Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mahalakshmi Profiles P Ltd vs The Transmission Corporation Of ...
2025 Latest Caselaw 1020 Tel

Citation : 2025 Latest Caselaw 1020 Tel
Judgement Date : 10 January, 2025

Telangana High Court

Mahalakshmi Profiles P Ltd vs The Transmission Corporation Of ... on 10 January, 2025

Author: Nagesh Bheemapaka
Bench: Nagesh Bheemapaka
         HON'BLE SRI JUSTICE NAGESH BHEEMAPAKA

               WRIT PETITION No. 13917 OF 2023

ORDER:

Petitioner is before this Court seeking a direction to

respondents to allow additional open access power of 15 MW.

2. Petitioner is H.T. category consumer of the 2nd

respondent DISCOM. During 2017, it is stated, when they

applied for availing open access power of 6.5 M.W. (6500 KVA),

the 2nd respondent refused permission on the ground of non-

availability of distribution network corridor. Petitioner

therefore, filed Writ Petition No. 25144 of 2017 which was

allowed by order dated 28.09.2018 directing respondents

therein to allow open access on the ground that reasons stated

for refusal are dubious. Respondents thereafter, preferred Writ

Appeal No. 80 of 2019 and the same was dismissed.

Consequently, petitioner was allowed to avail open access power

of 6.5 MW.

Thereafter, CMD of petitioner was enhanced to 16.5

MW by 01.04.2022. Petitioner therefore, by letters dated

18.07.2022 and 04.08.2022 requested respondents to permit

open access of 16.5 M.W. Thereupon, the Chief Engineer, Rural

Zone, by letter dated 10.08.2022 directed petitioner to deposit

Rs.2,18,30,000/- for development of 132 KV independent line

from Manoharabad Sub-station to petitioner's factory and they

complied with the said direction even and the Superintendent

Engineer submitted report on 21.03.2023. In the meanwhile,

petitioner CMD was enhanced to 21.5 MW. and applied to

Respondents for issuance of no objection for availing additional

15 MW., making a total of 21.5 M.W., however respondents have

not issued no objection.

3. Learned counsel for petitioner Sri Erigi Ganesh

submits that respondents cannot deny open access and it is the

statutory right of petitioner under Sections 42 and 43 of the

Electricity Act (for short, 'the Act'). To support his contention, he

relied on the judgment of the Hon'ble Supreme Court in

Brihanmumbai Electric Supply and Transport Undertaking

v. Maharashtra Electricity Regulatory Commission (MERC) 1.

4. The case of TSSPDCL, as stated by the Chief

General Manager (IPC), is that petitioner enhanced its CMD

from 6.5 to 21.5 MW in 2022 and upgraded its voltage level from

33 KV to 132 KV. It is stated, respondents have been issuing

(2015) 2 SCC 438

NOC to petitioner for OA capacity of 6.5 MW amid saturated grid

constrains as per direction of this Court in Writ Petition No.

25144 of 2017. They chose to avail open access power for

higher OA capacity and if permitted, it will cause huge impact

on the schedules of the respondent company and affect the grid

stability. The argument of learned Standing counsel for

TSSPDCL Sri R. Vinod Reddy is that respondent company is

also to generate funds to subsidize economically-weaker

sections of society, farmers, etcetera. In the present case, the

entire grid capacity was allotted to various consumers and there

is no corridor available to accept the request of petitioner for

additional open access over and above 6.5 MW. According to

learned Standing Counsel, availing of supply through open

access with short intervals and higher OA capacity throughout a

day would further load the network resulting in congestion of

the existing network, in view of the same, petitioner was

informed vide letter dated 02.09.2022 that enhancement of OA

capacity cannot be considered. It is also submitted that this

respondent company with an intention to provide 24 hours

supply to all its consumers, has been purchasing power from

Power Exchanges in which rate is very uncertain and depends

upon the external factors such as availability of power and

demand across the nation and they are under obligation to

supply uninterrupted power to all consumers and utilise the

grid judiciously to accommodate them.

5. Having gone through the provisions of the

Electricity Act, particularly a conjoint reading of Sections 42

and 43 of the Act along with the objectives and purposes for

which it was enacted, it becomes clear that when an Application

is made by a consumer to a distribution licensee for supply of

electricity, such a distribution licensee can request other

distribution licensee in the area to provide its network to make

available for wheeling electricity to such consumers and this

open access is to be given as per the provisions of Section 42(3).

However, TSSPDCL vide letter dated 02.09.2022 informed that

enhancement of OA capacity could not be considered as availing

of supply through open access with short intervals and higher

OA capacity throughout a day would further load the network

resulting in congestion of existing network.

6. Admittedly, petitioner was allowed OA capacity of

6.5 MW in 2017 and thereafter it was enhanced to 16.5 MW in

2022 and 21.5 MW. Though, as contended by the learned

counsel, it shall be the duty of distribution licensee to develop

and maintain an efficient distribution system and further

Section 42 (3) of the Electricity Act casts a duty upon the

distribution licensee to provide Open Access to the consumers,

in this regard, the case of TSSPDCL is that distribution corridor

is getting overloaded due to various schemes of Government of

Telangana to provide 24 hours power supply to all the services

including agricultural services from January 2018 onwards and

to abide by the policy of the State Government, TSDISCOMS

have to make necessary arrangements for adequate power

procurement from various sources for which rate is very

uncertain and depends upon the external factors such as

availability and demand. Apart from that, petitioner has been

availing supply from respondent when power prices at exchange

are at higher rate than the distribution companies' tariffs.

7. In view of the specific contentions of learned

Standing Counsel, this Court is of the view that if petitioner is

permitted to upgrade the OA capacity, it will further burden the

network resulting in congestion of the existing network. The

Writ Petition does not merit consideration and the same is liable

to be dismissed.

8. The Writ Petition is accordingly, dismissed. No

costs.

9. Miscellaneous Applications, if any shall stand

closed.

-------------------------------------

NAGESH BHEEMAPAKA, J

08th January 2025

ksld

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter