Citation : 2025 Latest Caselaw 4916 Tel
Judgement Date : 17 April, 2025
THE HONOURABLE SMT. JUSTICE K. SUJANA
APPEAL SUIT No.913 of 1999
JUDGMENT:
Challenging the order dated 07.12.1998 passed in
O.S.No.13 of 1992 by the learned Senior Civil Judge, Asifabad,
the present appeal suit is filed.
2. The brief facts of the case are that the plaintiff is a coal
transport contractor for the defendant company under a
contract from July 1991 to July 1993. He owns a tipper
vehicle bearing No.AEK-2298 which was damaged on
November 19/20, 1991, when a coal bunker unexpectedly fell
on it while stationed under the bunker for coal loading. The
plaintiff reported the incident to the defendant, and both
parties assessed the damages. The plaintiff claims that the
defendant neither repaired the vehicle nor compensated him
for waiting charges, which caused a daily loss of Rs.1,500/-
from November 19, 1991, until repairs were completed on
December 27, 1991. The plaintiff spent Rs.1,67,219/- on
repairs and sustained additional losses due to waiting charges
of Rs.55,500 for 37 days. He sold damaged parts as scrap for
SKS,J
Rs.5,000 and is now claiming a total amount of Rs.2,17,719/-
from the defendant.
3. However, the defendant acknowledges the plaintiff's
contractor status and ownership of the vehicle but denies
responsibility for the accident. They claim the coal bunker fell
accidentally and the damage was assessed at Rs.40,000/-.
The defendant offered to repair the vehicle at its workshop,
but the plaintiff refused and chose to repair it himself. The
defendant disputes the repair cost claimed by the plaintiff and
denies any obligation to pay waiting charges. He argued that
the plaintiff's claim is excessive and that, per the contract
agreement, the defendant is not liable for accidents beyond its
control. The defendant asserts that the plaintiff should seek
compensation from his insurance company and requests the
dismissal of the suit.
4. Basing on the above pleadings, the trial Court framed
two issues and on behalf of the plaintiffs i.e., PWs.1 and 2
were examined and Ex.A1 to A27 are marked. DWs.1 and 2
are examined and Exs.B1 to B7 were marked on behalf of the
defendants.
SKS,J
5. After examining the evidence, the trial Court, vide order
dated 07.12.1998, partly allowed the suit holding that the
damage caused to the plaintiff's vehicle was a direct
consequence of the defendant company's negligence in
maintaining the bunker on its premises. Relying on exhibits
such as Ex. A-2, A-25 to A-27 and joint inspection reports, the
trial Court concluded that the damage was not remote but
arose during the discharge of contractual obligations. It was
observed that the defendant did not fail to respond to multiple
notices sent by the plaintiff, nor did it protest the quotations
issued for repairs. The oral offer to get the vehicle repaired or
pay Rs.40,000/- was unsubstantiated by written
communication and was therefore considered insufficient to
refute the plaintiff's claim.
6. Further, the trial Court accepted the claim of the
plaintiff of Rs.1,67,219/- towards actual repairs, supported by
a series of bills (Ex. A-7 to Ex. A-22), as genuine and
unrebutted. Waiting charges for 37 days were also awarded at
Rs.1,200/- per day, amounting to Rs.44,400/-, based on
prevailing transportation rates. After deducting Rs.5,000/-
realized from selling damaged parts, the trial Court held the
SKS,J
plaintiff entitled to Rs.2,06,619/- as total damages. Interest
at 12% p.a. from the date of the suit till realization was also
granted, considering the silence of the defendant and failure
to challenge the claim. Aggrieved by the said judgment, the
appellant/defendant preferred the present appeal suit.
7. Heard Sri P. Sri Harsha Reddy, learned Standing
Counsel for Singareni Collieries Co. Ltd., appearing on behalf
of the appellant as well as Sri L. Harish, learned counsel
appearing on behalf of the respondent.
8. Learned counsel for the appellant submitted that the
judgment and decree passed by the trial Court is contrary to
law, based on a wrong reading of the evidence, and ignores the
actual terms of the contract between the parties and that the
contract does not mention payment of any compensation or
damages in case of an accident. The vehicle involved was
insured, and the insurance company was not made a party to
the suit, making the suit defective. The accident was not
intentional or due to negligence but purely accidental and
beyond the control of the appellant. He further submitted that
according to Clause 14 of the agreement, the appellant is not
SKS,J
liable for any loss or damage caused due to factors beyond its
control.
9. Learned counsel for the appellant argued that both
parties had mutually agreed during a joint inspection to settle
the matter by paying Rs.40,000/-. Despite this, the trial
Court awarded a much higher amount, which goes against the
agreement. There is no proper evidence to show that the
bunker was in bad condition or that the appellant was
negligent. In fact, the respondent did not check the condition
of the bunker before using it, which any responsible person
should have done. Both parties believed the bunker was in
working condition, so blaming the appellant alone is
unjustified. He contended that the claim for waiting charges
is baseless as the contract does not provide for any such
payment. The repair bills produced by the respondent are
inflated, not supported by proper evidence, and were wrongly
accepted by the trial Court. The trial Court shifted the burden
of proof to the Appellant and assumed negligence without any
solid proof. The appellant had even offered to repair the
vehicle out of goodwill, which was not an admission of fault or
liability. The learned Judge misread the intention behind this
SKS,J
offer and wrongly concluded that the Appellant had a role in
causing the accident.
10. He further contended that the trial Court relied on
unrelated judgments and misapplied the law under Section 73
of the Contract Act. The trail Court also wrongly excluded the
appellant's documents and accepted exaggerated credit bills
from the respondent without proper verification. The award of
Rs.2,06,619/- with interest at 12% and costs is not justified
in light of the contract terms, especially Clause 14. Therefore,
he prayed the Court to set aside the judgment of the trial
Court by allowing this appeal suit.
11. On the other hand, learned counsel for the respondent
submitted that the appellant himself admitted that a joint
inspection was conducted and that the respondent agreed to
accept Rs.40,000/- towards damages. When there was no
negligence on the part of the appellant, there would be no
reason to offer Rs.40,000/- as compensation. On the one
hand, he admitted his negligence by offering Rs.40,000/-, and
on the other hand, he claims that the negligence lies with the
respondent. He cannot take such a contradictory stand. With
regard to negligence, the trial Court elaborately discussed the
SKS,J
documents filed by the plaintiff and also examined the
concerned witness, P.W.2 - professional mechanic, who
deposed about the damage to the vehicle, the repairs carried
out, and the accident involving the said vehicle. Based on the
evidence and the documents filed by the respondent, the trial
Court rightly delivered its judgment. There is no illegality in
the judgment of the trial Court, and hence, the learned
counsel prayed for dismissal of the appeal suit.
12. The points that arise for consideration in this appeal
are:
i. Whether the respondent/plaintiff is entitled to damages to the tune of Rs.2, 11,619/-?
ii. Whether the appellant is liable to pay the said compensation?
iii. Whether the judgment of the trial Court warrants any interference?
Point Nos.i and ii:
13. In light of the submissions made by both the learned
counsel and upon perusal of the material available on record,
it is the case of the plaintiff that he entered into a contract
with the Defendant-Company for transportation of coal. In
pursuance of the said contract, the plaintiff deposited an
SKS,J
amount of Rs.25,000/- with the Defendant-Company and
commenced transportation work. On the alleged date of the
incident, while the plaintiff's tipper was stationed under the
bunker at SRP-2 incline for loading coal, the coal bunker
suddenly collapsed, causing substantial damage to the tipper.
14. There is no dispute regarding the collapse of the coal
bunker and the resultant damage to the plaintiff's vehicle.
The appellant/defendant has admitted the said incident. The
primary contention raised by the appellant is that, in view of
Clause 14 of the agreement, the company is not liable for any
compensation. A perusal of Clause 14 reveals that the
company shall not be liable for compensation in the event of
losses suffered by the contractor due to reasons such as
strike, lock-out, shortage of labour, fire, breakdown or road
accidents, riots, war, insurrection, restraints imposed by
Governmental Acts or Legislation, or any other causes beyond
the control of the company.
15. However, none of the contingencies enumerated in
Clause 14 are applicable to the present case. The collapse of
the bunker, which was under the control of the Appellant-
Company, cannot be said to be a circumstance beyond the
SKS,J
control of the company. Thus, the protection under Clause 14
does not extend to the facts of this case.
16. Furthermore, the appellant, in both the written
statement and the grounds of appeal, categorically admitted
that he offered to repair the vehicle and even proposed
payment of Rs.40,000/- towards damages after receiving legal
notice from the respondent/plaintiff. This itself is an
indication of implied admission of negligence on part of the
appellant.
17. The contention of the learned counsel for the appellant
that the respondent should have claimed compensation from
the insurance company is also without merit. The learned
counsel for the respondent rightly pointed out that the
incident did not constitute a road accident, and therefore, the
insurance company was not liable to pay damages. When the
negligence is attributable to the Company, the respondent is
not bound to proceed against the insurer. Thus, the
appellant's contention on this aspect is liable to be rejected.
18. With regard to the quantum of damages awarded by the
trial Court, the appellant contended that the amount is
SKS,J
exorbitant. However, the respondent/plaintiff produced
documentary evidence under Exhibits A1 to A27, including
repair bills under Exhibits A7 to A22, amounting to
Rs.1,71,000/-. To substantiate the said bills, the respondent
examined P.W.2, a professional mechanic, who corroborated
the extent of damage and the repair work undertaken. Nothing
substantial was elicited during the cross-examination of P.W.2
to discredit his testimony. Therefore, the trial Court rightly
concluded that the respondent/plaintiff spent an amount of
Rs.1,67,270/- towards repairs and mechanic charges.
19. The trial Court also awarded waiting charges at the rate
of Rs.1,200/- per day, based on prevailing market rates, for a
total of 37 days. The said claim is supported by the evidence
on record, and there appears to be no illegality in awarding
such damages.
20. However, with respect to the interest awarded, the trial
Court granted interest @ 12% per annum from the date of
filing of the suit till the date of realization. This needs
modification in light of Section 34 of the Code of Civil
Procedure, 1908 (for short 'CPC'), which reads as follows:
SKS,J
"Section 34 CPC - Interest
(1) Where and in so far as a decree is for the payment of money, the Court may, in the decree, order interest at such rate as the Court deems reasonable to be paid on the principal sum adjudged, from the date of the suit to the date of the decree, in addition to any interest adjudged on such principal sum for any period prior to the institution of the suit, 1 [with further interest at such rate not exceeding six per cent. per annum as the Court deems reasonable on such principal sum], from the date of the decree to the date of payment, or to such earlier date as the Court thinks fit :
2[Provided that where the liability in relation to the sum so adjudged had arisen out of a commercial transaction, the rate of such further interest may exceed six per cent. per annum, but shall not exceed the contractual rate of interest or where there is no contractual rate, the rate at which moneys are lent or advanced by nationalised banks in relation to commercial transactions.
Explanation I.--In this Sub-section, "nationalised bank" means a corresponding new bank as defined in the Banking Companies (Acquisition and Transfer of Undertakings) Act, 1970 (5 of 1970).
Explanation II.-- For the purposes of this section, a transaction is a commercial transaction, if it is connected with the industry, trade or business of the party incurring the liability.]
SKS,J
(2) Where such a decree is silent with respect to the payment of further interest 3[on such principal sum] from the date of the decree to the date of payment or other earlier date, the Court shall be deemed to have refused such interest, and a separate suit therefore shall not lie.
Correct the grammar and improve the sentences like the judgment of the Court and further insert section 34 of CPC in the judgment where it is relevant and improve the sentences with regard to section 34 of CPC."
21. In the present case, though the transaction is in the
nature of a commercial arrangement, no contractual rate of
interest has been established. Therefore, in the absence of a
specific contractual stipulation or evidence of prevailing
lending rates from nationalised banks, the interest rate must
be regulated within the permissible limits of Section 34 CPC.
22. Accordingly, the interest awarded by the trial Court is
modified to the following extent:
a) The respondent/plaintiff shall be entitled to
interest at the rate of 12% per annum from
the date of suit till the date of decree, as
adjudged by the trial Court.
SKS,J
b) However, from the date of the decree till the
date of realization, the interest shall be
limited to 6% per annum, in consonance with
the mandate of Section 34 CPC.
Point No.iii
23. In view of the above discussion, the appeal suit is liable
to be dismissed except to the extent of modification in the
interest component. The judgment and decree of the trial
Court are upheld, subject to the variation in interest as
indicated above.
24. In view thereof, this appeal suit is dismissed. There
shall be no order as to costs.
Miscellaneous applications, if any pending, shall stand
closed.
_______________ K. SUJANA, J Date: 17.04.2025 SAI
SKS,J
THE HONOURABLE SMT JUSTICE K. SUJANA
P.D. JUDGMENT
IN
Date: 17.04.2025
SAI
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!