Citation : 2022 Latest Caselaw 5429 Tel
Judgement Date : 28 October, 2022
THE HON'BLE THE CHIEF JUSTICE UJJAL BHUYAN
AND
THE HON'BLE SRI JUSTICE C.V.BHASKAR REDDY
WRIT APPEAL No.705 of 2022
JUDGMENT: (Per the Hon'ble the Chief Justice Ujjal Bhuyan)
Heard Mr. K.Gopal, learned counsel for the
appellants; Ms. Borra Lakshmi Kanakavalli, learned
Assistant Government Pleader for Municipal
Administration and Urban Development Department
appearing for respondent No.3; Mr. M.A.K.Mukheed,
learned counsel appearing for respondents No.4 to 6; and
Dr. J.Vijaya Laxmi, learned Government Pleader appearing
for respondent No.7.
2. This writ appeal is directed against the order dated
01.09.2022 passed by the learned Single Judge disposing
of W.P.No.38242 of 2017 filed by respondents No.1 and 2
as the writ petitioners.
3. Respondents No.1 and 2 had filed the related writ
petition for quashing of building permission dated
05.09.2015 issued by respondents No.4 to 6 in favour of
the appellants on the ground that the building permission
was obtained on the basis of fake urban land ceiling
clearance certificate. Writ petitioners further sought for
demolition of the constructions made on the basis of such
building permission.
4. Relevant facts or rather the admitted facts culled out
by the learned Single Judge as is discernible from the order
dated 01.09.2022 are as follows:
"6. The admitted facts are that the petitioners have filed a suit i.e. O.S.No.619 of 2015 on the file of XIII District Judge, Ranga Reddy District at L.B.Nagar and initially an interim injunction was granted on 27.06.2015 directing the unofficial respondents not to create any third party rights in respect of the suit schedule property. The permission was granted in favour of the unofficial respondents on 05.09.2015. Thereafter, the unofficial respondents have entered appearance in the said suit on 05.11.2015."
5. Though learned counsel for the writ petitioners
contended that interim injunction granted on 27.06.2015
was made absolute, learned Single Judge noted that no
materials were placed before the Court in this regard. On
the contrary, learned counsel representing Greater
Hyderabad Municipal Corporation submitted that the
interim injunction was not extended. Learned Single
Judge concluded that on the date of obtaining building
permission appellants had not entered appearance in the
suit (O.S.No.619 of 2015) and therefore they were not
aware of the pending proceeding. Hence, they proceeded
with the construction. On the allegation that the building
permission was obtained by furnishing incorrect
information, learned Single Judge found no substance in
the allegation. On the other hand, it was recorded by the
learned Single Judge that though the civil suit is pending,
appellants have completed major portion of the
construction. Thereafter, the following order came to be
passed by the learned Single Judge.
"10. In the facts and circumstances, this court deems it appropriate to permit the unofficial respondents to complete the construction activity. The unofficial respondents except completing the construction shall not lease out or create any third party rights till the outcome of the suit. The respondent corporation shall also not issue occupancy certificate to the said building pending orders of the civil court and till the outcome of the suit or till the said interim orders are vacated by the civil court."
6. When the learned Single Judge recorded that there
was no suppression or misfurnishing of information by the
appellants while obtaining building permission and that
there was nothing on record to show that injunction order
of the civil Court being in force, we are of the view that
such blanket restriction imposed on the appellants is not
justified.
7. Learned counsel for the appellants has made a
statement before the Court that appellants would not
create any third party rights in the building being
constructed. We record the said statement.
8. That portion of the order of the learned Single Judge
directing Greater Hyderabad Municipal Corporation not to
issue occupancy certificate to the building being
constructed during pendency of the civil suit, in our view,
is uncalled for and unwarranted. At this stage we may
mention that writ petitioners could very well have produced
the injunction order if the same was indeed extended.
Instead of approaching the civil Court for extension of
injunction or availing the remedy in the event such prayer
was rejected, the related writ petition came to be filed.
9. That being the position, order dated 01.09.2022
passed in W.P.No.38242 of 2017, more particularly the
order contained in paragraph 10 thereof, is modified to the
extent that appellants may complete the construction of
the building based on the building permission dated
05.09.2015, but shall not create any third party rights
therein till outcome of the suit. The remaining portion of
the order contained in paragraph 10 is accordingly set
aside.
10. Writ appeal is disposed of.
Miscellaneous applications pending, if any, shall
stand closed. However, there shall be no order as to costs.
______________________________________ UJJAL BHUYAN, CJ
______________________________________ C.V.BHASKAR REDDY, J 28.10.2022 vs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!