Citation : 2022 Latest Caselaw 4835 Tel
Judgement Date : 22 September, 2022
THE HON'BLE SRI JUSTICE A. VENKATESHWARA REDDY
CCCA No.66 of 2002
JUDGMENT:
This Appeal Suit is filed by the appellant/plaintiff
assailing the judgment and decree dated 17.08.2001 in OS
No.417 of 1998 on the file of the learned XI Additional
Chief Judge, City Civil Court (Fast Track Court) at
Hyderabad.
2. The plaintiff has filed the original suit in OS No.417
of 1998 for recovery of Rs.9,21,300/- against the person
and property of the defendants with future interest at 12%
per annum from the date of suit till the date of realization
with costs. The trial Court after full length trial upon
considering the oral and documentary evidence adduced on
both sides dismissed the suit of the plaintiff holding that
the defendants did not agree to reimburse the expenditure
incurred by the plaintiff on completion of the balance work
in the suit house and that the original agreement entered
into between the parties was cancelled by execution of the
sale deed and delivery of possession of suit schedule house
AVRJ CCCA No.66 of 2002
on 31.10.1996 under Ex.A.1 sale deed in favour of the
plaintiff and accordingly the suit was dismissed.
3. Feeling aggrieved by the said judgment and decree
dated 17.08.2001 in OS No.417 of 1998, the appellant/
plaintiff has filed this appeal suit on the following grounds
praying to set aside the judgment and decree of the trial
Court, consequently to decree the suit for an amount of
Rs.12,80,607/- with costs:
i) that the trial Court has proceeded on assumptions and presumptions and dismissed the suit and passed the decree in favour of the defendants and against the plaintiff;
ii) that the trial Court has failed to consider the evidence available on record and also failed to look into the fact that the first defendant has handed over the possession of the suit schedule house in semi-finished condition;
iii) that the trial Court has not considered the evidence of PWs.1 & 2 wherein both the witnesses categorically stated that plastering, flooring, tiles, windows, doors,
AVRJ CCCA No.66 of 2002
grills etc., were not completed and the house was not fit for occupation; and
iv) that the trial Court has also failed to consider that the plaintiff has spent an amount of Rs.9,21,300/- to attend the left over work.
4. In spite of service of notice, none appeared on behalf
of the respondents/defendants, remained absent and they
were set ex parte. Heard the learned counsel for the
appellant/ plaintiff. The submissions made by him have
received due consideration of this Court. Perused the
material available on record.
5. The learned counsel for the appellant/plaintiff seeks
to submit that the plaintiff has entered into an agreement
with the defendants for construction of a house in an open
area of 220 square yards of plot No.2 in Survey No.106
situated at Road No.7, Banjara Hills, Hyderabad on
02.06.1994 and as per the agreement, the defendants have
to complete the entire work only for an amount of
Rs.15,60,000/-, and the plaintiff has agreed to pay the said
amount in instalments @ Rs.70,000/- per month.
AVRJ CCCA No.66 of 2002
Accordingly, the plaintiff has paid in all an amount of
Rs.14,20,000/- during the period from 14.07.1994 to
16.02.1996 and requested the defendants to complete the
work by the end of October 1996. But the defendants have
failed to execute the work as agreed to. Having frustrated
with the attitude of defendants, the plaintiff obtained
registered sale deed in respect of the suit schedule property
on 31.10.1996. Thereafter, the plaintiff has spent about
Rs.9 lakhs for fixtures, doors, bore-well, drainage
connection, window glasses, electrical and sanitary works,
flooring and kitchen finishing works, overhead tank etc.
The plaintiff has also spent additional amount of
Rs.50,000/- for completion of the balance work. Thus, the
defendants are due to pay an amount of Rs.9,30,000/-
after adjustment of Rs.4,90,000/- as mentioned in the
registered sale deed Ex.A.1, out of the total amount of
Rs.14,20,000/- received by the defendants from the
plaintiff. On repeated demands made by the plaintiff, only
an amount of Rs.1,00,000/- was paid in September, 1997
and failed to pay the balance amount of Rs.8,30,000/-.
The plaintiff has got issued a legal notice dated 08.08.1998
AVRJ CCCA No.66 of 2002
calling upon the defendants for payment of the said
amount, hence, the plaintiff is entitled for recovery of the
said amount of Rs.9,21,300/- together with costs.
6. The learned counsel for the appellant/plaintiff further
contends that the trial Court has failed to appreciate the
oral evidence of PWs.1 to 6 and contents of Exs.A.1 to A.31
and simply arrived at a conclusion that in view of the
execution of original of Ex.A.1-sale deed by the defendants
in favour of the plaintiff, earlier agreement, if any entered
between the parties, stands cancelled, which is not correct.
He has also relied on the principles laid by the Hon'ble
Apex Court in Rangammal v. Kuppuswami and another1.
7. In the light of the submissions made by the learned
counsel for the appellant/plaintiff, the following points
arise for consideration:
i) whether the appellant is able to prove the terms of contract dated 02.06.1994; and
ii) whether the impugned judgment and decree dated 17.08.2021 is sustainable?
(2011) 12 SCC 220
AVRJ CCCA No.66 of 2002
Point Nos.(i) and (ii):
8. Since both the point Nos.(i) & (ii) are interconnected,
for the sake of brevity, they are answered together as
under:
9. It may be stated that the plaintiff has filed the
original suit for recovery of Rs.9,21,300/- with interest at
12% per annum. The defendants 1 & 2 have filed a
detailed written statement alleging that as per the
agreement dated 02.06.1994, they have agreed to construct
the house as per the specifications at the costs of
Rs.16,40,000/-. It is not correct to allege that the plaintiff
has agreed to pay Rs.14,20,000/- and paid the said
amount @ Rs.70,000/- per month till the end of October
1996. The plaintiff has in all paid Rs.14,20,000/- from
14.07.1994 to 07.02.1996 irregularly. The defendants
have never expressed their inability to proceed with the
construction work. In fact, the plaintiff has represented
that his father wants to change the plan and intends to go
for more construction, requested the defendants to cancel
the contract at that stage. By that time 90% of the
AVRJ CCCA No.66 of 2002
construction was completed and the contract was cancelled
at the request of the plaintiff only. It was represented by
the plaintiff that the Government was going to enhance the
registration charges and accordingly requested to execute
the registered sale deed, thereby registered sale deed was
executed on 31.10.1996. There was no agreement at that
time for completion of the balance work by the defendants.
It is false to allege that the plaintiff has spent Rs.9 lakhs
for fixtures such as doors, bore-well and other items and in
fact all these items were completed at the time of handing
over the possession of suit house to the plaintiff by
executing the sale deed. The defendants are not liable to
pay any amount much less an amount of Rs.9,30,000/-.
They have not paid Rs.1,00,000/- to the plaintiff in
September 1997 agreeing to pay the remaining amount in
future instalments.
10. Based on the above pleadings, the trial Court has
framed the following issues:
1. Whether the agreement was cancelled by the plaintiff as pleaded by the defendants?
AVRJ CCCA No.66 of 2002
2. Whether the plaintiff is entitled to recover the said amount from the defendants?
3. To what relief?
11. During the trial, on behalf of plaintiff, PWs.1 to 6 are
examined and Ex.A.1 to A.31 documents are marked,
whereas on behalf of the defendants, DW.1 is examined.
12. PW.1 is the plaintiff. He has supported the plaint
averments. PW.2 is the father of the plaintiff and he is the
power of attorney holder under Ex.A.31. He stated that he
visited the suit schedule property in November 1996 by
then the roof alone was laid, windows and doors were not
fixed and there was no plastering. He attended all the
remaining works and incurred expenditure and prepared a
consolidated statement as Ex.A.16.
13. PW.3 is a mason, who attended the mason work of
the suit house from October 1997 to February 1998. He
stated that he received the payment from PW.2 for the
work done by him. Similarly, PW.4 is the carpenter, who
attended the carpentry work if the suit house from
October, 1996 to February 1998. PW.5 is a plumber, who
said to have attended the plumbing work from June 1997
AVRJ CCCA No.66 of 2002
to March 1998. PW.6 is a welder, who attended the welding
work in the suit house during May 1997 to February,
1998.
14. Be it stated that as per the evidence of PWs.4 to 6
they have received payments only from PW.2. As against
the above evidence of plaintiff, the first defendant himself
got examined as DW.1. Though he was cross-examined at
length, nothing worth mentioning is elicited. His evidence
remained consistent throughout the cross-examination.
However, it is admitted by DW.1 that the construction work
was supposed to be completed by the end of October 1996,
80% of the work was completed by November 1996 and
only the windows and doors were not fixed and there was
no plastering.
15. The plaintiff has not filed the original or copy of
contract dated 02.06.1994 to ascertain the terms of
agreement for construction of the house. Undisputedly,
Ex.A.1-sale deed was executed by the defendants on
31.10.1996. A plain reading of Ex.A.1 shows that the
defendants have sold the house to the plaintiff, nothing is
AVRJ CCCA No.66 of 2002
mentioned about the unfinished structure sold under
Ex.A.1 or that the defendants have agreed to complete the
remaining work. The plaintiff is withholding the best
evidence of agreement of sale dated 02.06.1994 to
ascertain the terms and the suit claim has to be decided
only basing on the oral evidence. Thus, the oral evidence
of PWs.1 & 2 is only available to ascertain the terms of
agreement dated 02.06.1994. The first defendant is
residing at Zeddah and in his evidence he stated that he is
holding copy of said agreement but it is not carried by him
and it is with him at Zeddah and nowhere it is mentioned
in the agreement that only with an amount of
Rs.14,20,000/- the entire work has to be completed.
16. It may be a fact that PWs.4 to 6 have received
payment from PW.2 but that does mean that the entire
semi-finished structure was handed over and that there
was an agreement and the defendants violated the terms
and conditions mentioned therein. It is pertinent to note
that nothing is mentioned in Ex.A.1 at the time of
registration of the building that the defendants have to
meet the expenses for the remaining work. If really there
AVRJ CCCA No.66 of 2002
was an agreement and the defendants have failed to
comply the terms of agreement, the plaintiff as a prudent
man ought to have filed a report of concerned Engineers to
the effect, what was the work completed and what was the
work left over by the time of execution of Ex.A.1-sale deed
or he ought to have mentioned in Ex.A.1 that a semi-
finished structure is sold and the defendants have agreed
to complete the structures with a stipulated time.
Undisputedly, the plaintiff has not taken any such steps,
simply obtained a registered sale deed, original of Ex.A.1
on 31.10.1996 and taken over the possession of the suit
schedule property.
17. In such factual matrix, the trial Court has rightly
appreciated the oral and documentary evidence available
on record including the evidence of first defendant as DW.1
who stated that by the time of execution of Ex.A.1, almost
80% of the work was completed including flooring,
plastering, sanitary pipeline, parapet wall, external
plastering etc. It is the further evidence of DW.1 that the
defendants have requested PW.2 for payment of
instalments as per the schedule, but the plaintiff requested
AVRJ CCCA No.66 of 2002
to register the property and hand over the possession
stating that they will proceed with further construction. It
is only as per the request of the plaintiff, registered sale
deed was executed under the original of Ex.A.1 and
possession was delivered. It appears that subsequent to
Ex.A.1-sale deed, the plaintiff has carried the remaining
work.
18. Another important circumstance which goes against
the plaintiff is that at the time of obtaining registered sale
deed, the original of Ex.A.1, the plaintiff did not raise any
objection or protest regarding the construction of the
building. If really the defendants have failed to complete
the construction as per the schedule, the plaintiff as a
prudent man ought to have raised objections, at the time of
execution of sale deed. Though the plaintiff has stated that
in September 1997, an amount of Rs.1 lakh was paid by
the plaintiff, except the oral evidence of PW.1, nothing is
available on record as to the payment of Rs.1 lakh by the
defendants to the plaintiff. Ex.A.16 is the book maintained
for the entire expenditure for Exs.A.6 to A.16, whereas
Exs.A.17 to A.30 are the receipts. These receipts under
AVRJ CCCA No.66 of 2002
Exs.A.17 to A.30 are not in dispute by the defendants and
their case is that the plaintiff was irregular in payments.
Thus, there is no evidence to show the nature of works
undertaken by the plaintiff under Ex.A.16 only because the
defendants failed to execute the work as agreed or what
were the works agreed to be executed by the defendants as
per terms of agreement dated 02.06.1994 and that there is
deficiency in the services and as such said works were not
completed by the time of execution of sale deed under
Ex.A.1.
19. In Rangammal's case (supra) relied by the learned
counsel for the appellant/plaintiff, the Hon'ble Apex Court
while dealing with the Section 101 of Evidence Act held
that the burden of proving the fact that always lies upon
the person who asserts the fact and until such burden is
discharged, the other party is not required to be called
upon to prove his case. The Court has to examine as to
whether the person upon whom the burden lies has been
able to discharge the burden and until he arrives that
conclusion, he cannot proceed on the basis of weakness of
the other party.
AVRJ CCCA No.66 of 2002
20. In this case, the plaintiff has come up with a specific
plea that as on the date of registration of the suit schedule
property under the original of Ex.A.1, the defendants failed
to complete the structures as per the terms of contract
dated 02.06.1994 and that the plaintiff had to incur huge
amounts as mentioned in Ex.A.16, but the original or copy
of contract dated 02.06.1994 is not filed by the plaintiff.
Whereas, the defendants denied the suit claim and the first
defendant as DW.1 has categorically asserted that they
have completed more than 80% of the work and it is only
at the request of the plaintiff they have executed Ex.A.1-
registered sale deed. The plaintiffs have requested for
execution of sale deed stating that they will get the
remaining work completed with their own funds. Thus, to
believe the version of the plaintiff, it is for the plaintiff to
file the original agreement dated 02.06.1994 to ascertain
the terms of contract. Further, there is no such report of
Engineer or any other expert to indicate that as on the date
of Ex.A.1-sale deed, major portion of the work was not
completed. On the other hand, nothing is indicated in
Ex.A.1 that a semi-finished structure was registered and
AVRJ CCCA No.66 of 2002
that the defendants have agreed to carry out the remaining
work subsequent to Ex.A.1.
21. Therefore, when the facts of the present case are
tested on the touchstone of the principles laid in the above
decision with reference to Sections 101 and 102 of
Evidence Act, the answer is in the negative. The burden
lies on the plaintiff to prove the terms of contract dated
02.06.1994 and also to prove that in spite of execution of
Ex.A.1 sale deed, the terms of agreement dated 02.06.1994
are still in force, but the plaintiff failed to discharge the
same. The plaintiff is not entitled to depend on the
weakness or otherwise of the defendants case. The plaintiff
has to stand or fall on his own legs. In such circumstances,
as the plaintiff failed to prove the terms of contract dated
02.06.1994 with regard to the execution of left over work
by the defendants, the entries made in Ex.A.16 as to
payment of amount to PWs.4 to 6 is not helpful to the
plaintiff for recovery of said amount from the defendants,
more particularly in view of the execution of registered sale
deed Ex.A.1 and taking over the possession of the suit
schedule property on 31.10.1996 unconditionally.
AVRJ CCCA No.66 of 2002
22. In that view of the matter, I do not find any
irregularities or infirmities in appreciation of evidence by
the trial Court. The leaned judge of the trial Court having
carefully appreciated the oral and documentary evidence
available on record, has negatived the claim of the plaintiff
dismissing the suit with costs and the findings recorded by
the trial Court does not warrant any interference by this
Court.
23. In the result, the appeal suit is dismissed with costs
confirming the judgment and decree dated 17.08.2001 in
OS No.417 of 1998 on the file of the learned XI Additional
Chief Judge, City Civil Court (Fast Track Court) at
Hyderabad.
As a sequel, interlocutory applications, if any pending
in this appeal, shall stand closed.
__________________________________ A. VENKATESHWARA REDDY, J.
Date: 22.09.2022 Isn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!