Citation : 2021 Latest Caselaw 2274 Tel
Judgement Date : 3 August, 2021
HONOURABLE SRI JUSTICE M.S.RAMACHANDRA RAO
AND
HONOURABLE SRI JUSTICE T.VINOD KUMAR
C.M.A. No.254 of 2021
JUDGMENT: (Per Hon'ble Sri Justice M.S. Ramachandra Rao)
This Appeal is filed under Section 37 of the Arbitration and
Conciliation Act, 1996 (for short 'the Act') challenging the order
dt.30-03-2021 in A.O.P.No.621 of 2019 of the II Additional District
Judge, Ranga Reddy District at L.B. Nagar allowing the application
filed under Section 9 of the Act filed by respondent and granting
injunction against the appellant from alienating or disposing of the
schedule property to others pending disposal of C.M.A.No.496 of
2015 on the file of this Court.
The Background
facts
2. The land in an extent of Ac.10.00 situated in Sy.Nos.251/4 and
252/4 situated at Wattinagulapally village, Rajendranagar Mandal,
Ranga Reddy District originally belonged to the paternal grandmother
of the appellant and she had bequeathed the same to the appellant and
his two brothers under a registered Will dt.22.09.1982.
3. The respondent along with P.Kishan Prasad had come forward
to purchase an extent of Ac.5.00 of land out of the total extent of
Ac.10.00 and paid Rs.30.00 lakhs under a receipt-cum-sale
commitment.
::2::
4. The said land is allegedly affected under G.O.Ms.No.111 issued
by the State Government restricting constructions within a particular
radius of Osman Sagar and Himayathsagar water bodies; and having
come to know the same and after several rounds of deliberations, the
respondent and his associate entered into an Agreement of Mutual
Benefit Settlement dt.06.09.2006 with the appellant and his brothers.
5. Under the said agreement, the parties have agreed to sell the
subject land to the third parties and to share the proceeds thereof and
it was also agreed that any unsold part of land at the end of 9 months
from the date of the Agreement may be registered in favour of the
parties of the second part at a price upto Rs.3.20 crores per acre.
O.P.No.568 of 2007
6. It was contended by appellant that the terms of the Agreement
of Mutual Benefit Settlement did not workout and no sales to the third
parties have taken place nor the respondent and his associate have
come forward for getting the land registered in their name at the price
as agreed upon in the Agreement; and so the respondent and his
associate invoked Section 9 of the Act, and filed O.P.No.568 of 2007
before the I Additional District Judge, Ranga Reddy District at
L.B.Nagar for an interim measure by way of injunction restraining the
respondents therein from alienating the subject land.
7. The said Court passed orders directing maintenance of status
quo.
::3::
8. Thereafter the respondent approached the High Court under
Section 11(6) of the Act for appointment of an Arbitrator and
accordingly, Justice P.L.N. Sarma (Retd) was appointed as an
Arbitrator.
The arbitral award
9. The Arbitrator passed an award dt.10.10.2009 rejecting the
claim of the respondent for specific performance of the agreement
dt.06.09.2006 and merely directed refund of the amount with interest
to the respondent and his associate by the appellant and his brothers.
A.O.P.No.55 of 2010
10. The respondent and his associate challenged the Award by way
in A.O.P.No.55 of 2010 under Section 34 of the Act before the II
Additional District Judge, Ranga Reddy at L.B. Nagar and the same
was allowed by order dt.08.04.2015 setting aside the award, and
holding that the respondent and his assocaite are entitled to claim
specific performance of the contract on depositing the Government
value with goodwill as offered by them.
C.M.A.No.496 of 2015
11. The appellant and his brothers questioned the order
dt.08.04.2015 in A.O.P.No.55 of 2010 in C.M.A.No.496 of 2015
before the High Court ; and an interim order was passed on
27.07.2015 in C.M.A.M.P.No.1002 of 2015 staying the order under ::4::
Appeal, and the said order is still in force and the said Appeal is
pending.
O.P.No.621 of 2019
12. The respondent again filed O.P.No.621 of 2019 invoking
Section 9 of the Act seeking an injunction restraining the appellant
from alienating the schedule lands pending disposal of C.M.A.No.496
of 2015.
13. He pleaded that there were certain transactions during the years
2010 and 2013 by way of Gift Deeds/sale deeds by the appellant and
his brothers and that certain sale deeds were executed by the brothers
of the appellant in his favour in the year 2018, and that there were
some enquiries by third parties for purchase of the schedule land and
so it is necessary to restrain the appellant from making any
alienations.
The stand of the appellant
14. The Appellant opposed A.O.P.No.621 of 2019 raising several
contentions.
15. It was contended therein that Section 9 of the Act is not
maintainable since the Arbitration was over long back and the petition
filed under Section 34 of the Act was also over in 2015 itself, and the
matter is sub judice in C.M.A.No.496 of 2015 and hence any relief to
be sought for is to be sought only in the said C.M.A. and not by way
of an application under Section 9 of the Act. He stated that there is no ::5::
cause of action for the filing the application merely on the basis of
alleged enquiries by third parties. It was also pleaded that the
respondent has collusively purchased certain extents of land from the
brothers of the appellant and was trying to harass the appellant by way
of present application, which is not maintainable.
The order in AOP NO.621 of 2019
16. By order dt.30.03.2021, the Court below allowed A.O.P.No.621
of 2019.
17. It held that after entering into the Agreement of Mutual Benefit
Settlement dt.30.08.2006, the two brothers of the appellant
compromised the issue with the respondent and his associate and in
consequence thereof, the two brothers of appellant executed Exs.P-7
to P-9 registered sale deeds dt.27.12.2018; in view of the same, the
dispute is settled among the respondent and his associate and two
brothers of the appellant; and consequently, no cause of action
survives for the respondent to sue the two brothers of appellant and
also join his associate as a petitioner in A.O.P.No.621 of 2019.
18. It also rejected the contention of the appellant that the
compromise or settlement between the respondent and his associate
on onside and the two brothers of the appellant on another side will
make the Agreement of Mutual Benefit Settlement dt.30.08.2006
unexecutable against the appellant. It relied on Section 44 of the
Indian Contract Act, 1872. It also held that the doctrine of frustration
contained in Section 56 of the said Act is not applicable.
::6::
19. The Court below also referred to Ex.P-5 registered gift
settlement deed dt.01.02.2010 executed by appellant in favour of his
wife, which showed that specific extent of Ac.1.06½ gts and another
land was alienated; that the said land was part of the land which was
the subject matter of Agreement of Mutual Benefit Settlement
dt.30.08.2006; that such an execution of gift deed indicates that there
must have been a partition among the appellant and his brothers, and
that was why even the brothers of the appellant executed Exs.P-7 to P-
9 registered sale deeds on 27.12.2018 in favor of respondent and his
associate.
20. It also took note of the fact that O.P.No.568 of 2007 had got
dismissed for default and the status quo granted therein no longer
survives and the respondent cannot be faulted in filing A.O.P.No.621
of 2019 in seeking interim relief on a new and different cause of
action which accrued on him later i.e. pendency of C.M.A.No.496 of
2015 in this Court.
21. The Court below also noted that in violation of the interim
status quo order granted in O.P.No.568 of 2007, appellant had
executed the registered gift settlement deed Ex.P-5 dt.01.02.2010 in
favour of his own wife, Ex.P-6 registered sale deed dt.27.12.2013 and
Ex.P-10 registered sale deed dt.01.11.2014 to third parties and so
there is justification for respondent in filing A.O.P.No.621 of 2019.
22. Challenging the same, this Appeal is filed.
::7::
The present Appeal
23. Heard Sri V.Srinivas, learned Senior Counsel for
Ms.V.Chitralekha, leaned counsel for appellant and Sri
I.V.Radhakrishna Murthy, learned counsel for respondent.
24. Learned counsel for appellant contended that the Court below
ought not to have granted interim injunction restraining the appellant
from alienating 'A' and 'B' schedule properties since the basis of the
pleading of the appellant is merely an allegation of respondent that
appellant was trying to alienate his share of the property to third
parties and that a neighbouring land ower K.Pratibha had approached
the respondent on 30.10.2019 and made enquiries. He alleged that
even the affidavit of the said neighbouring land owner has not been
filed by respondent to substantiate the said pleading and there is no
basis for the apprehension of respondent that appellant is alienating
the subject property.
25. Learned counsel for respondent refuted the said contention and
supported the order passed by the Court below.
The consideration by the Court
26. We have noted the contentions of both sides.
27. There is no dispute that the property transaction which is
subject matter of Agreement of Mutual Benefit Settlement
dt.30.08.2006 was subject matter of an arbitral award dt.10.10.2009
and the learned Arbitrator had rejected the claim of respondent for ::8::
specific performance of the said agreement and merely directed
refund of the amount to the respondent and his associate by the
appellant and his brothers with interest; that the said award has been
challenged in A.O.P.No.55 of 2010 by the respondent and his
associate under Section 34 of the Act in the Court of the II Additional
District Judge, Ranga Reddy at L.B. Nagar; and the said Court had
passed an order on 08.04.2015 allowing the O.P. and setting aside
Award and holding that respondent and claimants are entitled to
specific performance of award contract on depositing the Government
value with goodwill as offered by them.
28. It is also an admitted fact that the appellant and his brothers
have questioned the order dt.08.04.2015 in A.O.P.No.55 of 2010 in
C.M.A.No.496 of 2015 and this Court had passed an interim order in
C.M.A.M.P.No.1002 of 2015 on 27.07.2015 staying the order passed
in A.O.P.No.55 of 2010.
29. So, the dispute between the appellant and respondent has not
yet attained finality and it would have to be adjudicated in
C.M.A.No.496 of 2015 pending before this Court for the last 6 years.
30. If before adjudication of C.M.A. the appellant is allowed to
make alienations of the subject property, certainly there would be
serious prejudice to the respondent and his associate.
31. The fact that the appellant had executed Ex.P-5 registered gift
settlement deed dt.01.02.2010 in favour of his wife, Ex.P-6 registered
sale deed dt.27.12.2013 and Ex.P-10 registered sale deed ::9::
dt.01.11.2014 in favor of third parties shows that in spite of interim
order granted in A.O.P.No.568 of 2007, the said alienations had been
made by the appellant. Merely because a third party affidavit of
K.Pratibha, neighbouring land owner had not been filed, it cannot be
said that the respondent cannot be granted any relief .
32. In fact the very filing by the appellant of the appeal against the
order dt.30.03.2021 in A.O.P.No.621 of 2019 challenging such a
restraint indicates that the appellant has an intention to sell the subject
property, for otherwise there was no necessity for filing of this appeal
at all.
33. In our considered opinion, preservation of the property pending
disposal of C.M.A.No.496 of 2015 is necessary, and the appellant
cannot be allowed to create third party interests on the subject
property without the dispute being adjudicated in the said CMA.
34. We therefore do not find any merit in the appeal and it is
accordingly dismissed. No costs.
35. Consequently, miscellaneous petitions, pending if any, shall
stand closed.
______________________________ M.S. RAMACHANDRA RAO, J
___________________ T.VINOD KUMAR, J Date: 03-08-2021 Vsv
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!