Citation : 2022 Latest Caselaw 2032 Tel
Judgement Date : 20 April, 2022
HON'BLE SMT. JUSTICE LALITHA KANNEGANTI
WRIT PETITION No. 32603 of 2021
O R D E R:
This Writ Petition is filed to declare the action of the
2nd respondent in transferring / assigning the obligations under
the Authorization Agreement dated 26.10.2017 in favour of the
5th respondent as contrary to the Agreement and the same is
illegal, arbitrary, against the principles of natural justice and
violative of Articles 14, 19(1)(g), 21 and 300-A of the
Constitution of India. A consequential direction is sought to set
aside the letter dated 17.11.2021.
2. Learned Senior Counsel Sri A. Sudarshan Reddy
appearing on behalf of M/s Pillix Law Firm submits that the 2nd
respondent had issued tender notification dated 05.10.2016 for
construction of Foot Over Bridges (FOBs.) at various locations of
Hyderabad under PPP mode on a commercial format and along
with the said notification, the 2nd respondent had issued request
for proposal (RFP) by providing standards, specifications, design
guidelines and maintenance and performance standards to be
adhered to by the bidder. It is stated that the petitioner after
verifying the details of the project, which was provided in the
tender notification dated 05.10.2016, had participated in the
competitive bidding and the petitioner was found to be the
preferred bidder as it has quoted the lowest authorization period
for the development of modern FOB. It is also stated that the
petitioner was awarded to execute the construction of FOBs. as
per the Letter of Intent and an agreement was entered on
26.10.2017 for two FOBs. at Sujana Forum Mall and Temple
Bus Stop, Kukatpally. It is stated that the petitioner
commenced the work and completed the structure as per the
standards specifications, designs, guidelines on 16.11.2019
within seven months from the date of handing over the same. It
is stated that further, by letters dated 16.08.2017, 11.01.2018,
09.10.2020 and 01.11.2021, the petitioner had asked
Respondents 3 and 4 to increase the tenure of the authorization
period in view of the project complexities involved as per Article
5, Obligations of Parties, Section 5.1(d) & (e) of the
Authorization Agreement, but for the best reasons known to
Respondents 3 and 4, they did not choose to act upon the
above-said letters. It is stated that the petitioner had invested
huge amounts for completion of project and before the petitioner
could commence commercial operations, COVID-19 pandemic
started and the petitioner suffered huge setbacks in terms of
revenue generation from the project. It is stated that
surprisingly, the petitioner was served with an intimation letter
dated 12.11.2021 wherein it is stated that the 2nd respondent
approved transfer of FOBs. from the administrative control of
Respondents 3 and 4 ie. Project Wing to the 5th respondent i.e.
Advertisement Wing with effect from 10.11.2021. It is further
stated that the FOBs. constructed by the petitioner are now
under the administrative control of the 5th respondent and that
all the matters relating to FOBs. will be dealt with by the 5th
respondent and all the communications pertaining to the said
FOBs. shall only be made with the 5th respondent. Learned
Senior Counsel submits that the said action of Respondents 2 to
4 and the letter issued by the 5th respondent is contrary to the
terms of the Agreement and unilaterally the respondents cannot
alter the terms of the Agreement. It is submitted that as per
clause 17.4(b) of Article 17 of the Authorization Agreement
which reads as under:
" No amendment or modification or waiver of any provision of this Agreement, nor consent to any departure by any of the parties there from shall in any event be valid and effective unless the same is in writing and singed by the parties or their duly authorized representatives especially empowered in this behalf and then such waiver or consent shall be effective only in the specific instance and for the specific purpose for which it is given."
there cannot be waiver of any of the provisions of the
Authorization Agreement nor consent for departure by any of
the parties unless the same is in writing and signed it is not
valid. He submits that the particular action of the respondents
in straightaway issuing this notice is contrary to the said
Agreement. He also relied on clause 11.2(h) of Article 11 and
submits that the rights and interest of the petitioner in the
project will pass to Respondents 2 to 4 after the transfer date
which is on completion of the authorization period. Hence, it is
submitted that the obligation of the parties to the agreement will
be entangled between the parties and cannot be either
transferred or assigned and cannot be transferred in a manner
unknown to law. Learned Senior Counsel relying on the
judgment of the Apex Court in Kapilaben v. Ashok Kumar
Jyantilal Sheth Trough PoaGophalbhai Madhusudan Patel1
submits that the letter impugned in the Writ Petition is not only
in violation of the Agreement but also unethical for the reason
that the 5th respondent who is holding the post of Additional
Commissioner (Advertisements), GHMC is also holding the post
of The Director, Enforcement Vigilance and Disaster
Management and he has levied several challans to the FOBs.
2019 SCC Online SC 1512
alleging the advertisement on the FOBs. as illegal in spite of the
fact that the petitioner is having Authorization Agreement
granted by Respondents 2 to 4. It is submitted that the 5th
respondent was so prejudiced against the petitioner and started
issuing challans on daily basis. The petitioner has challenged
the said challans issued by the 5th respondent by filing several
Writ Petitions before this Court. He submits that in spite of the
categorical findings of the Hon'ble High Court, the 5th
respondent is still continuing to issue challans on the very same
ground. He submits that the action of the 2nd respondent in
transferring / assigning the project FOBs. to the 5th respondent
is completely in violation of the procedural impropriety where
the decision-making authority has failed in its duty to act fairly.
It is submitted that by the impugned proceedings, the
Authorization Agreement is virtually being transferred to the 5th
respondent and the same amounts to novation, hence, the
petitioner has come before this Court.
3. Initially, on 21.12.2021, an interim order was
passed and the impugned proceedings were suspended. Later,
the interim order was extended form time to time.
4. Sri Pasham Krishna Reddy, learned Standing
Counsel for the respondent Corporation filed a detailed counter
affidavit. He submits that construction of FOBs. is completed
and FOBs. are under operation and the 2nd respondent has
instructed to hand over FOBs. to the Advertisement wing for
better monitoring and proper implementation of the
Authorization Agreement. It is stated that the role of
Engineering Department ends with the construction and
commissioning of FOBs. and thereafter, the advertisement wing
is better equipped to monitor the Authorization Agreement,
hence, they have agreed to transfer the Authorization Agreement
form Engineering Wing to Advertisement Wing. It is stated that
the Authorization Agreement is made and executed between the
parties ie. Greater Hyderabad Municipal Corporation and M/s
GMR Ads. and Advertisement Wing is also part of GHMC and
the transfer cannot termed as violation of the terms of the
contract. He further submits that as per the orders of the
Commissioner, GHMC dated 10.11.2021, all the records have
been handed over to the 5th respondent and the petitioner was
intimated about handing over of the records by proceedings
dated 17.11.2021 and in the process, the request of the
petitioner was denied and the petitioner was directed to make
correspondence with the 5th respondent. It is stated that when
the petitioner has misused the FOBs. for advertisement and also
gave vague explanations for the notices issued, the 5th
respondent, who is the Director of EV & DM, GHMC issued
challans for violating the Rules. Learned Standing Counsel
submits that for effective utilization of the officers and staff of
GHMC to bring the regulation of all the FOBs. with
advertisements under a single wing, the 2nd respondent has
instructed the 5th respondent to monitor the maintenance of the
FOBs. with powers conferred under the Greater Hyderabad
Municipal Corporation Act, 1955. It is submitted that by
transferring the administrative control to the Advertisement
Wing, none of the provisions of the Authorization Agreement is
violated or altered. He also relied on the judgment of the
Hon'ble Apex Court in Maharashtra Law Development
Corporation v. State of Maharashtra2 and submitted that the
Court will be concerned with the correctness of the decision
rather than the method to reach such decision. He submits that
the measures adopted by the respondents are proportionate to
the pursued objective and through the impugned decision there
is no effect on the rights, interests and liberties of the petitioner.
Further, relying on the judgment of the Apex Court in M/s Sethi
Auto Service Station v. Delhi Development Authority,
(2011) 15 SCC 616
learned Standing Counsel submits that by transfer of charge
from Respondents 3 and 4 to the 5th respondent neither the
rights and obligations under the Authorization Agreement are
altered nor the petitioner was deprived of any benefit or
advantage, hence, question of legitimate expectation does not
arise. Learned Standing Counsel submits that absolutely there
is no legal and tenable ground to interfere with the order
impugned.
5. The sum and substance of the arguments advanced
on behalf of the learned Senior Counsel is that as per the terms
of the contract, the 4th respondent is the Authority and now the
control has been shifted from the 4th respondent to the 5th
respondent, who is not competent and the said transfer
amounts to violation / altering the terms of contract. There is
no dispute about the proposition that conditions of the
agreement of a contract cannot be unilaterally changed as the
rules of the game cannot be changed after the game starts.
When extensive arguments are advanced by the learned Senior
Counsel, this Court has specifically asked a query - which part
of the agreement / provision / condition says that control of the
FOB is with the Project Wing and now by virtue of the impugned
proceedings it is transferred from Project Wing to the
Advertisement Wing that amounts to change or alteration of the
conditions of the Agreement. Learned Senior Counsel though
relied on several provisions in the agreement, could not point
out what is the violation / alteration of the terms of the
Agreement. It is an admitted fact that the Agreement is between
GHMC and the petitioner. There are several terms in the
Agreement and as per Clause 17 of the Agreement, conditions of
the Agreement cannot be changed and from the entire
Agreement, learned Senior Counsel could not point out that the
project wing of GHMC is specified in any of the conditions. The
Corporation for effective implementation of the said contract
had initially directed the project wing to take care of installation
of FOBs. and now as commissioning of FOBs. is over, for
effective implementation, they wanted this to be under the
administrative control of the Advertisement Wing which has
nothing to do with any of the conditions in the Agreement. It is
only for better administration and for convenience of GHMC.
The petitioner could not make out any ground much less
tenable ground to interfere with the impugned order.
6. The only grievance of the petitioner appears to be
that the Additional Commissioner, who is the 5th respondent
has issued certain challans against the petitioner and they
assumed that if the control is transferred to him, it would cause
some prejudice. That itself cannot be a ground to interfere with
the proceedings impugned in the Writ Petition. This Court do
not find any infirmity in the proceedings, dated 17.11.2021 and
it cannot be termed as alteration or change in the terms and
conditions of the contract. The Writ Petition is therefore, liable
to be dismissed.
7. The Writ Petition is accordingly, dismissed. There
shall be no order as to costs.
8. The miscellaneous Applications, if any shall stand
closed.
___________________________ LALITHA KANNEGANTI, J 20th April 2022
ksld
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!