Citation : 2022 Latest Caselaw 4741 Tel
Judgement Date : 20 September, 2022
THE HON'BLE SRI JUSTICE K.SURENDER
CRIMINAL APPEAL Nos.836 & 837 of 2008
COMMON JUDGMENT:
1.
The appellants are A1 and A2, convicted and sentenced to
undergo rigorous imprisonment for one year each for the charge
under Sections 7 and Section 13(1)(d) r/w Section 13(2) of the
Prevention of Corruption Act, 1988 (for short 'the Act of 1988')
in C.C.No.30 of 2003, dated 27.06.2008 passed by the Principal
Special Judge for SPE & ACB Cases, City Civil Court,
Hyderabad. Aggrieved by the same, present appeal is filed.
2. Criminal Appeal No.836 of 2008 is preferred by AO2 and
Criminal Appeal No.837 of 2008 is preferred by AO1. Since both
these appeals arise out of judgment in CC No.30 of 2003, they
are being heard together and disposed off by way of this
Common Judgment.
3. For the sake of convenience, the parties herein after will be
referred to as arrayed before the trial Court.
4. AO1 was Additional Assistant Engineer and AO2 was Sub
Engineer in the office of the Divisional Engineer (Electrical and
Operations) City VI, APCPDCL, Bowenpally. The case of the
prosecution is that P.W.1 was working as Factory Manager in
R.C.Metal Fabs at Hyderabad of which P.W.3 is the proprietor.
On behalf of R.C. Metal Fabs, P.W.3 applied for 10 HB Industrial
Electric power on 30.06.2001 in the office of the Divisional
Engineer (Operations) wherein AOs 1 and 2 were working. On
09.06.2001, the Divisional Engineer forwarded the application to
AO1. When P.W.1 met AO1 on 09.06.2001, AO1 demanded to
pay Rs.6,000/- as bribe and referred the concerned file to AO2.
AO2 also made demand of Rs.2,000/-. The case was pending
and during November, 2001, when P.W.1 again met AOs.1 and 2
they informed that bribe as demanded earlier has to be paid.
Since 10 HB industrial electric supply was not sanctioned,
manufacturing process was stalled. P.W.1 met AOs.1 and 2
twice in the month of November, 2001 and again on 04.12.2001.
The bribe amount was reduced by AO1 to Rs.4000/- and AO2 to
Rs.1000/-. According to P.W.1, P.W.3 instructed him to
complain to ACB about AOs 1 and 2. Accordingly, on
05.12.2001, P.W.1 lodged Ex.P1 complaint in writing. The trap
was arranged on the same day at 2.00 p.m. At 2.00 p.m, the trap
party members gathered in the office of ACB and after following
the pre trap formalities, prepared Ex.P3 pre-trap proceedings.
The trap party went to the office of AO around 5.00 p.m. P.Ws.1
and 2 went into the office and when demanded by AO1 and AO2,
the bribe amount of Rs.4,000/-was paid to AO1 and Rs.1,000/-
was paid to AO2. P.W.2 relayed signal to the trap party
indicating acceptance of bribe by AOs.1 and 2, as such, the trap
party entered into the office and conducted tests on the hands of
AOs.1 and 2. The amount of Rs.4,000/- was recovered from the
pocket of AO1 and the amount of Rs.1,000/- was recovered,
which was placed in the attendance register. The tests conducted
on the hands of both the AOs.1 and 2 proved positive and
thereafter, the post trap proceedings under Ex.P10, was
prepared. P.W.9, the DSP handed over investigation to P.W.10
and after conclusion of investigation, charge sheet was laid for
the offences under Sections 7 and Section 13(1)(d) r/w Section
13(2) of the Act.
5. The prosecution examined P.Ws.1 to 11 and marked Exs.P1
to P21. On behalf of the accused, D.Ws.1 to 3 were examined
and marked Exs.X1 to X9 in support of the defence. After
conclusion of trial, learned Special Judge found the appellants
guilty as stated above.
6. Sri T.Niranjan Reddy, learned Senior Counsel appearing for
the appellants would submit that at the very inception, during
post trap proceedings AO1 stated that the amount was given
towards purchase of meter. Ex.X1 marked through P.W.1, which
is a letter addressed by P.W.3 dated 29.11.2001 undertaking to
purchase a new meter through a representative. P.W.1 was
working on commission basis in the factory of P.W.3 However,
P.W.3 did not support the case of the prosecution. Further the
independent mediators P.W.4-Divisional Engineer, P.W.6-
Divisional Engineer (Stores), P.W.7-Junior Assistant, District
Registrar of Assurances, who is the other mediator have all
turned hostile to the prosecution case. Section 164 Cr.P.C
statement of P.W.1 was recorded before the Metropolitan
Magistrate as admitted by PW10, however, the said statement
was suppressed. From the evidence of P.W.1, he did not know
the procedure to be followed for installing new meter. In fact, the
proprietor, P.W.3 stated that he has given letter dated
29.11.2001 and received quote from AO1 for Rs.3,996/- for
installing of new meters. According to P.W.4, the memos issued
by the department Exs.X3 and X4 indicate that the customers
can purchase new meters at their expense. Similarly, P.W.5 also
marked Exs.X5 and X6, which reflect the allotment of letters to
different sections and that there were no new three phase meters
in Ferozguda Section. AOs.1 and 2 have proved their defence,
which was stated at the earliest point of time in the second
mediator's report Ex.P10 that the amount of Rs.4,000/- was
towards purchase of new meter which was undertaken to be paid
by P.W.3. Except P.W.1 none of the witnesses P.W.2
independent mediator, nor P.W.3 who is the owner of the
industry have spoken anything about demand of bribe by the
appellants, for which reason, the appellants are entitled to be
acquitted. Further the sanction is bad in law for the reason of
the ACB not providing documents to the sanctioning authority
and apparently the sanction was mechanically granted.
7. Learned counsel for the appellants relied upon the following
judgments; i) Suraj Mal v. State (Delhi Administration) [(1979)
4 Supreme Court Cases 725], wherein the Hon'ble Supreme
Court held that mere recovery of bribe money divorced from the
circumstances under which it was paid is not sufficient to
convict when the substantive evidence in the case was not
reliable; ii) C.M.Girish Babu v. CBI, Cochin, High Court of
Kerala [(2009) 3 Supreme Court Cases 779], wherein the Hon'ble
Supreme Court held that mere recovery is not enough and the
accused can discharge his burden by preponderance of
probability; iii) V.Sejappa v. State by Police Inspector
Lokayukta, Chitradurga {(2016) 12 Supreme Court Cases 150],
wherein it is held that when demand is not proved, the appellant
has to be acquitted; iv) T.K.Ramesh Kumar v. State through
Police Inspector, Bangalore [(2015) 15 Supreme Court Cases
629], wherein it is held that though recovery was made, however,
in the absence of proof of demand, there cannot be conviction
under Sections 7 and 13(1)(d) r/w Section 13(2) of the Act.
8. On the other hand, learned Special Public Prosecutor for
ACB submits that though the witnesses P.Ws.2, 3, 4, 6 and 7
were declared hostile to the prosecution case, it does not have
bearing on the demand and acceptance of bribe by the
appellants. P.W.1's evidence is sufficient to infer that the
industry of P.W.3 had applied for 10 HB industrial power
connection, for which, new meter was required. Over a period of
nearly six months, meter and power supply was not provided, as
such, vexed by the demand made by the appellants, Ex.P1 was
lodged. The circumstantial evidence in the case is sufficient to
record conviction.
9. In reply to the arguments of the learned counsel for the
appellants that the sanction was not proper and the sanctioning
authority was not provided with the documents of the case, the
learned Public Prosecutor relied upon the judgment of Hon'ble
Supreme Court in the case of Girish Kumar Suneja v. CBI
[Crl.Appeal No.1137 of 2017, dated 13.07.2017 arising out of
SLP (Crl.) NO.9503 of 2016], wherein it was held that unless
prejudice was shown and when the Court after judicial scrutiny
finds a person guilty, the question of sanction would be
inconsequential.
10. P.W.3 who is the owner of the industry in which electric
connection was sought, did not support the case of P.W.1
regarding the demand of bribe by AOs.1 and 2 contrary to the
version of P.W.1. P.W.3 stated that the amount was paid for
purchase of new meter, which request for new meter was made
vide Ex.X1 letter dated 29.11.2001. Though the witness was
treated as hostile by the prosecution, the version of P.W.3 that
he intended to purchase a new meter at the cost of Rs.3,996/- is
supported by document Ex.X1. Exs.X3 and X4, are the memos
issued by the department which permit purchase of meters at
the customer's expense, as stated by P.W.4, the Divisional
Engineer. P.W.5, the Additional Divisional Engineer has stated
that there were no three phase meters in Ferozguda Section.
11. At the earliest point of time, when the DSP questioned AO1
regarding Rs.4,000/-, he stated that P.W.1 brought Rs.4,000/-
for purchase of 3 phase high quality meter. He narrated that the
industry of P.W.3 was not given three phase meter as there was
no supply of meters. Pursuant to the request of P.W.3, the
amount was received towards purchase of meter. The said
version is corroborated by the evidence of P.Ws.3, 4 and 5 under
Exs.X1 to X4 and the version of AO1 recorded during post trap
proceedings.
12. Both the independent mediators, P.Ws.2 and 8 did not
state anything about alleged demand made by the appellants on
the trap day. In the back ground of an application that was made
by PW3 for purchase of meter which was pending consideration
for which amount was accepted by AO1. In view of the evidence
of P.Ws.3, 4 and 5 and Exs.X1 to X5, the appellants have
discharged their burden of proving that the amount was not
towards bribe. The amount of Rs.1,000/- was recovered, which
was placed in the attendance register, for the reason of this
Court not believing the version of PW.1 that there was a demand
from these appellants for providing electric connection, recovery
from the attendance register of Rs.1,000/- is of no consequence.
For the said reason, the prosecution has failed to prove that
there was demand of bribe and further AO1 explained the reason
for receipt of the said amount at the earliest point of time,
supported by the documentary evidence for which reasons
benefit of doubt is extended to the appellants.
13. In the said circumstances, the prosecution has failed to
prove its case beyond reasonable doubt, however the appellants
have discharged their burden as discussed above.
14. For the aforementioned reasons, the conviction recorded by
the trial Court in CC No.30 of 2003 dated 27.06.2008 is set aside
and the appellants are acquitted. Since the appellants are on
bail, their bail bonds shall stand cancelled.
15. Accordingly, Criminal Appeals are allowed.
_________________ K.SURENDER, J Date:20.09.2022 kvs
THE HON'BLE SRI JUSTICE K.SURENDER
Crl.A.Nos.836 & 837 of 2008
Dated:20.09.2022
kvs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!