Citation : 2022 Latest Caselaw 1806 Tel
Judgement Date : 11 April, 2022
THE HONOURABLE SMT JUSTICE P.MADHAVI DEVI
WRIT PETITION No. 2023 & 3374 OF 2022
COMMON ORDER:
In Writ Petition No.2023 of 2022, the petitioner is
seeking a 'Writ of Mandamus' or any appropriate writ declaring
the action of respondent No.3 in not allowing the petitioner to
proceed with the work awarded to the petitioner under the
agreement No.149/2018-19/SE/R&B/KKM dated 31.12.2018
in relation to the construction of BT road from Kaliveru to
Chennapuram from KMs 0/0 to 21/0 in Charla Mandal,
Bhadradri-Kothagudem District, though extension of time was
granted up to February, 2022 without issuing any notice and
following the procedure under Clause 24 of Part-I general
conditions of the contract as illegal and arbitrary and to
further direct the respondent No.3 not to interfere with the
work without following due process of law.
2. In writ petition No.3374 of 2022, the petitioner is seeking
a 'Writ of Mandamus' declaring the action of the respondent
No.3 in issuing a memo No.T3/TS/SEK/R&B/2021-22/2017,
dated 05.01.2022, allotting part of the work i.e., from KM 0/0
to 7/0 in Charla Mandal, Bhadradri-Kothagudem District
covered under the petitioner's agreement L.S.A.B.NO. /2018-
::2::
PMD,J W.P.NO.2023 & 3374_2022
19/SC/R&B/KMM, dated 31.12.2018, to the 5th respondent,
as illegal and arbitrary.
3. The facts of the case leading to the filing of these two writ
petitions are that the petitioner being a special class contractor
has been executing various Government works and he was
awarded the contract of construction of BT road from Kaliveru
to Chennapuram from KM 0/0 to 21/0 in Charla Mandal of
Bhadradri-Kothagudem District, vide agreement No.149/2018-
19/SE/R&B/KKM, dated 31.12.2018 being the successful
bidder.
4. The petitioner submitted that he was supposed to
complete the work by the end of February 2022, as extended
by the respondents. He submitted that the delay in execution
of work was due to local issue which was resolved only in the
month of December 2021 and he had put all his machinery
and material on the site and was continuing with the work and
the 3rd respondent on 06.01.2022 had orally directed the
petitioner to stop the work.
::3::
PMD,J W.P.NO.2023 & 3374_2022
5. According to petitioner, no notice was issued to him, and
even though clause 52 of the agreement prescribes that when
a contract is to be terminated, the petitioner has to be issued a
notice. It is the case of the petitioner that the petitioner should
be made known of the allegations against him before taking
any decision of termination of contract. He submits that no
notice was issued and the petitioner was directed to stop the
construction work.
6. Petitioner filed Writ Petition No.2023 of 2022 and during
the pendency of the same before this court, on 20.01.2022 the
petitioner has received two letters one by registered post and
the other by ordinary post and in the registered post, the
respondent No.4 has sent a letter bearing no.
AB/A2/Contractor Notice/2021-22, dated 06.01.2022, stating
that the same is being issued in continuation with the letter
reference SE/R&B/KMM/AgtNo /2021-22/SC/R&B/KM,
dated 05.01.2022 and on the perusal of the cover, the
petitioner noticed that same was dispatched from the office of
the respondents on 06.01.2022. However, the said cover was
registered only on 19.01.2022. Therefore, the contention of the
respondents that the notice was already issued to the ::4::
PMD,J W.P.NO.2023 & 3374_2022
petitioner and served on the petitioner on 06.01.2022 is
incorrect. In order to buttress the submission that the notice
dated 05.01.2022 was not issued on 06.01.2022, the petitioner
also stated that the letter received under ordinary post
contains a memo No.TS/TS/SEK/R&B/2021-22/1017,dated
05.01.2022, which has been issued by the respondent No.3,
according to which, exercising power under Clause 60 (c) of PS
to A.P.S.S., a part of the work which is stated to have been
withdrawn from the petitioner and entrusted to the respondent
No.5, and in this letter also, there was no reference at all to the
letter dated 06.01.2022 sent through registered post which
was stated to have been dispatched on 05.01.2022. Therefore,
according to him, the letter dated 05.01.2022 is an ante-dated
letter and even the letter dated 06.01.2022 posted on
19.01.2022 is only to cover up the lapses of the respondents.
7. Petitioner submits that though the respondents are
stating the delay caused in completion of contract to be the
reason for entrusting a part of the work to the respondent
No.5, and respondent No.5 was granted time upto 04.09.2022,
to complete the work, whereas the petitioner was allowed time
only upto 28.02.2022, and the petitioner, if permitted would ::5::
PMD,J W.P.NO.2023 & 3374_2022
have completed the contract within the given time. He submits
that the action of the respondents in granting part of the work
to respondent No.5 without terminating the contract with the
petitioner in accordance with the terms and conditions of the
contract is illegal, arbitrary and that it caused imparable loss
to the petitioner.
8. Petitioner placed reliance upon various documents in
support of the contentions that no notice was issued to the
petitioner prior to stopping the work of construction of road
from KM 0/0 to 7/0 in Charla Mandal, Bhadradri-Kothagudem
District.
9. Respondent No.3 has filed a counter-affidavit stating that
the petitioner was required to complete the work of
construction of the road within the extended time February,
2022. He submits that in spite of extension of time and several
notices being given by the respondents to petitioner to
commence the work vide notices dated 11.05.2021,
18.06.2021, 23.06.2021 and the final notice on 16.07.2021,
the petitioner has neither commenced the work nor replied to
the notice issued to him, and therefore the respondents had no ::6::
PMD,J W.P.NO.2023 & 3374_2022
options but to invoke clause 26 of the agreement and had to
entrust the work to the respondent No.5, by withdrawing a
part of the work under clause 60(c) of the PS to A.P.S.S. in
order to provide transportation facilities for the local people
and the police department. Respondent No.3 therefore denied
the allegations made by the petitioner that the entrustment of
the work to the respondent No.5 is without any intention of
causing loss to the petitioner.
10. The respondent No.5 has also filed counter-affidavit
stating that he is a qualified contractor to complete the work
and on entrusting of the work by the respondents to him,
respondent No.5 has commenced the work and the work is in
progress in all respects. It is submitted that the entire
machinery, which is at the site, belongs to the respondent No.5
and the work is going on with rapid speed. He therefore
supports the action of the respondent no.3 in entrusting the
work to him.
11. Learned counsel for the respondents also placed reliance
upon the various decisions to the effect that dispute between
the department and the contractor is purely a private lis and
therefore writ jurisdiction cannot be invoked to resolve such ::7::
PMD,J W.P.NO.2023 & 3374_2022
disputes. He placed particular reliance on the Judgment of the
Hon'ble Supreme Court in the State of Gujarat Vs Meghiji
Pethraj Shah Charitable Trust and Others1 and also order
in Civil Appeal No. 6086 of 2015 dated 14.08.2015, in the case
of the State of Kerala & others Vs. M.K.Jose.
12. Having regard to the rival contentions and the material
on record, it is seen that the dispute is as to whether the
respondent No.3 could have withdrawn certain part of work
from the petitioner and entrusted the same to the respondent
No.5 without following the procedure laid down in various
clauses of the agreement.
13. A Copy of the agreement between the petitioner and the
respondent No.3 is placed at pages 22 to 31 of the writ papers,
while a copy of Standard Bidding document is at pages 32 to
122 of the writ papers. Clause 24 of the Bid Document refers
to Dispute Redressal System, while clause 52 refers to
Termination of Contract. According to clause 52.1, the employer
may terminate the contract if the contractor causes
fundamental breach of the contract, and Clause (e) of 52.2
1994 LF(SC) (894), ::8::
PMD,J W.P.NO.2023 & 3374_2022
specifies that the fundamental breach of contract shall include
delay in the completion of work by the number of days for
which the maximum amount of liquated damages can be paid,
as defined in clause 44.1.
14. Admittedly, the contract which was awarded to the
petitioner was a project sanctioned by the Government of
India, under left wing extremist affected areas, under road
construction project for (RCPLWE Area), Telangana State, and
the work is to be taken up on top priority.
15. It is also not in dispute that the entire work was to be
completed by the petitioner, as per the contract by the end of
the 30.06.2020, but as the respondents could not get the
clearance, the petitioner could not complete the work and
therefore the time got extended upto 28.02.2022.
16. While the petitioner still had time to complete the work,
the official respondents have withdrawn a part of the work by
proceeding dated 06.01.2022. However, the dispute between
the Government and the petitioner appears to be not with
regard to any fulfillment of any statutory obligation by the ::9::
PMD,J W.P.NO.2023 & 3374_2022
respondents, but it is with regard to breach of conditions of
the contract.
17. The Hon'ble Supreme Court in the case of State of
Gujarat Vs. Meghiji Pethraj Shah Charitable Trust and
others cited supra has held that if a matter is governed by the
contract, the writ petition is not maintainable.
The relevant paragraph is reproduced hereunder for
ready reference i.e., paragraph 20 which reads as under:
"We are unable to see any substance in the argument that the termination of arrangement without observing the principle of natural justice (audi alteram partm) is void. The termination is not a quasi-judicial act by any stretch of imagination; hence it was not necessary to observe the principles of natural justice. It is not also an executive or administrative act to attract the duty to act fairly. It was - as has been repeatedly urged by Shri Ramaswamy - a matter governed by a contract/agreement between the parties. If the matter is governed by the contract, the writ petition is not maintainable since it is a public law remedy and is not available in private law field, e.g., where the matter is governed by a non-statutory contract. [In this connection, see Assistant Excise Commissioner & Ors. V. Isaac Peter & Ors., (1994 (2) JT 140 on the relevance of doctrine of fairness in matters governed by contract, arrived at calling ::10::
PMD,J W.P.NO.2023 & 3374_2022
for tenders, auction or by negotiations]. Be that as it may, in view of our opinion on the main question, it is not necessary to pursue this reasoning further.
18. Similar view has also been expressed in the case of State
of Kerala & Others V/s M.K.Jose, at paragraph 13 wherein,
the Hon'ble Supreme court has held as under:
"A writ court should ordinarily not entertain a writ petition, if there is a breach of contract involving disputed questions of fact. The present case clearly indicates that the factual disputes are involved. In State of Bihar v. Jain Plastics and Chemicals Ltd. 1, a two-Judge Bench reiterating the exercise of power under Article 226 of the Constitution in respect of enforcement of contractual obligations has stated:-
It is to be reiterated that writ petition under Article 226 is not the proper proceedings for adjudicating such disputes. Under the law, it was open to the respondent to approach the court of competent jurisdiction for appropriate relief for breach of contract. It is settled law that when an alternative and equally efficacious remedy is open to the litigant, he should be required to pursue that remedy and not invoke the writ jurisdiction of the High Court. Equally, the existence of alternative remedy does not affect the jurisdiction of the court to ::11::
PMD,J W.P.NO.2023 & 3374_2022
issue writ, but ordinarily that would be a good ground in refusing to exercise the discretion under Article 226.In the said case, it has been further observed:-
It is true that many matters could be decided after referring to the contentions raised in the affidavits and counter-affidavits, but that would hardly be a ground for exercise of extraordinary jurisdiction under Article 226 of the Constitution in case of alleged breach of contract. Whether the alleged non-supply of road permits by the appellants would justify breach of contract by the respondent would depend upon facts and evidence and is not required to be decided or dealt with in a writ petition. Such seriously disputed questions or rival claims of the parties with regard to breach of contract are to be investigated and determined on the basis of evidence which may be led by the parties in a properly instituted civil suit rather than by a court exercising prerogative of issuing writs."
Further at paragraph 27, the Supreme Court has held out the
legal points emerging from the said judgment as to the
maintainability of the writ petition.
para 27 read as:
::12::
PMD,J W.P.NO.2023 & 3374_2022
(a) In an appropriate case, a writ petition as against a State
or an instrumentality of a State arising out of a contractual
obligation is maintainable.
(b) Merely because some disputed questions of fact arise for
consideration, same cannot be a ground to refuse to
entertain a writ petition in all cases as a matter or rule.
(c) A writ petition involving a consequential relief of monetary
claim is also maintainable.
While laying down the principle, the Court sounds a word
of caution as under:-
"However, while entertaining an objection as to the maintainability of a writ petition under Article 226 of the Constitution of India, the court should bear in mind the fact that the power to issue prerogative writs under Article 226 of the Constitution is plenary in nature and is not limited by any other provisions of the Constitution. The High Court having regard to the facts of the case, has a discretion to entertain or not to entertain a writ petition. The Court has imposed upon itself certain restrictions in the exercise of this power. (See Whirlpool Corpn. v. Registrar of Trade Marks) And this plenary right of the High Court to issue a prerogative writ will not normally be exercised by the Court to the ::13::
PMD,J W.P.NO.2023 & 3374_2022
exclusion of other available remedies unless such action of the State or its instrumentality is arbitrary and unreasonable so as to violate the constitutional mandate of Article 14 or for other valid and legitimate reasons, for which the Court thinks it necessary to exercise the said jurisdiction".
19. In view of the above decisions of the Supreme Court, this
Court is of the opinion that both the above writ petitions are
not maintainable as the case is with regard to breach of the
contract and involves investigation into various facts, such as
whether notices were in fact issued to the petitioner before
withdrawal of part of the contract and whether the petitioner
had commenced and was carrying on the contract as per the
instructions of the respondent etc. Therefore, this Court is of
the opinion that the petitioner has to approach appropriate
Court for redressal of his grievances.
20. Thus, both the Writ Petitions are accordingly dismissed.
No order as to cost.
::14::
PMD,J W.P.NO.2023 & 3374_2022
21. Miscellaneous applications, pending if any, shall also
stand closed.
____________________ P.MADHAVI DEVI , J
Date: 11-04-2022 SU
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!