Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Abdul Rahman vs The State Of Telangana
2025 Latest Caselaw 2744 Tel

Citation : 2025 Latest Caselaw 2744 Tel
Judgement Date : 4 March, 2025

Telangana High Court

Abdul Rahman vs The State Of Telangana on 4 March, 2025

Author: K. Lakshman
Bench: K. Lakshman
      THE HONOURABLE SRI JUSTICE K. LAKSHMAN

              WRIT PETITION No.6411 OF 2025

ORDER:

Heard Smt. Thakur Roopa Singh, learned counsel for

the petitioner, Sri G.Madhusudhan Reddy, learned Standing

Counsel appearing for respondent Nos.2 to 4 and learned

Assistant Government Pleader for Assignment for 5th

respondent.

2. Petitioner herein is claiming that he is the

absolute owner and possessor of Plot No.817-B admeasuring

200 square yards in Survey No.202, situated at Kondapur

Village, Serilingampally Mandal, Ranga Reddy District on the

strength of a registered Sale Deed bearing Document

No.15229 of 2023 dated 27.09.2023. He has obtained

building permit order dated 31.12.2024 for construction of

Stilt for parking + 2 upper floors. Petitioner has not

commenced construction. In the meanwhile, 3rd respondent

has issued show cause notice dated 29.01.2025 stating as

follows:

"The Provisional permission obtained for construction of individual Residential Building vide reference 1st cited, has been examined in detail by the Post Verification team as per the rules and regulations in force. It is noticed that it has been obtained by suppressing the material facts and by misrepresentation of documents facts as stated below:

"As per the scrutiny and inspection report of TPS & ACP- 20, Sri ABDUL RAHMAN, submitted proposals the construction of residential building consist of 1 stilt + 2 upper floors over the Plot No: PLOT BEARING NO:817-B, Locality: KONDAPUR, Survey No: 202, Kondapur(V), Serilingampally Circle 20, Serilingampally Zone, Serilingampally(M), GHMC, Rangareddy (Dist). Inspected the site, verified the submitted documents and observed that, the survey numbers 202 are covered under prohibited properties as CEILING SURPLUS LAND. Prior NOC is required from the concerned authorities for issue of building permission. The applicant has not submitted any document with regard to the regularization of said plot from the ULC authorities, In this regard, a show cause notice may be issued to the applicant with a direction to show cause as to why the provisional permission obtained by self-certification should not be revoked within 7 days, otherwise the same will be cancelled without any further notice.\n\n"

Hence you are hereby directed to show cause in writing as to why the provisional permission obtained by you shouldn't be revoked for the reasons stated as above. Your explanation should be submitted within 7 days from the date of receipt of this notice, failing which the provisional permission granted will be revoked without further notice."

3. 3rd respondent directed the petitioner to submit

explanation within seven days. When petitioner went to office

of 3rd respondent to explain the same orally, he refused to

hear the same. Thus, according to the petitioner, he has

submitted explanation orally. Without considering the same,

3rd respondent has issued revocation letter dated 20.02.2025

revoking the aforesaid building permit order. Challenging the

same, petitioner filed the present writ petition.

4. Whereas Sri G.Madhusudhan Reddy, learned

Standing Counsel appearing for respondent Nos.2 to 4, on

instructions, would submit that 3rd respondent has issued

show cause notice dated 29.01.2025 with the aforesaid

allegations and despite granting seven days time, petitioner

herein failed to submit explanation. Therefore, 3rd respondent

has revoked the building permit order dated 31.12.2024 vide

revocation letter dated 20.02.2025. There is no error in it.

Perusal of revocation letter would reveal that there is no

reference to the show cause notice dated 29.01.2025.

5. As discussed supra, the building permit order is

dated 31.12.2024. Petitioner obtained the said building

permit order under Telangana State Building Permission

Approval and Self Certification System (TS-bPASS) Act, 2020

by uploading all relevant documents by way of

self-certification and self-declaration. Thereafter within 21

days, 3rd respondent has to conduct post-verification and

issue work commencement letter. Otherwise it amounts to

deemed permission in terms of Section 7(10) of Telangana

State Building Permission Approval and Self Certification

System (TS-bPASS) Act, 2020 and Rule 12(vii) of TS-bPASS

Rules, 2020. Even then, 3rd respondent has issued revocation

letter dated 20.02.2025. Petitioner failed to obtain work

commencement letter pursuant to building permit order dated

31.12.2024.

6. 3rd respondent has to consider prima facie title and

prima facie possession of the petitioner over the subject

property. He cannot revoke the building permit order dated

31.12.2024 on the ground that petitioner has not submitted

NOC from the concerned authorities and he has not filed

regularization proceedings. This Court vide order dated

26.04.2022 in W.P.No.16868 of 2022 considered the said

aspects and directed the Municipality not to insist for NOC

from the Revenue Department. This Court also placed

reliance on principle laid down in judgment in Hyderabad

Potteries Private Limited v. Collector, Hyderabad

District 1. Feeling aggrieved by the said order, GHMC

preferred an appeal vide W.A.No.403 of 2022. The said

appeal was dismissed vide judgment dated 05.07.2022. In

fact, petitioner has to bring the said facts to the notice of 3rd

respondent by submitting written explanation. Petitioner

cannot contend that he has submitted explanation orally.

7. As discussed supra, there is no reference to the

show cause notice in the revocation letter dated 20.02.2025.

The same is in violation of principles of natural justice and

procedure laid down under Telangana State Building

Permission Approval and Self Certification System (TS-bPASS)

Act, 2020.

8. It is relevant to note that 3rd respondent, being

Deputy Commissioner, GHMC has no power, authority or

jurisdiction to revoke the building permission and it is 2nd

respondent Commissioner, GHMC, who is having power to

1 2001(3) ALD 600

revoke the building permission. Therefore, 2nd respondent

has to initiate action afresh for revocation of building

permission issued in favour of petitioner.

9. Therefore, without going into the merits and

demerits of the case, only on the said ground, the impugned

revocation letter dated 20.02.2025 is set aside. Matter is

remanded back to 2nd respondent with a direction to initiate

fresh action, serve fresh show cause notice on the petitioner

granting seven (07) days time to petitioner. On receipt of the

said show cause notice, petitioner shall submit explanation

along with copy of order dated 26.04.2022 in W.P.No.16868 of

2022 and judgment dated 05.07.2022 in W.A.No.403 of 2022

within seven (07) days. Thereafter, 2nd respondent shall pass

orders on consideration of the aforesaid aspects within four

(04) weeks. Till then, petitioner shall not proceed with the

construction. Subject to the result of the said enquiry, on

obtaining work commencement letter, petitioner shall proceed

with the construction strictly in accordance with the aforesaid

building permit order and work commencement order, failing

which liberty is granted to respondent Nos.2 and 3 to take

action against the petitioner in accordance with the procedure

laid down under the Greater Hyderabad Municipal

Corporation Act, 1955.

9. Writ Petition is accordingly disposed of. There

shall be no order as to costs.

Miscellaneous petitions pending, if any, shall stand

closed.

__________________ K. LAKSHMAN, J Date: 04.03.2025 KL

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter