Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Vinayak Steels Ltd., S.C.No. ... vs The Telangana State Electricity
2024 Latest Caselaw 4090 Tel

Citation : 2024 Latest Caselaw 4090 Tel
Judgement Date : 16 October, 2024

Telangana High Court

M/S. Vinayak Steels Ltd., S.C.No. ... vs The Telangana State Electricity on 16 October, 2024

Author: Nagesh Bheemapaka

Bench: Nagesh Bheemapaka

         HON'BLE SRI JUSTICE NAGESH BHEEMAPAKA

WRIT PETITIONS No. 32582, 19494 AND 26216 OF 2023

COMMON ORDER:

Petitioners in all these Writ Petitions is a private

limited company incorporated under the provisions of the

Companies Act, 1956. They question the action of Transmission

Corporation of Telangana Limited and Southern Power

Distribution Company Limited of Telangana State in not

granting clearance / no objection for availing open access for

the aggregate load of 42 MW, 16.5 MW and 45 MW respectively,

as the same is contrary to Section 42 of the Electricity Act, 2003

apart from being violative of Articles 14, 19(1)(g) and 21 of the

Constitution of India.

2. The case of petitioner in Writ Petition No. 32582 of

2023 is that they established an induction furnace unit which

engaged in manufacture of Mild Steel Ingots, after obtaining a

High Tension Power Supply Connection bearing No. RJN-773

from the 4th respondent; as on today, petitioner's contracted

Maximum Demand with the 4th respondent is 42,000 KVA (42

MWs.). Thereafter, petitioner acquired additional load and by

25.04.2003, its load capacity came to 42 MW. Soon after

petitioner acquired additional load, it has been applying for

open access permission for the capacity of 42 MW, however, the

Chief Engineer, SLDC - 3rd respondent is not granting

permission to avail open access in respect of power purchased

by petitioner through Indian Energy Exchange for a capacity of

42 MW. Without assigning any reason, the 3rd respondent has

been granting permission for 24.49 MW ignoring the fact that

capacity of petitioner approved by the 4th respondent is 42 MW

as on that day.

3. Petitioner in Writ Petition No. 19494 of 2023 states

that they established an industrial unit in Survey No. 97E of

Kothur Village, Shadnagar Mandal, Ranga Reddy District,

engaged in the manufacture of MS Rods, Sponge Iron and Mild

Steel Ingots, by obtaining two High-Tension Power supply

bearing Service Connection Nos. MBN-371 & MBN-710 from the

1st respondent, a licensee under the Electricity Act, 2003 (for

short, 'the Act'). Petitioner was originally availing power at 33

KV and presently, 132 KV voltage supply.

It is stated under Section 42(2) of the Act, it is

obligatory on the part of the Electricity Regulatory Commissions

of each State to see that open access is made available to all the

consumers of the electricity after five years of coming into force

of the Act. Petitioner has been availing open access power with a

load of 8.5 M.Ws. the open access corridor of the 4th respondent

controlled by the 9th respondent which is a Government of India

Company established to regulate the open access corridor of the

southern states of India. Apart from that, they have been

availing power with a capacity of 8 M.Ws. from the 8th

respondent which is a state-owned company. Accordingly, the

2nd respondent used to give standing clearance certificate for the

capacity of 16.5 M.Ws. and presently, the 8th respondent

stopped generation of power due to operational contingency as a

result of the same, petitioner is unable to avail any power from

the 8th respondent for the capacity of 8 M.Ws.

It is stated that ever since petitioner started availing

power from the 8th respondent, the 2nd respondent has been

issuing aggregate standing clearance certificate for the aggregate

load that is being availed from the inter-state supply made by

the private generating companies through Indian Energy

Exchange and the power supplied by the 8th respondent by

allowing petitioner to use open access corridor of the 4th

respondent for the capacity of 16.5 K.Ws. Recently, petitioner

applied for grant of clearance certificate for availment of 16.5

M.Ws. aggregate load, through Indian Energy Exchange;

curiously, the 2nd respondent declined to give the certificate,

stating that they will not give the same to the extent of power

that was being availed by petitioner from the 8th respondent

source. The 2nd respondent stated that they would not consider

petitioner's request due to congestion in grid as of now and his

case would be considered in future depending upon availability

of grid.

4. Petitioner in Writ Petition No. 26216 of 2023 is the

consumer of the 2nd respondent - DISCOM under HT Category

with a CMD of 45,000 KVA at present with service No.MDK-

1060. Initially, they have two service connections viz., MDK-

1060 with a CMD of 9990 KVA and MDK-1395 with a CMD of

9990 KVA. and the later service was merged with former and

obtained additional CMD of 4020 making a total CMD of 24000

KVA. The supply was being made through 132 KV dedicated

feeder from China Sankarampet Sub-station. While so, it is

stated, petitioner applied for availing power through open access

source by purchasing power from IEX for 24 MV, for which,

respondents issued no objection for the month of November-

2021 and from December-2021 on, they were allowing 17 MW

only. It is stated, thereafter, petitioner got its CMD enhanced to

45 MW by addition of 21 MW with effect from 29.12.2021 and

applied for 45 MW open access power, but respondents were

allowing only 17 MW open access. Therefore, petitioner applied

to the Chief Engineer SLDC on 15.06.2023 to grant 'No

Objection' as also to the Chief General Manager, IPC, TSSPDCL

on 17.06.2023. The Chief Engineer, SLDC gave reply dated

19.06.2023 stating that the subject has to be dealt with by

TSSPDCL with regard to CMD and technical feasibility.

TSSPDCL, however, has not chosen to give any reply.

Petitioner contends that consumer has a statutory

right to avail open access power and respondents have a

statutory obligation to permit the same. Due to liberalization of

Government Control Regime in 1992, electricity that was being

generated and transmitted by state-owned utilities was not at all

sufficient to meet the need of the hour and therefore, the

Central Government has introduced a rational development of

power through various sources which include both

conventional, non-conventional and renewable sources and

encouraged private sector to enter into power generation, but

there are difficulties for private generators to sell the power

generated by them as they can't erect and maintain the

distribution network. Taking into consideration all these

situations, Government in the 2003 Act made it obligatory on

the Central and State transmission utilities to transmit power

generated by private sector to the consumers. In that direction,

provisions are incorporated under Sections 38, 39, 40 and 42 of

the Act. Section 38 (2) (d) stipulates that central transmission

utility shall provide non-discriminatory open access to its

transmission system on payment of charges. To the same effect

Section 39 (2) (d) is applicable to State transmission utility.

Sections 40 and 42 of the Act further obligate the transmission

licensees to build, maintain and operate an efficient coordinated

inter-state or intra-state transmission systems. Therefore, it is

the statutory obligation of the transmission utilities to provide

open access and they can't avoid the said obligation by resorting

to some excuses that there is no transmission line or congestion

in the grid. Foreseeing such a situation, the Central Regulatory

Commission in its open access Regulations under Clause 6

stipulated to invite open bids and provide access in 45 days. It

is stated that consumer is not at the mercy of the either

TRANSCO or DISCOM. It is its statutory right to have access to

the distribution system.

It is stated that action of the respondents violates

the provisions of Section 42 of the Act and Regulation 2 of 2005

of the APERC which was adopted by TSERC vide Regulation 1 of

2014 and CERC (Open Access in interstate Transmission)

Regulation-2008 as amended in 2009. Section 42 (1) mandates

the Distribution Licensee to develop and maintain an efficient

co-ordinate and economical distribution system in its area of

supply. Sub-Section-2 mandates that State Commission shall

introduce open access in such phases within one year of the

appointed date by it. In compliance with the said direction in

sub-section-2, APERC issued Regulation 2 of 2005 notified on

01.07.2005 called 'Terms and Conditions of Open Access to

intra State Transmission and Distribution networks', which was

amended from time to time. CERC issued the Regulation stated

supra. Under Regulation 2 of 2005, open access users are

categorized as long-term open access users where requirement

of open access is two years and more; for long term open access,

State Transmission Utility (STU) constituted by the State

Government under Section 39 (1) of the Act is the Nodal Agency

and for short term open access transactions, the Nodal Agency

is the State Load Dispatch Centre (SLDC). It is stated that State

Load Dispatch Centre (SLDC) receive and process the

applications and grant NOC also after consulting Transmission

or Distribution Licensee whose networks would be used for such

transactions. Respondents are obligated by the above-stated

provisions to do all acts enabling petitioner to avail open access

power. The inaction on the part of the respondents is intentional

to deny the open access power to them.

5. In the counter filed in Writ Petition No. 26216 of

2023, the 4th respondent states that petitioner after merging the

two units and making total CMD of 45MW, submitted

Applications to avail NOC for whole 45MW. As per clause 5 of

Regulation 2 of 2005, Nodal agency for processing short term

open access transactions is TSSLDC. The relevant clause is

extracted below:-

" For all long-term open access transactions, the Nodal Agency for receiving and processing applications shall be the State Transmission Utility (STU).

For short-term open access transactions, the Nodal Agency for receiving and processing applications shall be the State Load Dispatch Centre (SLDC)"

Procedure for checking feasibility for allowance of

open access to any applicant is laid down in Clause 3 (Scope) of

Central Electricity Regulatory Commission (Open Access in

inter-State Transmission) Regulations, 2008 and the same is

extracted below:

" 3. Subject to any other regulations specified by the Commission, the long- term customer shall have first priority for using the inter-State transmission system for the designated use. These regulations shall apply for utilization of surplus capacity available thereafter on the inter-State transmission system by virtue of-

(a) Inherent design margins;

(b) Margins available due to variation in power flows; and© Margins available due to in-built spare transmission capacity created to cater to future load growth or generation addition:"

In addition to the above, Section 6 which is related

to verification of feasibility check for processing OA application

in Central Electricity Regulatory Commission (Open Access in

inter-State Transmission) (Amendment) Regulations, 2009 is

reproduced below for kind perusal:

" b) While processing the application for concurrence or 'no objection' or prior standing clearance, as the case may be, the State Load Despatch Centre shall verify the following, namely- Existence of infrastructure necessary for time-block-wise energy metering and accounting in accordance with the provisions of theGrid Code in force, andAvailability of surplus transmission capacity in the State network."

It is stated that any Open Access Consumer willing

to avail open access power under Inter/Intra State STOA,

feasibility has to be verified at various levels, viz., Verification of

line/Feeder capacity, Verification of transmission and

distribution Capacity, Verification of Sub Station feasibility,

Verification of metering provisions as per CEA norms at the

consumer end to avail open access power, Verification of

Compatibility Check of the installed ABT meters with the EBC

Software. The process also involves verification of design

margins and margins available for spare transmission or

distribution network where information of the whole

transmission or distribution network is to be gathered at

various levels. According to respondents, distribution corridor

is getting overloaded due to the scheme of Government of

Telangana to provide 24 hours power supply to all the services

including agricultural services from January, 2018 onwards,

therefore, TS DISCOMs had to make necessary arrangements

for adequate power procurement from various sources and as a

result of which, the network became completely loaded. However

this respondent has been continuously issuing NOC for OA

capacity of 17MW to petitioner through IEX every month duly

considering the sum of earlier OA demands of the two units of

petitioner. In the light of the above provision, Regulations and

Rules set forth by TSERC, TSSPDCL is processing many open

access transactions every month with a view to provide non-

discriminatory open access to the consumers through the same

Inter State and Intra State transmission/distribution network.

All the above Open access transactions are being accorded

approval for wheeling or utilizing the transmission/distribution

network and this respondent No.4/TSSPDCL is according

approval for OA capacity of 1200-1300 MW in Open access as

per the applications received every month. The transaction

corresponding to OA quantum of 17MW pertaining to petitioner

which is being applied every month is also included in the said

volume of OA transactions. The request of petitioner seeking 45

MW OA power is almost 2.5 times the present OA demand

(17MW).

It is stated that petitioner avails power through

open access when the price is cheaper and lower, when the

price goes high, they avail supply from this respondent

company. This type of transactions at the behest of petitioner

has been causing huge impact on the schedules of this

respondent and grid stability and would be detrimental to the

grid stability as petitioner is trying to avail 2.5 times the earlier

OA demand which will have pecuniary effect on respondent

which is working at large on "No Loss No Profit Basis". The

additional burden on respondents due to the said act of

petitioner will finally be passed on to the end

consumer/common people by way of increase in Tariff. The

distribution network is highly loaded due to various open access

transactions. The availing of supply through open access with

short intervals and higher OA capacity throughout a day would

further load the network resulting congestion of the existing

network.

In addition, this respondent company with an

intention to provide 24 hours supply to all its consumers has

been purchasing power from Power Exchanges in which rate is

very uncertain and depends upon the external factors such as

availability of power and demand across the Nation. It is unfair

on the part of petitioner to state that respondent is purchasing

power at cheaper rates. In fact, petitioner avails supply from

this Respondent when power prices at exchange are at higher

rate than the Distribution companies' tariffs. They are under

obligation to supply uninterrupted power to all consumers, who

will purchase power from Power Exchanges to meet even these

types of transactions from petitioner and likewise other open

access consumers.

This Court passed interim order dated 21.09.2023

directing to consider the representation of petitioner dated

17.04.2023. In compliance with the said order, this respondent

vide letter dated 07.10.2023 considered the representation of

petitioner and passed orders rejecting the request of petitioner

for issuance of NOC for enhancement from 17 to 45 MW due to

congestion in the grid and their Application for additional

quantum would be considered in future depending on

availability of grid.

6. The Chief General Manager (IPC), TSSPDCL also

filed the counter affidavit in Writ Petition No. 19494 of 2023,

almost reiterating the averments made in the counter referred to

supra.

7. Heard Sri...... learned Senior Counsel on behalf of

Smt. K. Jayasree, learned counsel for petitioners and Sri R.

Vinod Reddy, learned Standing Counsel for respondents and

perused the record. Sri Irigi Ganesh, learned counsel appearing

for petitioner in Writ Petition No. 26216 of 2023 submits that

the Hon'ble Supreme Court in Brihanmumbai Electric Supply

and Transport Undertaking v. Maharashtra Electricity

Regulatory Commission (MERC) 1 at para 26 held that it shall

be the duty of distribution licensee to develop and maintain an

efficient distribution system and further stated that Section 42

(3) of the Electricity Act casts a duty upon the distribution

licensee to provide Open Access to the consumers. Therefore,

the respondents cannot take shelter under the lame excuse that

grid space would not permit Open Access.

8. The simple case of petitioners is that Respondent -

Transmission Corporation of Telangana Limited is not granting

clearance / no objection for availing open access for the

aggregate load of 42 MW, 16.5 MW and 45 MW respectively.

According to petitioners, Sections 40 and 42 of the Act obligates

the transmission licensees to build, maintain and operate an

efficient coordinated inter-state or intra-state transmission

systems. Therefore, it is the statutory obligation of the

transmission utilities to provide open access and they can't

2015 (2) SCC 438

avoid the said obligation by resorting to some excuses that there

is no transmission line or congestion in the grid. Foreseeing

such a situation, the Central Regulatory Commission in its open

access Regulations under Clause 6 stipulates to invite open bids

and provide access in 45 days. It is the complaint of petitioner

that consumer is not at the mercy of the either TRANSCO or

DISCOM and it is their statutory right to have access to the

distribution system. Though learned counsel for petitioner

relying on the judgment in Brihanmumbai Electric Supply

and Transport Undertaking's case, submits that it shall be

the duty of distribution licensee to develop and maintain an

efficient distribution system and further as per Section 42 (3), a

duty is cast upon the distribution licensee to provide Open

Access to consumers, in the counter, it is the categorical stand

of the respondent that petitioner avails power through open

access when the price is cheaper and lower, when the price goes

high, they avail supply from this Respondent company. This

type of transactions at the behest of petitioner has been causing

huge impact on the schedules of this Respondent and grid

stability and would be detrimental to the Grid stability and

which will have pecuniary effect on respondents which is

working at large on "No Loss No Profit Basis". The additional

burden on the respondent due to the said act of petitioners will

finally be passed on to the end consumer/common people by

way of increase in Tariff. The distribution network is highly

loaded due to various open access transactions. The availing of

supply through open access with short intervals & higher OA

capacity throughout a day would further load the network

resulting congestion of the existing network. As is evident from

the counter, the respondent company with an intention to

provide 24 hours supply to all its consumers has been

purchasing power from Power Exchanges in which rate is very

uncertain and depends upon the external factors such as

availability of power and demand across the Nation. The

respondent company is under obligation to supply

uninterrupted power to all consumers and will purchase power

from Power Exchanges to meet even these types of transactions

from petitioner and likewise other open access consumers.

Further, this Court on 21.09.2023, in Writ Petition No. 26216 of

2023, as an interim measure, directed the 4th respondent

therein to consider representation of petitioner dated

17.04.2023, pursuant to which, the 4th respondent vide letter

dated 07.10.2023 considered and rejected the request of

petitioner for issuance of NOC for enhancement from 17 to 45

MW due to congestion in the grid and their Application for

additional quantum would be considered in future depending on

availability of grid.

9. In view of the foregoing circumstances and keeping

in view the obligations to be discharged as narrated by the

respondent Company in the counter-affidavit, this Court is of

the opinion that petitioners are not entitled for any positive

relief. The Writ Petitions are therefore, liable to be dismissed.

10. All the three Writ Petitions are accordingly,

dismissed. No costs.

11. Consequently, miscellaneous Applications, if any

shall stand closed.

-------------------------------------

NAGESH BHEEMAPAKA, J

15th October 2024

ksld

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter