Citation : 2022 Latest Caselaw 4072 Tel
Judgement Date : 8 August, 2022
THE HON'BLE THE CHIEF JUSTICE UJJAL BHUYAN
AND
THE HON'BLE SRI JUSTICE N.V.SHRAVAN KUMAR
WRIT APPEAL Nos.280, 463, 475, 477, 478, 483,
485 of 2022
COMMON JUDGMENT: (Per the Hon'ble the Chief Justice Ujjal Bhuyan)
This common judgment will dispose of all the present
writ appeals.
2. Heard Mr. T.Koteshwara Prasad, learned counsel for
the appellants and Mr. Padma Rao Lakkaraju, learned
counsel appearing for the National Highway Authority of
India (NHAI).
3. All the writ appeals have been filed by different
persons assailing the common judgment and order dated
22.03.2022 passed by the learned Single Judge disposing
of W.P.Nos.18201, 18461, 22024, 24151, 24188, 24749,
25482, 26933 and 26938 of 2021 wherein the appellants
were writ petitioners in the writ petitions.
4. All the writ petitions were filed assailing the award
dated 30.11.2019 passed by the Joint Collector &
Competent Authority for Land Acquisition, N.H.363,
2
Mancherial District contending that the same was passed
without following the due procedure as contemplated
under the Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act,
2013 (briefly, 'the 2013 Act' hereinafter) as amended by the
Telangana Amendment Act, 2016.
5. The writ petitions were contested by the NHAI by
contending that the acquisitions were carried out in
accordance with law. There was no deviation from the
procedure while passing the award.
6. We have heard learned counsel for the parties and
perused the materials on record, including the detailed
order of the learned Single Judge.
7. Learned Single Judge noted that appellants did not
file any title document or revenue record to show that the
subject lands are private patta lands or that appellants are
having right, title or interest over the same. Except for the
structures on the land, no other documents were filed by
3
the appellants to show that they are owners of the subject
land.
8. On the contention of the appellants that NHAI did not
follow the due process of law in the course of land
acquisition, learned Single Judge perused the counter
affidavit filed by NHAI as well as the documents on record
and thereafter came to the conclusion that NHAI had
scrupulously followed the procedure contemplated under
the 2013 Act. Learned Single Judge held as follows:
"Though a specific plea was taken by the petitioners
that the respondents have not followed due process of law in
the process of land acquisition, a perusal of the counter affidavit filed by NHAI as well as the documents filed along with the said counter shows that the official respondents have scrupulously followed the procedure contemplated under the Act. Initially, the Notification under Section 3-A of the Act was issued on 04.01.2018 and the same was published in the local news papers on 11.01.2018 giving 21 days time for filing objections, if any, by the land owners/interested persons. However, no objections were received from the land owners/interested persons within the time stipulated. Therefore, Notification under Section 3D(1) of the Act was issued and the same was published in Gazette No.711 dated 26.02.2018. Thereafter, the Notification under Section 3(G) of the Act was published in the daily news papers on 10.03.2018 informing all the land owners to attend the enquiry on 16.03.2018 at Tahsil Office, Naspur. The persons, who were found to be in possession of the structures as well as fruit
bearing trees, were awarded compensation for the same. As the subject lands were claimed by the Forest Department, land value was not awarded to the petitioners.
Once it is established by the respondent authorities that the procedure as contemplated under the Act has been followed scrupulously and necessary notifications as contemplated under the Act were issued, the petitioners cannot contend that the provisions of the Act were not followed. Moreover, the record reveals that the notifications and publications were published both in the official Gazette as well as in the local news papers. Therefore, the contention of the petitioners that the procedure was not followed is without substance and contrary to the record. Once, the notification is published, it is for the petitioners to file their objections well within the time stipulated in those notifications, but, they cannot seek any relief to consider their objections after the statutory period had elapsed. The petitioners have not disputed these notifications published in the Gazette or the news papers, moreover, once the Award is passed, the direction of again giving an opportunity to the petitioners to have their objections considered does not arise unless the petitioners are able to show that the statutory procedure was not followed at all, which they have failed to do so."
9. Thereafter, learned Single Judge noted that the
award had already been passed and compensation amount
was deposited with the competent authority. Therefore,
learned Single Judge declined to grant the relief sought for
by the appellants. However, it was observed that if the
appellants have any grievance with regard to the quantum
of compensation awarded for the structures, they were
given liberty to approach the competent authority under
Section 3G(5) of the National Highways Act, 1956, within
four weeks. NHAI has been directed to deal with such
application in accordance with the National Highways Act,
1956.
10. Regarding prayer for alternative accommodation,
learned Single Judge noted that State Government had in
principle agreed to provide alternative accommodation and
had directed the Collector, Mancherial to furnish necessary
proposals for rehabilitation of the 201 affected families,
including the appellants, for the purpose of allotting house
sites of 80 square yards each. Noticing that the counter
affidavit of NHAI was silent in this regard, learned Single
Judge directed that in case Collector, Mancherial District,
had not complied with such direction, he should submit
necessary proposals expeditiously, whereafter Government
was directed to pass necessary orders allotting house site
pattas to the affected families, including the appellants.
11. Learned counsel for NHAI submits that such
alternative accommodation has been provided to the 201
families. Barring appellants No.1 and 2 in W.A.No.280 of
2022, most of the appellants have accepted the alternative
accommodation.
12. After thorough verification of the materials on record,
learned Single Judge came to the conclusion that NHAI
had acquired the subject land as per the procedure
contemplated under the National Highways Act, 1956.
Land acquisition is for a public purpose, namely, for
widening of the road. There should be no hindrance to
execution of such work which is of public importance.
13. On due consideration, we do not find any error or
infirmity in the views expressed by the learned Single
Judge. However, the authorities are directed to release the
awarded compensation to the appellants, if not already
released. Further, as observed by the learned Single Judge,
if the appellants are aggrieved by the quantum of
compensation, they can avail their remedy as provided
under the law. We extend the time limit for availing such
remedy by a further period of four weeks from today. That
apart, if any of the appellants have not received alternative
accommodation, Collector, Mancherial District shall do the
needful and ensure that they are provided alternative
accommodation at the earliest and at any rate within a
period of four months from today.
14. Before parting with the record, we may note and
direct that in the event any affected person(s) has not
received compensation, they may also avail their remedies
as provided under the National Highways Act, 1956,
instead of filing writ petitions before this Court.
15. All the writ appeals are accordingly disposed of.
Miscellaneous applications pending, if any, shall
stand closed. However, there shall be no order as to costs.
______________________________________ UJJAL BHUYAN, CJ
______________________________________ N.V.SHRAVAN KUMAR, J
08.08.2022 vs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!