Citation : 2022 Latest Caselaw 5269 Tel
Judgement Date : 26 October, 2022
1
Dr. GRR ,J
W.P. Nos.21932 and 28909 of 2021
THE HON'BLE Dr. JUSTICE G. RADHA RANI
WRIT PETITION Nos. 21932 and 28909 OF 2021
COMMON ORDER:
1. Writ Petition No.21932 of 2021 is filed by the petitioners to issue a Writ
of Mandamus declaring the inaction of the respondent Nos.2 and 3 being the
scheduled public sector banks under the RBI Act, 1934 in refusing to act on
their promise and failure to discharge their obligations under the Bank
Guarantees bearing No. 12821IGL0002621, 12821IGL0002721,
12821IGL0003321, 12821IGL0003421, 12821IGL0003521 as illegal, arbitrary,
unjust and unconstitutional and in gross violation of statutory obligations under
Section 6(1)(e) of the Banking Regulation Act, 1949, Section 126 of the
Contract Act, 1872, Principles of Natural Justice and Article 14 of the
Constitution of India inspite of several requests made including vide legal
notices dated 11.08.2021 and consequentially to direct the respondent No.1 to
initiate necessary action against respondent Nos. 2 and 3 for illegally reneging
on their statutory obligations.
2. Writ Petition No.28909 of 2021 is filed to issue a Writ of Mandamus
declaring the action of the Respondents No.2 and 3 being Scheduled Public
Sector Bank under the RBI Act, 1934 by unilaterally closing the Bank
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
Guarantees as returned bearing No.128220IGFIN0048 128220IGFIN0049
128220IGFIN0051 128220IGFIN0053 128220IGFIN0054 128220IGFIN0055
12821IGL0000121 12821IGL0001821 12821IGL0002821 128211GL0003221
and 128220IGFIN0046 as illegal, arbitrary, unjust and unconstitutional and in
gross violation of statutory obligation under Section 6(1)(e) of the Banking
Regulation Act 1949, Section 126 of the Contract Act 1872, Principles of
Natural Justice, Article 14 of the Constitution of India inspite of several requests
made including vide Legal Notice dated 11.08.2021 and consequentially to
direct the Respondent Nos.2 and 3 to reopen the 11 Bank Guarantees as returned
and also to direct the Respondent No.1 to initiate necessary action against
Respondents Nos.2 and 3 for illegally reneging on their statutory obligations.
3. Heard Sri S.Niranjan Reddy, learned senior counsel representing
Sri D. Narender Naik, learned counsel for the petitioners and the learned
counsel for respondent No.1, Sri S. Ravi, learned senior counsel appearing for
respondent Nos. 2 and 3 and the learned counsel for respondent No.4.
4. The learned senior counsel for the petitioners submitted that the petitioner
was a technology company involved in construction and real estate procurement
of material for their projects and third party projects. The 2nd respondent was a
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
scheduled public sector commercial bank and the 3rd respondent was the branch
office of the second respondent in Madhapur, Hyderabad. The respondent Nos. 2
and 3 had undertaken applications and issued bank guarantees to the petitioner
on behalf of respondent No.4. The respondents 1 to 3 were performing public
functions and were squarely covered under Article 12 of the Constitution of
India. The respondent Nos. 2 and 3 derive their powers to give guarantees from
Section 6(1)(e) of the Banking Regulation Act, 1949. The respondent No.4,
Kompass Infrastructure Private Limited approached the petitioner to provide
various construction materials on credit terms. In furtherance of such
understanding, respondent Nos. 2 and 3 promised the petitioner that the
obligations of respondent No. 4 would be performed failing which the
respondent Nos. 2 and 3 being public sector schedule banks under RBI Act,
1934 had taken upon themselves to make good the statutory promise and
payment obligation. Had it not been for the solemn promise and guarantee
given by the respondent Nos.2 and 3, the petitioner would not have entered into
contract with respondent No.4. Solely on the basis of the guarantee by
respondent Nos. 2 and 3, the petitioner extended credit facility to respondent
No.4. The respondent Nos. 2 and 3 issued sixteen (16) bank guarantees, out of
which five (05) bank guarantees for an amount of Rs.7,15,00,000/- were live and
eleven (11) bank guarantees for an amount of Rs. 16,61,58,250/- were illegally
closed. The validity and issuance of the bank guarantees was confirmed by
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
respondent Nos. 2 & 3 vide SFMS message (Mechanism suggested by RBI to
confirm validity of a bank guarantee). As per clause No.4 of the bank
guarantee, it was expressly mentioned that the guarantee should be irrevocable.
As per clause No.6 of the bank guarantee, it was specifically mentioned that the
respondent Nos. 2 and 3 would undertake not to revoke the bank guarantee
except with the previous consent of the petitioner. On 05.07.2021, the petitioner
invoked the live bank guarantees aggregated to a sum of Rs.7,15,00,000/- and
requested respondent No.3 to make the payment to the petitioner as per its
obligations under the bank guarantee. But till date respondent No.3 had not
acted in furtherance of its obligation under the said bank guarantees and the
petitioner had not received the amounts as promised by the scheduled bank i.e.,
respondent Nos. 2 and 3. Besides the aforesaid five (05) live bank guarantees
which were pending encashment, the petitioner had also invoked eleven (11)
illegally closed bank guarantees and on 13.07.2021 produced eleven (11)
original bank guarantees. However, as a rude shock to the petitioner in response
to the petitioner's letter of invocation dated 05.07.2021 and 06.07.2021, a reply
was issued vide letter dated 06.07.2021 that in respect of eleven (11) bank
guarantees amounting to Rs.16,61,58,250/-, as per the records of the branch, the
said bank guarantees were returned along with a covering letter. The petitioner
had never returned the said bank guarantees and the original bank guarantees
issued by the bank were in possession of the petitioner. It was a clear indication
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
of conspiracy and collusion among the respondent Nos. 2 and 3 and the officials
of respondent No.4 to commit criminal breach of trust, especially when all the
sixteen (16) original bank guarantees were with the petitioner. All sixteen (16)
original bank guarantees were shown to officers of the respondent No.2 at the
branch and they duly verified the same.
4.1 On 13.07.2021, the petitioner was informed to come to the branch of
respondent No.3 along with the bank guarantees. The petitioner's representative
arrived at Hyderabad from Mumbai on the said date at 05.00 PM along with all
the original bank guarantees. The respondent No.3 and their audit team verified
all the originals. But till date, the petitioner had not received the amount. The
petitioner was made to run from pillar to post from Head Office to Branch
Office and to several offices of respondent Nos. 2 and 3. Inspite of going
through so much trouble, there was no response from respondent Nos. 2 and 3.
4.2 It was further submitted that upon enquiry, the petitioner was informed
that respondent No.3, employees of respondent No.2 and officials of respondent
No.4 had colluded and closed sixteen (16) bank guarantees without any notice
and intimation to the petitioner and a police complaint was filed vide FIR No.
791/2021 dated 08.07.2021 before Madhapur Guttala P.S., Cyberabad. The said
complaint was registered in respect of the illegally closed bank guarantees. No
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
further details were provided by the respondent Nos. 2 and 3 and no payment
was made inspite of the fact that the petitioner had brought all the 21 original
bank guarantees for verification and officers of the respondent Nos. 2 and 3
were fully satisfied after verifying the original bank guarantees. Admittedly, the
ongoing investigation was only in respect of the illegally closed bank guarantees
and not in respect of the live bank guarantees. The respondent Nos. 2 and 3
were under obligation to fulfill the promise made otherwise such illegal
omissions would squarely amount to arbitrary and illegal actions colored with
malafides. Notwithstanding the enquiries and pending police investigation, the
respondent Nos. 2 and 3 were under an immediate obligation to release the
amounts against the bank guarantees which had been submitted for encashment.
The petitioner was restricting his claim to the live bank guarantees (5 in No.) for
Rs.7,15,00,000/- and reserves all his rights to pursue his remedies in relation to
the illegally closed bank guarantees (11 in No.) for Rs. 16,61,58,250/-. The
petitioner had given more than two months notice and requested the respondent
Nos. 2 and 3 to comply with their promise and obligations but they continued to
ignore the petitioner's request. The respondent Nos. 2 and 3 had not disputed
the petitioner's claim under the live bank guarantees for Rs. 7,15,00,000/- in any
way till date. The petitioner issued a legal notice dated 11.08.2021 calling upon
respondent No. 2 to immediately process and encash the sixteen (16) bank
guarantees for a total sum of Rs. 23,76,58,250/- but the respondent Nos. 2 and 3
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
had not replied to the same. Having given adequate opportunity to the
respondent No.2, the petitioner addressed a letter to the Reserve Bank of India
i.e., respondent No.1 to direct the respondent Nos. 2 and 3 to act in accordance
with good banking practices and to comply with its obligations. The
Respondent No.1 had not taken action. The failure of the respondent Nos. 2 and
3 to act in accordance with the terms and conditions of the bank guarantees was
causing grave and irreparable harm and injury.
4.3 He also relied upon the judgment of the Hon'ble Apex Court in the case
of ABL International Limited v. Export Credit Guarantee Corporation of
India Limited1, wherein it was held that:
"It is clear from the above observations of this Court, once the State or an instrumentality of the State is a party of the contract, it has an obligation in law to act fairly, justly and reasonably which is the requirement of Article 14 of the Constitution of India. Therefore, if by the impugned repudiation of the claim of the appellants the first respondent as on instrumentality of the State has acted in contravention of the above said requirement of Article 14, then we have no hesitation in holding that a writ court can issue suitable directions to set right the arbitrary actions of the first respondent".
5. The learned senior counsel Sri. S. Ravi representing the respondent Nos. 2
and 3 submitted that the prayer in the writ petition was completely different with
the prayer sought for by the learned counsel for the petitioners as there was no
prayer in the writ petition even to honor the bank guarantees.
(2004) 3 SCC 553
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
5.1 He further submitted that the respondent No. 4 was enjoying the credit
facilities from erstwhile Andhra Bank, Madhapur Brach which was
amalgamated with Union Bank of India w.e.f. 01.04.2020. At the request of the
said borrower, the respondent banks sanctioned credit facilities vide sanction
letter dated 05.09.2020 subject to terms and conditions mentioned in the
sanction letter. The respondent bank issued Bank Guarantees for an amount of
Rs.15,00,00,000/- and Secured Overdraft limit of Rs.3,26,00,000/- in total
Rs.18,26,00,000/-. The respondent bank also issued some other bank guarantees
on behalf of the borrower. While the matter stood thus one M/s. OFB Tech. Pvt.
Limited vide e-mail dated 23.06.2021 requested the respondent to confirm
issuance of Bank Guarantee No.128211GL0003821 dated 24.06.2021 for Rs.
2,00,00,000/- with expiry date 23.06.2022. The respondent bank sent reply
stating that the said Bank Guarantee number did not exist and it was not issued
by their branch. On 01.07.2021, the branch had again received e-mail from M/s.
OFB Tech. Pvt. Limited to confirm the Bank Guarantee referred above and the
respondent reiterated that the said bank guarantee was not issued by their
branch. The said M/s. OFB Tech. Pvt. Limited filed a writ petition before the
High Court at New Delhi. In the light of the said development, suspecting
fraud, the respondent bank lodged a complaint dated 08.07.2021 with Station
House Officer, Madhapur, Hyderabad against the said borrower and its
directors. The Station House Officer, Madhapur registered FIR No. 791 of 2021
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
under Section 406, 420, 465, 467, 468 and 471 read with Section 120 of IPC and
took up investigation. During the course of investigation, the said case was
transferred to Central Crime Station, Economic Offences Wing, Hyderabad and
the investigation was pending. The respondent bank also lodged supplementary
complaint dated 07.09.2021 and the same was acknowledged by the CCS-EOW
on 08.09.2021. The respondent bank suspected that there might be nexus in
between the borrower and the beneficiaries to de-fraud the bank and requested
the CCS-EOW to investigate into the matter whether the contracts which were
awarded by the above beneficiaries to the borrower were genuine business
transactions and whether the said beneficiaries had parted money to the
borrower by way of mobilization advance, etc., and whether the borrower had
received the material from the beneficiaries who were supposed to supply the
material to the borrowers. The respondent bank was also having an
apprehension whether the said beneficiaries were holding genuine bank
guarantees issued by the bank or fabricated bank guarantees and therefore
requested the CCS-EOW to call for the original bank guarantees from the
beneficiaries and refer the matter to forensic lab to decide the genuineness of the
said bank guarantees.
5.2 The learned counsel for respondent Nos. 2 and 3 further submitted that
CCS-EOW issued notice to the concerned parties including the beneficiaries
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
referred in the complaint / FIR No. 791 of 2021 under Section 91/160 of Cr.P.C.
and also issued a notice dated 10.08.2021 to the petitioners to appear before the
investigating officer along with the original bank guarantees and relevant
documents and witnesses to examine. The learned counsel further submitted
that the respondent Nos. 2 and 3 strongly suspected that the alleged contract
between the petitioner and the borrower was a non-existing one and no real
work had been allotted by the borrower to the petitioner. The respondent bank
had been induced by the petitioner and borrower by fraud and misrepresentation
to issue the bank guarantee at the first instance to a non-existing contract and the
very bank guarantee issued by the respondent bank was a voidable agreement
under Sections 17, 18 and 19 of the Indian Contract Act and it did not need to be
honoured by the bank. The above transaction would require deep investigation
by the police / investigating agency to find the roots of the fraud and to
investigate whether the beneficiary had obtained the bank guarantees with the
sole purpose of defaulting and whether the borrower and beneficiary had forged
/ fabricated and returned the bank guarantees and were trying to obtain unlawful
gain by invoking a returned bank guarantee. As the above matter was under
investigation by competent authority, any order passed in favor of the petitioner
during investigation would have far reaching consequences on the investigation
and the same would also cause irretrievable injustice to the respondent bank.
The investigating agency / police were required to investigate the persons
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
involved in the above fraud and to determine whether there was any nexus
between the borrower and the beneficiaries and whether the beneficiaries had
really paid the mobilization advance, supplied material, etc., to the borrower and
need to determine which bank guarantee was original and genuine as per the
forensic report. Unless the investigation was completed, the respondent bank
was not in a position to take a decision on the subject matter of invocation of the
bank guarantee as the same would cause irretrievable injustice to the respondent
bank and prayed to dismiss the writ petition.
6. The learned counsel for respondent No.1 submitted that the writ petition
was not maintainable against Reserve Bank of India either in law or on facts of
the case. Reserve Bank of India from time to time had issued various guidelines
and regulatory instructions with respect to bank guarantees as contained in
Master Circular on Guarantees and Co-acceptances dated 09.11.2021. The said
instructions would provide an enabling framework for the issuance of the bank
guarantees by banks in terms of approved policy. The bank guarantees shall
also comply with the general principles of the Indian Contract Act, 1872. The
bank guarantees were structured according to the terms of agreement with
security, maturity and purpose. The terms to be incorporated in the bank
guarantee were decided mutually between the parties i.e., applicant, bank and
beneficiary. In a de-regulated credit environment, being a regulator to banks, it
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
was neither advisable nor feasible for Reserve Bank of India to prescribe
granular details in structuring a guarantee. It was for the concerned parties to
formulate the same, subject to the provisions of the Indian Contract Act. An
enabling framework would also be provided by the Reserve Bank of India. All
customers of the banks were provided with a grievance redressal mechanism in
case, they were aggrieved by non-compliance with the directions or guidelines
issued by Reserve Bank of India. Unless the dispute involved adjudication of
disputed question of facts or law, in case of violation of regulatory prescription
of the Reserve Bank, the customers of the banks could approach the grievance
redressal mechanism provided by the Reserve Bank of India for redressal of
grievance against the banks. There were no specific averments against Reserve
Bank of India. The petitioner could not expect regulatory guidelines on the
terms and conditions required to be incorporated in the bank guarantee. The
petitioner could not call upon the High Court to issue Writ of Mandamus against
the Reserve Bank of India for the relief sought for in the writ petition and prayed
to dismiss the writ petition against the respondent No.1 with costs.
7. The learned counsel for respondent No.4 submitted that only on the office
objections, the respondent No.4 was made as a party to the writ petition. No
relief was claimed against respondent No.4, as such respondent No.4 had not
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
even filed any counter and contended that a writ petition was not maintainable
when fraud was alleged and prayed to dismiss the writ petition.
8. The learned counsel for the petitioners on the other hand contended that
the respondent No.3 bank had lodged a complaint against its own client that is
M/s. Kompass Infrastructure Private Ltd., and its directors, it would, by no
stretch of imagination, prevent the bank from making good on its guarantee and
delivering on its promise. It was shocking to know that the bank had only issued
bank guarantees and till date had not suffered any loss of a single rupee since it
had reneged on its solemn undertaking and guarantee. The said M/s. Kompass
Infrastructure Private Ltd. had undertaken its business contracts by availing
credit facilities from the petitioner. Ultimately, it was the petitioner, who had
suffered loss of approximately Rs. 25,00,00,000/- because of the coalition
between the bank and M/s. Kompass Infrastructure Private Ltd. It was even
more shocking to note that bank had filed complaint on 08.07.2021 and
registered an FIR No.791 of 2021 against M/s. Kompass Infrastructure Private
Ltd., and its director but not against its own officers who colluded and conspired
with M/s. Kompass Infrastructure Private Ltd., and played fraud on the
petitioner causing the petitioner to suffer gross monitory loss. The petitioner
was made a victim of cheating and breach of trust and would reserve his right to
file a police complaint against the officers and management of the bank.
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
8.1 He further contended that the bank after filing the writ petition only with a
malafide and malicious intent to avoid making the payment under the bank
guarantees (both closed and live) filed a supplementary complaint dated
07.09.2021. The pending FIR and investigation had nothing to do with the
petitioner and the same was between the bank and its client i.e., borrower. The
original bank guarantees were still with the petitioner and the bank had no right
to withhold payment in gross violation of Reserve Bank of India guidelines. It
was incorrect to state that there might be some nexus between the petitioner and
respondent No.4. On the contrary, it was the respondent Nos. 3 and 4 who had
colluded and conspired with each other to deprive the petitioner of its money.
8.2 He further contended that on one hand bank had granted bank guarantees
to the petitioner and other parties to a tune of Rs. 60,00,00,000/- . The
beneficiaries included Central Government undertakings, National Small
Industries Corporation Limited, Hindustan Petroleum Corporation Limited. The
bank could not make baseless allegations against the beneficiaries / real victims.
The petitioner was suffering huge loss due to the non-payment of the bank
guarantees. Mere pendency of investigation would not prevent the bank to
avoid payment under the guarantees.
9. The learned Senior Counsel for respondents 2 and 3 further submitted that
the Banks usually would honour the various bank guarantees issued from time to
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
time, if the said bank guarantees were in order. In the present case, as fraud was
suspected and as the matter was under investigation by the CCS-EOW,
Cyberabad, unless the investigation was completed, the respondent bank was not
in a position to take a decision on the subject matter of the invocation of the
bank guarantee.
10. Perused the record. As per the Master Circular issued by the Reserve
Bank of India on 09.11.2021 pertaining to payment of invoked guarantees, it
was stated that:
"Where guarantees are invoked, payment should be made to the beneficiaries without delay and demur. An appropriate procedure for ensuring such immediate honoring of guarantees should be laid down so that there is no delay on the pretext that legal advice of approval of higher authorities is being obtained".
"Delays on the part of banks in honoring the guarantees when invoked tend to erode the value of the bank guarantees, the sanctity of the scheme of guarantees and image of banks. It also provides an opportunity to parties to take recourse to courts and obtain injunction orders. In the case of guarantees in favor of government departments, this not only delays the revenue collection efforts but also gives an erroneous impression that banks are actively in collusion with the parties, which tarnishes the image of the banking system".
"There should be an effective system to ensure that the persons on whose behalf the guarantees are issued will be in a position to perform their obligations in the case of performance guarantees and honor their commitments out of their own resources, as and when needed, in the case of financial guarantees".
11. The learned counsel for the petitioner also relied upon several judgments
of the Hon'ble Apex Court. In this regard, he relied upon the judgment of the
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
Hon'ble Apex Court in Standard Chartered Bank v. Heavy Engineering
Corporation Limited and another2, wherein it was held that:
"As per the precedents laid down by this Court, the question of law is no more res integra and is well settled that the bank guarantee is an independent contract between the bank and beneficiary and bank is always obliged to honor its guarantee as long as it is an unconditional and irrevocable one. At the same time, the dispute between the beneficiary and the party at whose instance the bank has given the guarantee is immaterial and is of no consequence and only two exceptions to the rule have been carved out. The first is when there is a fraud of which the Bank has notice and a fraud of the beneficiary from which it seeks to benefit. The second exception to the general rule of non-intervention is such when there is an "irretrievable injury" or "irretrievable injustice" that would occur to the bank".
12. He also relied upon the judgment of the Hon'ble Apex Court in Ansal
Engineering Projects Limited v. Tehri Hydro Development Corporation
Limited3, wherein a three-judge bench of the Hon'ble Apex Court held that:
"It is settled law that bank guarantee is an independent and distinct contract between the bank and the beneficiary and is not qualified by the underlying transaction and the validity of the primary contract between the person at whose instance the bank guarantee was given and the beneficiary. Unless fraud or special equity exists, is pleaded and prime facie established by strong evidence as a triable issue, the beneficiary cannot be restrained from encashing the bank guarantee even if dispute between the beneficiary and the person at whose instance the bank guarantee was given by the Bank, had arisen in performance of the contract or execution of the Works undertaken in furtherance thereof. The bank unconditionally and irrevocably promised to pay, on demand, the amount of liability undertaken in the guarantee without any demur or dispute in terms of the bank guarantee. The object behind is to inculcate respect for free flow of commerce and trade and faith in the commercial banking transactions unhedged by pending disputes between the beneficiary and the contractor".
2020 (13) SCC 574
1996 5 SCC 450
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
13. He also relied upon the judgment of the Hon'ble Apex Court in
Hindustan Corporation Limited v. State of Bihar4, wherein a two-judge
bench of the Hon'ble Apex Court held that:
"What is important, therefore, is that the Bank Guarantee should be in unequivocal terms, unconditional and recite that the amount would be paid without demur or objection and irrespective of any dispute that might have cropped up or might have been pending between the beneficiary under the Bank Guarantee or the person on whose behalf the Guarantee was furnished. The terms of the Bank Guarantee are, therefore, extremely material. Since the Bank Guarantee represents an independent contract between the Bank and the beneficiary, both the parties would be bound by the terms thereof. The invocation, therefore, will have to be in accordance with the terms of the Bank Guarantee; or else, the invocation itself would be bad."
14. He also relied upon the judgment of the Hon'ble Apex Court in SBI v.
Mula Sahakari Sakhar Karkhana Limited5, wherein a two-judge bench of the
Hon'ble Apex Court held that:
"It is beyond any cavil that a bank guarantee must be construed on its own terms. It is considered to be a separate transaction". "If a construction, as was suggested by Mr. Naphade, is to be accepted, it would also be open to a banker to put forward a case that absolute and unequivocal bank guarantee should be read as a conditional one having regard to circumstances attending thereto. It is, to our mind, impermissible in law."
15. The settled position in law that emerges from the precedents of this Court
is that the bank guarantee is an independent contract between bank and the
beneficiary and the bank is always obliged to honor its guarantee as long as it is
an unconditional and irrevocable one. The dispute between the beneficiary and
(1999) 8 SCC 436
(2006) 6 SCC 293
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
the party at whose instance the bank has given the guarantee is immaterial and is
of no consequence. The exceptions to this rule is when there is a clear case of
fraud, irretrievable injustice or special equities. The Court ordinarily should not
interfere with the invocation or encashment of the bank guarantee so long as the
invocation is in terms of the bank guarantee.
16. He also relied upon the judgment of the Hon'ble Apex Court in Bank of
India v. Nangia Constructions (I) Pvt. Ltd., and others6 wherein it was held
that:
"It is unfortunate that a nationalized bank is finding excuses for refusing to make the payment on totally untenable and frivolous grounds. The Division Bench was fully justified in making observations regarding the conduct of the nationalized bank. The entire trust, faith and confidence of people depend on the conduct and credibility of the nationalized bank. In the present day world, the national and international commercial transactions largely depend on bank guarantees. In case the banks are permitted to dishonour their commitments by adopting such subterfuges, the entire commercial and business transactions will come to a grinding halt. This principle has been reiterated in large number of cases by this court. We do not deem it appropriate to burden this judgment by reiterating all those judgments".
17. He also relied upon the judgment of the Hon'ble Apex Court in Uttar
Pradesh Federation Ltd., v. Singh Consultants and Engineering (P) Ltd.7,
wherein, while explaining the salient features of letter of credit, it was held
that:
"The letter of credit has been developed over hundreds of years of international trade. It was most commonly used in conjunction with the sale
AIR 2008 SC 2906
(1998) 1 SCC 174
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
of goods between geographically distant parties. It was intended to facilitate the transfer of goods between distant and unfamiliar buyer and seller. It was found difficult for the seller to rely upon the credit of an unknown customer. It was also found difficult for a buyer to pay for goods prior to their delivery. The bank's letter of credit came into existence to bridge this gap. In such transactions, the seller (beneficiary) receives payment from issuing bank when he presents a demand as per terms of the documents. The bank must pay if the documents are in order and the terms of credit are satisfied. The bank, however, was not allowed to determine whether the seller had actually shipped the goods or whether the goods conformed to the requirements of the contract. Any dispute between the buyer and the seller must be settled between themselves. The Courts, however, carved out an exception to this rule of absolute independence. The Courts held that if there has been "fraud in the transaction" the bank could dishonour beneficiary's demand for payment. The Courts have generally permitted dishonour only on the fraud of the beneficiary, not the fraud of somebody else."
18. The learned senior counsel for the respondents also relied upon the same
judgment on the ground that 'fraud unravels all.' It was held that:
"The whole commercial purpose for which the system of confirmed irrevocable documentary credits has been developed in international trade is to give to the seller an assured right to be paid before he parts with control of the goods and that does not permit of any dispute with the buyer as to the performance of the contract of sale being used as a ground for non-payment or reduction or deferment of payment". "To this general statement of principle as to the contractual obligations of the confirming bank to the seller, there is one established exception: that is, where the seller, for the purpose of drawing on the credit, fraudulently presents to the confirming bank documents that contain, expressly or by implication, material representations of fact that to his knowledge are untrue. Although there does not appear among the English authorities any case in which this exception has been applied, it is well established in the American cases, of which the leading or 'landmark' case is Sztejn v. Henry Schroder Banking Corp., [ 1941] 3 1 NYS 2d 631. This judgment of the New York Court of Appeals was referred to with approval by the English Court of Appeal in Edward Owen Engineering Ltd. v. Barclays Bank International Ltd. [1978] 1 All E.R. 979 (1978) QB 159 though this was actually a case about a performance bond under which a bank assumes obligation to a buyer analogous to those assumed by a confirming bank to the seller under a documentary credit. The exception for fraud on the part of the beneficiary seeking to avail himself of the credit is a clear application to the maxim ex trupi cause non oritur actio or if plain English is to be preferred, 'fraud
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
unravels all', the courts will not allow their process to be used by a dishonest person to carry out a fraud."
19. The learned senior counsel for the respondents also relied upon the
judgment of the High Court of Calcutta in AIMS India Private Ltd., and
others v. Indian Bank and others8 on the ground that a writ was not
maintainable in the matters of Bank Guarantees as there was no public law
element involved in it and it would arise out of a contract. It was held therein
that:
"The claim of the petitioner is essentially a money claim. The bank guarantee is a contract between the bankers and the beneficiary. Although the same had been furnished at the instance of the petitioner, it cannot be said that the agreement was a tripartite one".
"This bench was also recently in A.C. Roy and Ors. v. Union of India and Ors. reported in MANU/WB/0035/1995: AIR1995Cal246 relying upon a large number of Supreme Court decisions, decisions of this court as also Patna High Court, enter alia, held that a dispute under a bank guarantee is a private dispute and the same does not involve any public element and, thus no writ is maintainable".
"It was held- "Right to enforce bank guarantee arises out of a contract qua- contract".
"There is no public law element involved in it".
"Thus a writ will not issue in the matter of enforcement of bank guarantee unless there exists a public law element."
20. As seen from the facts of the case, the bank issued 5 Bank Guarantees for
a total amount of Rs.7,15,00,000 i.e, B.G. No.12821IGL0002621 dated
17.04.2021 for an amount of Rs.1,07,50,000, B.G. No. 12821IGL0002721 dated
23.04.2021 for an amount of Rs.92,50,000, B.G. No. 12821IGL0003321 dated
1997 (4) SCC 237
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
20.05.2021 for an amount of Rs.2,15,00,000, B.G No. 12821IGL0003421 dated
07.06.2021 for an amount of Rs.1,50,00,000, B.G, No.12821IGL0003521 dated
07.06.2021 for an amount of Rs.1,50,00,000, for a period of one year in favour
of the petitioner and the bank also issued 11 Bank Guarantees for a sum of
Rs.16,61,58,250/-, total 16 bank guarantees for a total sum of Rs.23,76,58,250/-
in favour of the petitioner. The respondent bank had closed 11 Bank Guarantees
for a sum of Rs.16,61,58,250/- and the other 5 Bank Guarantees for an amount
of Rs.7,15,00,000 are live. The contention of the respondent bank was that one
M/s.OFB Tech. Private Limited inquired about bank guarantee for Rs.2.00
Crores and it sent a reply stating that the said Bank Guarantee did not exist and
it was not issued by their branch but the said M/s OFB Tech. Private Limited
filed a writ petition before the High Court at New Delhi, suspecting foul play the
bank lodged a complaint and the matter was under investigation. The bank also
issued a supplementary complaint on 07.09.2021 requesting the authorities to
investigate into the said matter and to determine who was holding the original
bank guarantee and whether or not the contracts entered between the petitioner
and the beneficiary were genuine or not and had any material being supplied for
the alleged advancement/ mobilization of bank guarantee executed by the
parties.
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
21. Thus the bank was suspecting that the alleged contracts between the
borrower and the beneficiaries were non-existent and no real work had been
allotted by the petitioners to the borrower and that it was induced by the
petitioners and the borrower by fraud and misrepresentation to issue the bank
guarantees at the first instance to a non-existent contract. The contention of the
bank was that if the contract was non-existent, then the bank guarantees issued
by the respondent bank would become voidable under Sections 17, 18 and 19 of
the Indian Contract Act.
22. The record would also disclose that the petitioners had also filed a
complaint before the Banking Ombudsman.
23. When the matters were under investigation and fraud was alleged and the
investigating authorities had to investigate the persons involved in the said fraud
and whether there was any nexus in between the borrower and the beneficiaries
and whether the beneficiaries had really paid the mobilization advance etc. to
the borrower and had to determine which bank guarantee was original and
genuine as per the forensic report and all the parties were suspecting each other
and were contending that they were cheated by others and a supplementary
complaint was lodged by the respondent bank seeking to investigate the role of
the petitioners in the said fraud, it is considered not fit to issue any directions to
the bank to honour both the closed and live bank guarantees.
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
24. In the result, the Writ Petition is dismissed. No order as to costs.
Miscellaneous Petitions pending, if any, shall stand closed.
_____________________ Dr. G. RADHA RANI, J Date: 26.10.2022 NSK
Dr. GRR ,J W.P. Nos.21932 and 28909 of 2021
17.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!