21 and also the property covered under DAGPA dt: 3-12-21 vide doc No.2256/2022 I.e 'A' schedule property, and the respondents further restrained from interfering with the possession of the petitioners over the 'B' schedule property."

The said interim protection under Section 9 of the Act is

still in operation for almost over fourteen months. Meanwhile,

the arbitration proceedings itself is progressing before the

Arbitrator.

19. In the said admitted factual matrix, what is to be

appreciated at this juncture is, should the interim order granted

by the Trial Court in the Section 9 petitionwarrants interference?

20. One cannot brush aside the fact that in the event if the

interim protection is not continued, the appellants would

continue with the construction, carry out the sale of all the

properties and subsequently, if the arbitration case stands

decided in favour of the respondents, they would find it difficult

to reap the fruits of the award so passed. At the same time, we

are also conscious of the fact that continuation of the interim

protection would stall the entire development and construction

activities, which would result in the project getting delayed and

the parties, particularly the appellants being put to unnecessary

financial burden of paying EMIs and interest for the protracted

period.

21. In the said circumstances, what is striking the conscious of

this Bench is to strike a balance so that the interest of both the

parties stands protected. In terms of the MoU, the balance of

amount payable by the appellants to respondent Nos.1 to 4 was

₹6,00,00,000/-. Now in case if the interim protection is

continued, the appellants will be put to substantial loss

financially as that could delay the project incurring financial

implications. In case, the interim stay is vacated, the respondent

Nos.1 to 4 would be put to considerable detriment upon the

appellants alienating the suit schedule property and receiving

sale consideration upon each alienation. Therefore, in the opinion

of this Bench and in the larger interests of justice, it would be

appropriate if the interim stay so far as restraint from alienating

the suit schedule property is ordered to be vacated subject to the

appellants providing solvent security to the satisfaction of the XI

Additional Chief Judge, City Civil Courts, Hyderabad, for an

amount of ₹6,00,00,000/- and permitting the appellants herein

to carry out the development activities.

22. Accordingly, with the aforesaid observation and direction,

the instant Civil Miscellaneous Appeal stands partly allowed.

23. As a sequel, miscellaneous applications pending if any,

shall stand closed. However, there shall be no order as to costs.

_____________ P.SAM KOSHY, J

___________________________ NAMAVARAPU RAJESHWAR RAO, J

Date: 21 .03.2025 GSD

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter