Citation : 2022 Latest Caselaw 6046 Tel
Judgement Date : 22 November, 2022
HON'BLE Smt. JUSTICE P.SREE SUDHA
APPEAL SUIT No.1703 of 2001
JUDGMENT
1. This appeal is directed against the judgment and decree
dated 29.01.2001 passed in O.S.No.9 of 1996 on the file of the
learned Senior Civil Judge, Miryalguda, wherein and whereby
the suit filed by the plaintiff is decreed with proportionate costs
and interest thereon at 12% per annum.
2. The defendant is the appellant and the plaintiff is the
respondent herein. The plaintiff filed a suit against the
defendant for grant of compensation of Rs.5,44,000/- with
interest thereon at 24% per annum from 14.05.1995 till the
date of realisation.
3. The trial Court considering the evidence on record and
also the arguments advanced by both the counsel granted
decree in favour of the plaintiff for an amount of Rs.3,12,410/-
with proportionate costs along with interest thereon at 12% per
annum from the date of gales i.e. 14.05.1995 till the date of
filing the suit i.e. 12.04.1996 and thereafter at 6% per annum
on Rs.3,12,410/- till realisation and the rest of the claim was
dismissed. The defendant was also directed to pay Rs.17,002/-
towards proportionate costs of the suit. Aggrieved by the said
judgment and decree, the defendant in the suit i.e. The New
India Assurance Company Limited, Nalgonda Branch, preferred
this appeal.
4. Heard the learned counsel for the appellant-defendant
and the learned counsel appearing for the respondent-plaintiff.
Perused the record.
5. Learned counsel for the appellant-defendant would
contend that the judgment of the trial Court is contrary to law
and material on record and it erred in granting compensation at
the rate of Rs.3,2,410/- without any basis and also erred in
believing the evidence of P.Ws.1 to 6 and disbelieving the
evidence of D.Ws.1 and 2. Learned counsel would also assert
that the trial Court has not considered the insurance policy
which is marked as Ex.B1 and the judgment under appeal is
not in consideration of the conditions of policy. Learned counsel
would also aver that the trial Court has not believed the report
of the joint survey-Ex.B3, but believed the survey report-Ex.B2
and also the subject matter of the lis has to be referred to the
Arbitrator as per the arbitration clause and lastly contended
that the damages awarded by the trial Court are excessive, and
thus, prayed the Court to set aside the judgment and decree
under appeal.
6. M/s.Miryalguda Groundnut Oil Mill represented by its
Partner filed the suit against the Insurance Company seeking
compensation. The plaintiff would submit that the firm was
dealing in oil business and in that connection the firm obtained
loan of Rs.8,05,000/- from the Andhra Pradesh State Financial
Corporation (APSFC) at Nalgonda Branch for construction of
building and erection of machinery and they were insured with
the defendant Insurance Company bearing Policy
No.161010602947 covering risk under the head Fire-Policy 'C'
on 01.10.1994 and that the said policy is being renewed from
time to time. The plaintiff would further submit that on
14.05.1995 there were heavy rains and gales and as a result of
which the plaintiff sustained huge loss apart from several other
business concerns - Electricity Board, Roads and Buildings
Department and Telephones at Miryalaguda town. Immediately
the plaintiff reported the matter to the APSFC and to the
defendant. On 17.05.1995 the Insurance Company appointed
the Surveyor by name R.L.N.Shastry and he visited the mill and
recorded his findings for the purpose of assessing the loss
caused to the building and machinery. Apart from the
Insurance Company's Surveyor, the plaintiff also appointed one
Surveyor - V.Goverdhan, Junior Engineer in Nagarjuna Sagar
Project at Miryalguda for assessment of damage caused to the
building and machinery and the work-sheet submitted by him
are also filed. The Surveyor sent a letter bearing
No.NIA/1412/MGN dated 24.05.1995 to the plaintiff firm with a
request to send certain papers and the plaintiff firm complied
with the same on 02.06.1995 and also received
acknowledgment. Later, the plaintiff firm waited for a period of
five or six weeks and met the defendant and enquired as to what
happened to the claim and upon which the Manager of the
defendant informed that the Surveyor estimated the loss to an
extent of Rs.3,10,000/- and also showed the report of the
Surveyor to the plaintiff and hence the plaintiff requested the
Manager of the defendant to grant the real loss of Rs.4,37,000/-
sustained by it. Thereafter, the Manager of the defendant
company sent a letter to the Surveyor seeking some more
clarifications and also instructed the plaintiff to meet the
Manager and accordingly, the plaintiff met with the Manager of
the defendant company after one week, but he has not
responded positively. The plaintiff would also assert that after
three days the Manager of the defendant bank accompanied
with another Surveyor-Nageswara Rao visited the plaintiff firm
to assess the loss. The plaintiff informed the joint surveyor that
the damage to the machinery and building was taken place
about two months back and he got it repaired by investing more
than Rs.4,00,000/- as he could not run the firm without getting
them repaired and he has obtained loan from SFC. The joint
surveyor did not see the photographs shown by the plaintiff and
did not even enquire with any of the neighbours and he was in
the mill only for one hour and he informed to the plaintiff that
he may get the claim of Rs.30,000/- towards damages. After
visiting of the joint surveyor the plaintiff ventilated its grievance
before the Senior Divisional Manager of the defendant company
and he sent a reply asking the plaintiff to obtain a certificate
from the Meteorological Department at Hyderabad confirming
that there was heavy gale in Miryalaguda on 14.05.1995. On 2nd
week of September, 1995 the Branch Manager of the defendant
company sent a letter along with discharge voucher settling the
loss at Rs.30,368/-. The plaintiff firm did not return the loss
voucher as it wanted to contest the matter before the Court. The
Branch Manager also sent another letter on 02.11.1995
instructing the plaintiff that if he fails to return the discharge
voucher within fifteen days from the date of receipt of the said
letter, the claim of plaintiff firm will be treated as closed. The
letter and voucher were filed by the plaintiff before the Court.
On 28.02.1996 the plaintiff got issued a legal notice to the
Branch Manager of the defendant company requesting for
supply of copies of the report of the surveyors but in spite of
receiving the notice the defendant company neither supplied the
copies nor replied to the notice. APSFC also took a policy for an
amount of Rs.8,50,000/- to protect its own interest over the
loan amount and the policy was taken on its own accord
without consulting the plaintiff firm. The plaintiff suffered loss
of Rs.5,44,000/- towards damage to the plant and machinery
including building Rs.4,37,000/- loss of Rs.45,000/- towards
non-functioning of the mill during the period from 14.05.1995
to 30.06.1995 and loss caused to the groundnut stock due to
the non-functioning of the mill is Rs.36,000/- along with the
interest paid to the creditors at the rate of Rs.6,000/- and
therefore the plaintiff filed the present suit for recovery of the
aforesaid amounts.
7. The defendant in his written statement denied the
contentions and submitted that the person who signed the
plaint is not competent. Initially the surveyor was appointed to
conduct survey but he did not consider the following aspects
while submitting the report:
a) The policy issued is a fire-C with F.S.T. extension and the policy was not issued on re-instatement value clause. The surveyor has not applied the relevant depreciations and considered the loss on replacement value contrary to the agreed conditions of the policy.
b) The surveyor has not given the dimensions of the building in the Mill premises and has not worked out the total value of the buildings. From the lay out planned it is noticed that total plinth area as per the dimensions of the different worked out at around 611 sq. meters. As such the total value is more than the value declared by the plaintiff on which basis the premium was calculated and collected. If the correct calculations are made there is an under insurance.
c) Similarly the surveyor's assessment in case of under-insurance of the machinery does not give the details of all the machineries with reference to the same insured.
and as such another surveyor was appointed to assess the loss
afresh and accordingly joint survey was conducted by both the
surveyors. In the joint survey the repairs done to the plaintiff
firm was also considered and the loss was rightly assessed for
an amount of Rs.30,368/- and thus the defendant company
offered the said amount and stated that they are ready and
willing to release the said amount on submission of the
vouchers by the plaintiff. The defendant also stated that there is
an arbitration clause in the policy and as such suit is not
maintainable and moreover suit is to be filed in a Court having
jurisdiction where the regional office is located and thus the
Court has no territorial jurisdiction and further stated that the
Court has no jurisdiction to award interest on unliquidated
damages.
8. The plaintiff examined himself as P.W.1 and also
examined the mechanic, mason, gumatha, hamali and an
independent witness as P.Ws.2 to 6 on his behalf. He filed
Exs.A1 to A19. The Branch Manager of the defendant company
was examined as D.W.1 and he examined the first surveyor as
D.W.2 and marked Exs.B1 to B6.
9. The plaintiff firm was registered by Registrar of the firms
on 27.06.1991 and filed the Xerox copy of the acknowledgment
dated 12.04.1996 and it clearly shows that the plaintiff is a
registered partnership firm. They also filed the newspaper under
Ex.A1 dated 16.05.1995 to prove the heavy gales in Miryalaguda
town on 14.05.1995 but the insurance company insisted the
plaintiff to obtain a certified copy from the Metrological
Department after conducting of the survey at a later date only to
harass the plaintiff. The letter was also addressed under Ex.A6
on 26.07.1995 and when he approached the concerned office
they stated that the barrow meter was taken away by somebody
and they noticed it only on 06.05.1995 and to that effect they
gave certificate. When there were no gales on 14.05.1995, the
defendant would not have appointed the surveyor D.W.2 to
proceed to the spot and estimate the damages. The Branch
Manager in his evidence deposed that there was under
insurance of the policy and as such in the event of loss the
company pays rateable proportion of loss and as such they
appointed a joint surveyor and rightly assessed the
compensation as Rs.30,368/-. He also admitted that they have
not filed the discrepancies found by the surveyors in the report
of the D.W.2. D.W.2 in his evidence stated that he considered
partial under insurance in respect of plant and machinery in his
report Ex.B2 and the loss and damage assessed by him is
correct. The joint surveyor has not collected the copy of the
policy before proceeding to the plaintiff firm and he has not even
collected the same from the head office before preparing the
report. In fact the said surveyor visited the places of damage for
several times and submitted his report and that no report was
reversed or required any joint survey. In this case only the
defendant company wanted to have joint survey for the reasons
best known to it. The photographs of the damaged plant and
machinery were taken by the surveyor-D.W.2 and in his report
he clearly stated that damage was caused to the machinery,
walls, roofs etc., and the roof collapsed and the debris were
lying throughout the plant and machinery and hence it is
necessary to change some of the equipment of the machinery
but the joint surveyor in his report stated that the damaged
items can be replaced with minor repairs and gave report under
Ex.P3.
10. The trial Court considering the entire evidence on record
rightly arrived to the conclusion that the plaintiff is entitled to
compensation of Rs.3,12,410/- as assessed by D.W.2 in his first
survey report and granted the amount along with interest and it
was also stated that the amount assessed by the surveyor is not
disputed by the plaintiff firm and as such the matter cannot be
referred to the arbitrator and the plaintiff rightly filed suit before
the civil Court. It was also observed by the trial Court that if
there are any irregularities in the procedural aspects by the
surveyors of the defendant company, P.W.1 cannot be
penalised. Moreover, the defendant did not opt for any arbitrator
and as such the plaintiff rightly approached the civil Court for
redressal. The counsel for the insurance company would submit
that the plaintiff is entitled for compensation at Rs.30,000/-
and odd as per Ex.B3. The trial Court after analysing the entire
evidence on record rightly arrived to the conclusion for grant of
compensation to an extent of Rs.3,12,410/- and there is no
infirmity in the judgment of the trial Court. Therefore, this
Court finds no reason to interfere with the judgment of the trial
Court.
11. In the result, the appeal merits no consideration and is
dismissed with costs confirming the judgment of the trial Court.
12. Miscellaneous Petitions, if any, pending in this revision
shall stand dismissed in the light of this final order.
____________________ P.SREE SUDHA, J.
22nd NOVEMBER, 2022.
PGS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!