Citation : 2022 Latest Caselaw 3017 Tel
Judgement Date : 23 June, 2022
HON'BLE SRI JUSTICE P.NAVEEN RAO
AND
HON'BLE SRI JUSTICE SAMBASIVARAO NAIDU
CIVIL MISCELLANEOUS APPEAL No.341 OF 2021
Date:23.06.2022
Between:
Linden Projects (P) Ltd,
Having its registered office at
Flat No.1003, H.NO.6-3-787, Royal Pavilion,
Amberpet, Hyderabad
Rep., by its Managing Director,
Varun Jupally, S/o.J. Krishna Rao,
Aged about 38 yrs, Occu : Business,
R/o.Plot No.110, Ambience Fort,
Attapur, Rajendranagar Mandal,
R.R.District
Now known as M/s. Levonor Projects Private Ltd.
.....Appellant
And
K. Janardhan Reddy S/o.Raji Reddy,
Aged about 59 yrs, Occu : Agriculture,
R/o.H.No.4-1-102, Attapur village,
Rajendranagar Mandal, R.R.District & others
.....Respondents
The Court made the following:
HON'BLE SRI JUSTICE P.NAVEEN RAO AND HON'BLE SRI JUSTICE SAMBASIVARAO NAIDU
CIVIL MISCELLANEOUS APPEAL No.341 OF 2021
JUDGMENT : (per Hon'ble Sri Justice P. Naveen Rao)
This appeal is preferred against the order dated 02.07.2021 passed in
Arb.O.P.No.312 of 2020 by the III Additional District Judge, Ranga Reddy
District at L.B.Nagar.
2. The Arbitration application was filed under Section 9 of the Arbitration
& Conciliation Act, 1996 by the respondents/petitioners seeking interim
measure of protection. On elaborate consideration of respective
submissions, the Court below partly allowed the application restraining the
respondent therein from alienating two Villas out of his share of 22 Villas till
the petitioners get clearance/regularization from the competent authority in
respect of Plot Nos.39 to 41. Though elaborate submissions are made, with
the active intervention of learned counsel for the appellant and learned
Senior Counsel appearing for the respondents, the parties have come to an
understanding for resolution of inter se dispute. At this stage, having regard
to the same, we are not recording in detail the controversy involved leading
to filing of this appeal.
3. Suffice to note that a development agreement was entered into
between the appellant and respondents on 18.06.2012 to develop the
property belonging to the respondents and construct 39 Villas. The
constructed Villas have to be shared in the ratio of 45:55 between the
developer and owners. In the said manner, developer gets 22 Villas and the
owners get 17 Villas. The owners are disturbed by the fact that three Villas
on land covered by Sy.No.116 are not being developed, whereas, the
developer is disposing of all the 22 Villas allotted to him and in such a case,
grave prejudice would be caused to the owners of land if these three Villas
are not developed.
4. The stand of the appellant/developer is that originally the developer
was not informed that the land in Sy.No.116 is a surplus land. But when
steps are being taken to develop and apply for permission, it turned out that
it was a surplus land. Unless the surplus land is regularized, developer
cannot undertake construction and that is the only reason why the
developer has not taken steps to construct three Villas while undertaking
construction of remaining Villas.
5. The Court is informed that the owners have applied for regularization
of their land in Sy.No.116. Government accordingly accepted the proposal
and issued demand notice on 14.03.2022, directing the owners to pay an
amount of Rs.44,47,500/- for the purpose of regularization of land in three
instalments i.e., on 21.03.2022, 14.07.2022 and 14.10.2022 respectively.
According to learned Senior Counsel appearing for the respondents, the
second instalment was due on 14.07.2022, but the owners have already
paid the second instalment and final instalment is being paid within next 15
days.
6. Having regard to this submission of learned Senior Counsel for the
respondents, learned counsel for the appellant submits that in the event of
payment being made and if Government issues Government Order,
regularizing the land, within one month, the developer shall obtain
permission for construction of three Villas and shall complete construction
of those three Villas within six months from the date of obtaining
permission. Learned counsel also submits that till the construction activity
is completed as stated above, the appellant will not dispose of house plot to
an extent of 200 Sq yards in Sy.No.96 of Attapur Village, Rajendra Nagar
Mandal, Ranga Reddy District which is adjacent to Plot No.42. To that
extent also the deponent clearly asserts in Paragraph No.3 of the affidavit
filed on 06.09.2021 and the same is taken on record.
7. In view thereof, this appeal is disposed of as under :
Subject to the respondents paying balance amount for regularization
of their land in Sy.No.116 and securing orders from the Government, the
appellant shall apply immediately on receiving Government orders
regularizing the land in Sy.No.116 and secure building permission for
construction of three Villas i.e., 39, 40 and 41 in Sy.No.116 of Attapur
Village within one month and shall complete construction within six months
from the date of acquiring permission. Till the three Villas are constructed
and handed over to the respondents, the appellant shall not dispose of 200
Sq yards of plot adjacent to Plot No.42 in Sy.No.96 of Attapur Village.
8. Learned Senior counsel appearing for the respondents points out that
certain Villas are not finished completely and thereby, the respondents are
not able to enjoy the Villas or to deal with them. There appears to be some
more disputes between the parties. If the respondents issue notice on the
appellant indicating the deficiencies noticed by them or unresolved issues,
on service of notice, the appellant shall attend to the same, or respond to the
notice, as expeditiously as possible. It is always open to the parties to work
out their remedies as available in law, in case of any subsequent grievance.
Pending miscellaneous petitions, if any, shall stand closed.
__________________ P.NAVEEN RAO,J
__________________________ SAMBASIVARAO NAIDU,J 23rd June, 2022 Rds
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!