Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Sikkim Urja Limited vs M/S Abir Infrastructure Pvt. Ltd. And ...
2025 Latest Caselaw 42 Sikkim

Citation : 2025 Latest Caselaw 42 Sikkim
Judgement Date : 30 May, 2025

Sikkim High Court

M/S Sikkim Urja Limited vs M/S Abir Infrastructure Pvt. Ltd. And ... on 30 May, 2025

Author: Bhaskar Raj Pradhan
Bench: Chief Justice, Bhaskar Raj Pradhan
           THE HIGH COURT OF SIKKIM: GANGTOK
                              (Civil Appellate Jurisdiction)
------------------------------------------------------------------------------------------
DIVISION BENCH: THE HON'BLE MR. JUSTICE BISWANATH SOMADDER, CHIEF JUSTICE
                THE HON'BLE MR. JUSTICE BHASKAR RAJ PRADHAN, JUDGE
 ---------------------------------------------------------------------------------------


                            Arb. A. No. 01 of 2024

        Sikkim Urja Limited
        (Formerly: Teesta Urja Limited)
        Through Authorized Representative
        Satyan Sood,
        Executive Director
        (Project & Contractors)
        B2/1A, Africa Ave,
        Safdarjung Enclave,
        New Delhi- 110029.                                              .....     Appellant
                                        Versus

        1. Abir Infrastructure Pvt. Ltd.
        Through its Managing Director,
        Having its office at SF-2,
        Bikaji Cama Bhawan, Bikaji Cama Place,
        New Delhi - 110066.

        2. NVYUGA Engineering Company Ltd.
        Through its Authorised Signatory,
        # 1259, Lakshmi Towers, Road No.36,
        Jubilee Hills,
        Hyderabad - 500033.

        3. SEW Infrastructure Ltd.
        6-3-871, "Snehalata",
        Greenlands Road, Begumpet,
        Hyderabad - 500016 (A.P.)                                         ..... Respondents
        --------------------------------------------------------------------------
         Appeal under section 37 of the Arbitration and Conciliation
                                 Act, 1996
          [against the judgment dated 14.08.2023 passed by the learned Commercial Court,
          Gangtok, in Arbitration Case No. 05 of 2019 in M/s Teesta Urja Ltd., vs. M/s ABIR
                                   Infrastructure Pvt. Ltd. and Ors.]
        --------------------------------------------------------------------------
        Appearance:
        Mr. Anubhav Sinha, Mr. Akshaya Babu V., Mr. Rinzing Dorjee Tamang
        and Mr. Varun Pradhan, Advocates for the Appellant.
                                                                                                         2
                                         Arb. A. No. 01 of 2024
     M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.



Mr. R.S. Sravan Kumar and Mr. Sishir Mothay, Advocates for the
Respondents No. 1 and 3.

Mr. Biswabrata Basu Mallick, Ms Allakha, Mr. Pramit Chhetri and
Mr. Arun Rai, Advocates for the Respondent No.2.
---------------------------------------------------------------------------------------------------------


                         JUDGMENT

( 30th May, 2025 )

Bhaskar Raj Pradhan, J.

This is an appeal preferred under section 37 of the

Arbitration and Conciliation Act, 1996 (for short, the

Arbitration Act). The impugned judgment and order dated

14.08.2023 dismissed the petition filed by M/s Teesta Urja

Ltd. [now, Sikkim Urja Limited (appellant)] under section 34

refusing to interfere with the arbitral award dated

01.10.2019 in favour of the respondents herein.

2. The grounds for interference under section 34 of

the Arbitration Act are limited. When should a Court

interfere under section 34 is clearly defined in the provision

and amply clarified by the Hon‟ble Supreme Court in its

various judgments. On examination of the arbitral award,

we find that the arbitral award is in conflict with the public

policy of India, in that it is in contravention with the

fundamental policy of Indian law. We also find that the

arbitral award is vitiated by patent illegality appearing on

the face of the award. The Arbitral Tribunal has also

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

imposed the liability of payment of cess upon the appellant

although section 3 of the Building and Other Construction

Workers‟ Welfare Cess Act, 1996 (for short, the Cess Act,

1996) mandates that it is the respondent who are liable to

pay it. While determining who is liable to pay the cess, the

Arbitral Tribunal reversed the mandate of the law and

imposed the liability upon the appellant instead. The arbitral

award suffers from the vice of disregarding the two

judgments of the Hon‟ble Supreme Court in A. Prabhakara

Reddy and Company vs. State of Madhya Pradesh and Others1

and M/s Dewan Chand Builders and Contractors vs. Union of

India & Ors.2 Thus, the impugned judgment passed by the

learned Commercial Court while exercising the powers

under section 34 refusing to set aside such an arbitral

award requires to be interfered with. We explain our reasons

hereunder.

3. The claimant before the Arbitral Tribunal was the

consortium of M/s Abir Infrastructure Pvt. Ltd. (respondent

no.1 herein), M/s Navayuga Engineering Co. Ltd.

(respondent no.2 herein) and M/s SEW Infrastructure Ltd.

(respondent no.3 herein). The respondent therein was M/s

Teesta Urja Ltd.

(2016) 1 SCC 600

(2012) 1 SCC 101

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

4. The consortium of the respondents along with

M/s CGGC International Ltd, M/s CKD Hydro Power Pvt.

Ltd, M/s SABIR Dam & Water Works Construction Co., was

awarded the work for Turnkey execution of 1200 MW Teesta

Stage-III of Hydroelectric Project in the State of Sikkim after

a successful bid. For the said purpose various agreements

were executed. The contracts were subject to arbitration for

settlement of disputes. The contract was awarded on

18.04.2007 with subsequent amendments dated

26.05.2007. The contract was signed on 12.09.2007 and the

project completed on 28.02.2017.

5. According to the Arbitral Tribunal, as stated in its

award, the dispute arose with respect to the liability for the

payment of cess under the Cess Act, 1996. Teesta Urja Ltd.

addressed a letter on 29.08.2016 to the respondent no.2

with copies to the respondents no.1 and 3 making demands

of Rs.5.88 crores, Rs. 8.12 crores and Rs.27.39 crores from

the consortium members totalling to Rs.41.39 crores for

cess @1% and required them to pay it from the date of the

contract award on 18.04.2007. This was disputed by the

respondents who invoked the arbitration clause.

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

The statement of claim by the respondents

6. The respondents through their statement of

claims sought to have the letters dated 16.10.2010,

19.05.2014, 12.06.2014, 07.06.2016 and 04.08.2016 and

29.08.2016 issued by the appellant set aside. It also sought

a declaration that 1% cess is not recoverable from the

respondents and in the alternative the 1% cess be added in

the contract price as per the contract between the parties.

The respondents contended that the 1% cess was not

recoverable because the Building and Other Construction

Workers‟ (Regulation of Employment and Conditions of

Service) Act, 1996 (for short, the BOCW Act 1996) and the

Cess Act, 1996 were not operative in Sikkim at the time of

submission of the bid and, therefore, is a subsequent

legislation. It was also contended that clause 49 of the

General Conditions of Contract (for short, the GCC) clearly

showed that any change in the cost to the contractor

(deduction or addition) because of any subsequent change in

law after execution of the contract between the parties, shall

be determined by the engineer in-charge and shall be added

or deducted from the contract price and the engineer shall

notify the contractor accordingly. It was the respondents‟

case that the BOCW Act, 1996 and the Cess Act, 1996 was

implemented in the State of Sikkim only with effect from

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

06.09.2010, although the contract was awarded on

18.04.2007.

The statement of defence by the appellant

7. The appellant filed their statement of defence

contesting the statement of claims of the respondents. It was

submitted that there was no change in law under the

contract. Clause 17.4 of the GCC makes it obligatory upon

the respondent and sub-contractors to abide at all times

with all existing labour enactments and the rules made

thereunder, regulations, notifications and bye laws of the

State or Central Government or local authority and any

other labour law (including rules), regulations, bye laws that

may be passed or notification that may be issued under any

labour law in future either by the State or the Central

Government or the local authority. It was also contended

that clause 17.4 of the GCC clearly stipulated that the

BOCW Act, 1996 and the Cess Act, 1996 were applicable. It

was contended that under clause 33 of the GCC, the

respondents were responsible for payment of all

taxes/duties/levies, etc. It was submitted that the BOCW

Act, 1996 had come into force on 01.03.1996 prior to the

execution of the contract agreement dated 12.09.2007.

Further, the Cess Act, 1996 came into effect in the whole of

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

India on 03.11.1995 and the Government of India (GOI) had

on 26.09.1996 notified the rate of cess to the extent of 1% of

cost of construction incurred by the employer. Thus, both

the BOCW Act, 1996 and the Cess Act, 1996 have come into

effect on 01.03.1996 and 03.11.1995 respectively, much

prior to the date of submission of the price bids, i.e.,

13.02.2007 by the respondents and the execution of the

contract agreement dated 12.09.2007.

The issue framed by the Arbitral Tribunal

8. The issue formulated by the Arbitral Tribunal

was:

"(xv) The whole issue before AT revolves around the point as to whether BOCW Act is a „Change in Law‟ as per the contract between the parties because as per the Claimant this Act has come into force after the period of 30 days of opening of the Claimant‟s bid. If this question is answered in favour of the Claimant, it has to be determined as to who has to bear the cost of Welfare Cess, either the Claimant/Contractor or the Respondent as Establishment."

The award and findings of the Arbitral Tribunal

9. On examination of the BOCW Act, 1996 and the

Cess Act, 1996, the Arbitral Tribunal concluded:

"1. The work under this contract falls in category of "Building or Other Construction Work" as per Definition section 2(1)(a)(d).

2. Respondent is an "establishment" within the meaning of this Act as per Definition section 2(1)(a)(j).

3. The Claimant is an „employer‟ in relation to the Respondent being an „establishment‟ within the meaning of this Act as per Definition section 2(1)(a)(i). Section 7 of BOCW Act provides for Registration of „establishment‟ within a period of 60 days from the commencement.

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

4. The Rule 23(1) of BOCW Rules, 1998 prescribed the manner of making application for registration of establishment.

5. The Cess Act, in its sec. 3(1) provided for the Levy & Collection of Cess at rate not exceeding 2% but not less than one percent of the cost of construction incurred by an employer. The rate or levy of cess was to be specified by notification of the Central Govt. in the Official Gazette from time to time.

6. As per sec. 3(2) of this Act, the aforesaid cess was to be collected from every „employer‟ in such manner and at such rate as may be prescribed.

7. The Central Govt., vide its S.O. 2899 dt. 26.09.1996 notified that the cess @ 1% of the cost of construction incurred by the Employer is to be levied and collected.

8. The Time and Manner of Collection of such cess was prescribed by the Cess Rule (4). The applicable Rule 4(3) in the present matter is reproduced as below:

Notwithstanding the provisions of sub-rule (1) and sub-rule (2), where the levy of cess pertains to building and other construction work of a Government or of a Public Sector Undertaking, such Government or the Public Sector Undertaking shall deduct or cause to be deducted the cess payable at the notified rates from the bills paid for such works."

10. Even while observing as above, the Arbitral

Tribunal considered the failure of the appellant to take steps

to comply with the provisions of the BOCW Act, 1996 and

the Cess Act, 1996 from 2007 till 2010 until the Labour

Department issued the Circular on 06.09.2010 and directed

that it would be the appellant who would be liable to pay the

cess and further that the respondents or any of the

consortium members shall not be made liable to pay the

cess even in the future. The Arbitral Tribunal held that the

fact that the State of Sikkim formulated Rules in the year

2009 and resorted to implementation of the BOCW Act,

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

1996, the Cess Act, 1996 and the Rules made thereunder

from 06.09.2010 only, the levying of cess would amount to

change in law as envisaged in GCC clause 49.

11. The Arbitral Tribunal set aside the respondent‟s

letters dated 16.10.2010, 19.05.2014, 12.06.2014,

07.06.2016, 04.08.2016 and 29.08.2016. The Arbitral

Tribunal also held that the entire cost of cess as and when

assessed by the competent authority for any period with

regard to the contract shall be borne by Teesta Urja Ltd. It

was also held that as no recovery of cess has yet been made

from the respondents the same shall not be made

hereinafter from the respondent and other consortium

members either from their due payments or through

encashment of bank guarantees.

Section 34 petition by M/s Teesta Urja Ltd.

12. Teesta Urja Ltd. filed a petition under section 34

of the Arbitration Act against the arbitral award. The

appellant pleaded that:- the BOCW Act, 1996 came into

effect from 01.03.1996 and the Cess Act, 1996 with effect

from 03.11.1995; On 26.09.1996, the Government of India

notified the rate of cess at 1% of the cost of construction and

all these were notified much prior to the execution of the

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

contract agreement dated 12.09.2007; The appellant pointed

out clause 17.4 of the GCC provided that the respondent

shall abide by all existing labour enactments, rules,

regulations, notifications, etc.; On 06.09.2010, the

Department of Labour, Government of Sikkim (GOS) had

issued a Circular for implementation of the BOCW Act, 1996

and the Cess Act, 1996; On 13.02.2010, the respondents

being the contractors under the contract agreement got

themselves registered with the office of the Registering

Officer, Government of Sikkim under section 3 of the BOCW

Act, 1996; On 06.04.2011, the Department of Labour

directed the appellant to deposit the labour welfare cess

from the cost of construction employed by the employer; On

28.06.2011, the Department of Labour directed the

appellant to submit details of cost of construction incurred

by the employer; On 01.05.2014, the Department of Labour

directed the appellant to deposit the cess to the Sikkim

Building & Other Construction Welfare Board; The appellant

had requested the respondents by its letters dated

20.05.2014, 12.06.2014, 07.06.2016 and 04.08.2016 to

report compliance of the provisions of the BOCW Act, 1996

and the Cess Act, 1996; On 29.08.2016, the appellant once

again requested the respondents to report compliance and if

they failed to do so, deduction of 1% cess of the cost of

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

construction to be done from the bills raised by the

respondents; On 08.09.2016, the respondents denied their

liability stating that it would constitute a change in law and

invoked the provisions of clause 38 of the contract

agreement for settlement of dispute under the contract.

Ultimately, the Arbitral Tribunal constituted, rendered its

award which was challenged on various grounds including

failure to understand the BOCW Act, 1996 and the Cess Act,

1996 and interpret the judgment of the Hon‟ble Supreme

Court in A. Prabhakara Reddy and the Delhi High Court in

Delhi Metro Rail Corporation Limited vs. Simplex Infrastructure

ltd.3

The impugned judgment of the learned Commercial Court

13. The learned Commercial Court vide judgment

dated 14.08.2023 declined to interfere with the arbitral

award by holding that the arbitral award did not contravene

the fundamental policy of Indian law as claimed by Teesta

Urja Ltd. The learned Commercial Court upheld the

reasoning and interpretation of the Arbitral Tribunal and

concluded that even though the BOCW Act, 1996 and the

Cess Act, 1996 had been enforced from 1996 and 1995

respectively, it had not been made operational in Sikkim till

the issuance of the Circular dated 06.09.2010. The learned

(2011) 3 Arb LR 307

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

Commercial Court did not examine who was liable to pay

cess under the Cess Act, 1996 and whether the Arbitral

Tribunal could have reversed the liability of the respondents

as contractor to the appellant.

The appeal under section 37 by the appellant

14. The appellant has preferred the present appeal

under section 37 of the Arbitration Act challenging the

judgment dated 14.08.2023 passed by the learned

Commercial Court. The appellant states that the name of

Teesta Urja Ltd. changed to Sikkim Urja Ltd., w.e.f.,

21.03.2023.

15. Heard learned counsel - Mr. Anubhav Sinha, for

the appellant, Mr. R.S. Sravan Kumar for the respondents

no.1 and 3 and Mr. Biswabrata Basu Mallick for respondent

no.2.

The moot question

16. The moot question that arises for consideration is

whether the respondents were liable to pay the 1% of the

cost of construction as cess under the Cess Act, 1996 and

whether the respondents could have taken advantage of

clause 49 of the GCC as the appellant had failed to deduct

cess from the bills of the respondents till the issuance of the

Circular dated 06.09.2010 by the Labour Department?

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

Consideration The Building and Other Construction Workers' (Regulation of Employment and Conditions of Service) Act, 1996 (the BOCW Act, 1996)

17. The BOCW Act, 1996 dated 19.08.1996 came into

force with retrospective effect from 01.03.1996 throughout

the territory of India. The BOCW Act, 1996 was enacted to

regulate the employment and conditions of service of

buildings and other construction workers and to provide for

their safety, health and welfare measures and for other

matters connected therewith or incidental thereto.

18. Section 2(g), 2(i) and 2 (j) of the BOCW Act, 1996

defines the words „contractor‟, „employer‟ and

„establishment‟, thus:

"2. Definitions.-- .....................................................

(g) "contractor" means a person who undertakes to produce a given result for any establishment, other than a mere supply of goods or articles of manufacture, by the employment of building workers or who supplies building workers for any work of the establishment, and includes a sub-contractor;"

...................................................................

(i) "employer", in relation to an establishment, means the owner thereof, and includes, -

             (i)    ....
             (ii)   ....

(iii) in relation to a building or other construction work carried on by or through a contractor, or by the employment of building workers supplied by a contractor, the contractor;

.................................................................................

(j) "establishment‟ means any establishment belonging to, or under the control of, Government, any body corporate or firm, an individual or association or other body of individuals which or who employs building workers in any building or

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

other construction work; and includes an establishment belonging to a contractor, but does not include an individual who employs such workers in any building or construction work not being more than rupees ten lakhs;"

The Building and Other Construction Workers' Welfare Cess Act, 1996 (the Cess Act, 1996)

19. The Cess Act, 1996 dated 19.08.1996 came into

force with retrospective effect from 03.11.1995. The Cess

Act, 1996 was enacted to provide for the levy and collection

of a cess on the cost of construction incurred by employers

with a view to augmenting the resources of the Building and

Other Construction Workers‟ Welfare Boards constituted

under the BOCW Act, 1996.

20. Section 2(d) provides that words and expressions

used in the Cess Act, 1996 but not defined and defined in

the BOCW Act, 1996 shall have the meanings respectively

assigned to them in the BOCW Act, 1996.

21. Section 3 of the Cess Act, 1996 provided for levy

and collection of cess. It reads:

"3. Levy and collection of cess.--(1) There shall be levied and collected a cess for the purposes of the Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996, at such rate not exceeding two per cent. but not less than one per cent. of the cost of construction employed by an employer, as the Central Government may, by notification in the Official Gazette from time to time specify.

(2) The cess levied under sub-section (1) shall be collected from every employer in such manner and at such time, including deduction at source in relation to a building or other construction work of a Government or of a public sector

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

undertaking or advance collection through a local authority where an approval of such building or other construction work by such local authority is required, as may be prescribed.

(3) The proceeds of the cess collected under sub-section (2) shall be paid by the local authority or the State Government collecting the cess to the Board after deducting the cost of collection of such cess not exceeding one per cent. of the amount collected.

(4) Notwithstanding anything contained in sub-section (1) or sub-section (2), the cess leviable under this Act including payment of such cess in advance may subject to final assessment to be made, be collected at a uniform rate or rates as may be prescribed on the basis of the quantum of the building or other construction work involved."

22. As section 3 of the Cess Act, 1996 provides for

levying and collection of cess from "employer", it would be

relevant to consider who the "employer" is. The word

"employer" is not defined in the Cess Act, 1996. In terms of

section 2(d) of the Cess Act, 1996 when we peruse the

BOCW Act, 1996, section 2(i) defines the word "employer", in

relation to a building or other construction work carried on

by or through a contractor, or by the employment of building

workers supplied by a contractor, the contractor.

GOI Notification dated 26.09.1996 stipulating rate of cess at 1%

23. On 26.09.1996, the Government of India, Ministry

of Labour, notified the rate of cess @ 1% of the cost of

construction incurred by an employer under the Cess Act,

1996.

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

GOS Notification dated 12.09.1997 notifying BOCW Act, 1996 & Cess Act, 1996

24. On 12.09.1997, Gazette Notification was issued

by the Law Department, Government of Sikkim, thereby

notifying the BOCW Act, 1996 and the Cess Act, 1996 in

Sikkim Gazette.

The Building and Other Construction Workers' (Regulation of Employment and Conditions of Service) Central Rules, 1998

25. The Building and Other Construction Workers‟

(Regulation of Employment and Conditions of Service) Central

Rules, 1998 dated 19.11.1998 (for short, the BOCW Central

Rules, 1998) came into force on 19.11.1998. The BOCW

Central Rules, 1998 was made in exercise of the power

conferred under section 62 and section 40 of the BOCW Act,

1996.

The Building and Other Construction Workers' Welfare Cess Rules, 1998

26. The Building and Other Construction Workers‟

Welfare Cess Rules, 1998 (for short, the BOCW Cess Rules,

1998) came into force on 26.03.1998. It was made in

exercise of the power conferred by sub-section (1) of section

14 of the Cess Act, 1996. Rule 4 of the BOCW Cess Rules,

1998 is relevant and quoted below:

"4. Time and manner of collection--(1) The cess levied under sub-section (1) of section 3 of the Act shall be paid by an employer, within thirty days of completion of the

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

construction project or within thirty days of the date on which assessment of cess payable is finalised, whichever is earlier, to the cess collector.

(2) Notwithstanding the provisions of sub-rule (1), where the duration of the project or construction work exceeds one year, cess shall be paid within thirty days of completion of one year from the date of commencement of work and every year thereafter at the notified rates on the cost of construction incurred during the relevant period.

(3) Notwithstanding the provisions of sub-rule (1) and sub-rule (2), where the levy of cess pertains to building and other construction work of a Government or of a Public Sector Undertaking, such Government or the Public Sector undertaking shall deduct or cause to be deducted the cess payable at the notified rates from the bills paid for such works.

(4) Notwithstanding the provisions of sub-rule (1) and sub-rule (2), where the approval of a construction work by a local authority is required, every application for such approval shall be accompanied by a crossed demand draft in favour of the Board and payable at the station at which the Board is located for an amount of cess payable at the notified rates on the estimated cost of construction:

Provided that if the duration of the project is likely to exceed one year, the demand draft may be for the amount of cess payable on cost of construction estimated to be incurred during one year from the date of commencement and further payments of cess due shall be made as per the provisions of sub-rule (2).

(5) An employer may pay in advance an amount of cess calculated on the basis of the estimated cost of construction along with the notice of commencement of work under section 46 of the Main Act by a crossed demand draft in favour of the Board and payable at the station at which the Board is located.

Provided that if the duration of the project is likely to exceed one year, the demand draft may be for the amount of cess payable on cost of construction estimated to be incurred during one year from the date of such commencement and further payment of cess due shall be made as per the provisions of sub-rule (2).

(6) Advance cess paid under sub-rules (3), (4) and (5), shall be adjusted in the final assessment made by the Assessing Officer."

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

Contract Agreement dated 12.09.2007

27. On 12.09.2007, the contract agreement was

executed between M/s Teesta Urja Ltd. on the one part and

M/s Abir Constructions Pvt. Ltd. and M/s Sabir Dam &

Water Works Construction Company on the other part, who

were collectively referred to as the Contractor.

28. Clause 2 of the covenant stated that the contract

consisted of the following documents which are deemed to

be an integral part of the agreement as if herein set out

verbatim and/or if hereto annexed, viz.,

"A. Volume-I

1. Contract Agreement

2. Notification of Award (letter of acceptance)

3. General Conditions of Contract (GCC)

4. Special Conditions of Contract (SCC)

B. Volume-II Owner‟s Requirements/Technical Specifications for Civil Works consisting of:

1. General Technical Specifications

2. Particular Technical Specifications

C. Volume-III

1. Project Profile

2. Tender Drawings

D. Volume-IV Contractor‟s Proposal and any other document forming part of the Contract"

General Conditions of Contract (GCC)

29. Two clauses in the GCC which forms an integral

part of the contract agreement as noted above are important

to examine. The appellant contends that under clause 17.4

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

of the GCC, the Contractor was required to abide by the

BOCW Act, 1996 as well as the Cess Act, 1996. The

respondents on the other hand contend that as per clause

49 of the GCC they were not bound by any change in law

which was effected subsequent to the contract agreement.

These clauses read as under:-

"17.4 During continuance of the Contract, the Contractor and his sub-contractors shall abide at all times by all existing labour enactments and rules made thereunder, regulations, notifications and bye laws of State or Central Government or local authority and any other labour law (including rules), regulations, bye laws that may be passed or notification that may be issued under any labour law in future either by the State or the Central Government or the local authority. The Contractor shall keep the Owner indemnified in cases any action is taken against the Owner by the competent authority on account of contravention by the Contractor of any of the provisions of any Act or rules made thereunder, regulations or notifications including amendments. It the Owner is caused to pay or reimburse, such amounts as may be necessary to cause or observe, or for non-observance of the provisions stipulated in the notifications/byelaws/acts/rules/ regulations including amendments, if any, on the part of the Contractor, the Engineer/Owner shall also have right to recover from the Contractor‟s any bill or security available with the Owner either under this Contract or any other Contract any sum required or estimated to be required for making good the loss or damage suffered by the Owner.

........................................................................................ Salient features of some of the major labour laws that are applicable to construction industry are given below. ..........................................................................................

(xv) The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act 1996 and the Cess Act of 1996 All the establishments who carry on any building or other construction work and employees 10 or more workers are covered under this Act. All such establishments are required to pay cess at rate not exceeding 2% but not less than 1% of the cost of construction as may be notified by the Government. The Employer (Contractor) to whom the Act applies has to obtain a registration certificate from the Registering Officer appointed by the Government.

........................................................................................."

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

49. EFFECT OF CHANGES IN LAW

If, after the date 30 days prior to the latest date for submission of Price Bids for the Contract, i.e. 13.02.2007 there occur in India, changes to any Central or State Statute, Ordinance, Decree, or other Law or any regulation or by-law of any local or other duly constituted authority, or the introduction of any such Central State Statute, Ordinance, Decree, Law, regulation or by-law which causes additional or reduced cost to the Contractor, other than those already covered under „Article 32 -- Price Adjustment and Escalation‟, in the execution of the Contract, such additional or reduced cost shall be determined by the Engineer-in-charge and shall be added to or deducted from the Contract Price and the Engineer shall notify the Contractor accordingly. Notwithstanding the foregoing, such additional or reduced cost shall not be separately paid or credited if the same shall already have been taken into account in the indexing or any inputs to the Price Adjustment Formulae in accordance with the provisions of Article 32 of these conditions and further, adjustment of such additional or reduced cost shall be determined based on the actual, considering the difference of the taxes and duties prevailing as on the date 30 days prior to submission of price bid and as on the date of incurrence. The adjustment will be further subject to the condition that in case the benefits in duties and taxes under EXIM policy or any other policy of the Government are available, the adjustments will be made considering such benefits irrespective of whether the Contractor avails such benefits or not."

GOS Circular dated 06.09.2010

30. On 06.09.2010, the Department of Labour,

Government of Sikkim addressed a Circular to all

Secretaries/Heads of Department of Government of Sikkim

regarding implementation of the BOCW Act, 1996, the Cess

Act, 1996 and their respective Rules. It stated that the State

Government is required to implement the provisions of the

BOCW Act, 1996, the Cess Act, 1996 and their respective

Rules in view of the direction of the Hon‟ble Supreme Court

passed in Writ Petition No. 318 of 2006, as already notified

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

in Sikkim Herald. It also specified that the cess was to be

collected @ of 1% of the cost of construction incurred by an

employer or any executing agency as the case may be. It

clarified that as per Rule 5 of the BOCW Cess Rules, 1998,

the proceeds of the cess collected under Rule 4 shall be

transferred by such Government Office/Establishment as

the case may be to the Building and Other Construction

Welfare Board which has been constituted vide Notification

No.13/DL dated 26.02.2010 and published in the

Extraordinary Gazette No.64 dated 27.02.2010. All

concerned were required to implement the said provision by

deducting the cess from the cost of construction and

forwarded to the Building and Other Construction Welfare

Board. For the purpose of implementation of these Acts, list

of all contractors/establishments registered with the

concerned department including list of

contractors/establishment executing different building and

construction works were required to be forwarded to the

Labour Department indicating the cost of construction of the

work. The Circular further notified that in the event any

contractor/establishment having submitted bill for payment

in connection with execution of building and other

construction work, 1% of the cost of construction is required

to be deducted by the Department before the bills are

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

cleared, being the amount payable as cess in terms of the

provision of Section 3 of the Cess Act, 1996 read with Rule 4

of the BOCW Cess Rules, 1998. It notified that henceforth

all Works Department or any other

Department/Establishment as the case may be while

entering into any agreement with any

Contractor/Establishment for execution of any building and

other construction works including works being executed

departmentally shall in compliance of the provisions of the

BOCW Act, 1996 and the Cess Act, 1996 ensure deduction

@ 1% of the cost of construction as cess.

The Sikkim Building & Other Construction Welfare Board

31. In exercise of the powers conferred by sub-section

(1) and sub-section (3) of section 18 of the BOCW Act, 1996,

the State Government constituted the Sikkim Building &

Other Construction Welfare Board for the purposes of BOCW

Act, 1996 vide Notification dated 26.02.2010 published in

the Sikkim Government Gazette on 27.02.2010.

The Sikkim Building & Other Construction Workers' (Regulation of Employment and Conditions of Service) Rules, 2010

32. The Labour Department, Government of Sikkim,

in exercise of the powers conferred by section 40 and sub-

section (1) of section 62 of the BOCW Act, 1996 issued

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

Notification dated 31.08.2010 published in the Sikkim

Government Gazette on 01.09.2010 making the Sikkim

Building & Other Construction Workers‟ (Regulation of

Employment and Conditions of Service) Rules, 2010 (the

Sikkim Rules, 2010) with effect from 27.02.2009.

33. The learned Commercial Court came to a finding

that the BOCW Act, 1996, the Cess Act, 1996 and the rate of

cess @ 1% of the cost of construction had already been

notified by the Central Government when the contract

agreement was signed by the parties on 12.09.2007. The

respondents do not contest this fact obviously because it is

factually correct. However, the learned Commercial Court

seemed to have been persuaded to take cognizance of the

fact that in spite of the enforcement as above for almost

three years since the execution of the contract agreement

there was no whisper between the parties to implement

those provisions and the appellant was roused to the

situation only when the Labour Department issued the

Circular dated 06.09.2010. The learned Commercial Court

therefore came to the conclusion that although the BOCW

Act, 1996 and the Cess Act, 1996 were already notified as on

12.09.2007, it came to be implemented in the State of

Sikkim only after 06.09.2010 in compliance to the Order of

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

the Hon‟ble Supreme Court, thus, the learned Commercial

Court did not find any flaw in the reasoning of the Arbitral

Tribunal that the concerned provisions came to be

implemented in Sikkim after 06.09.2010. The learned

Commercial Court was of the view that the Arbitral Tribunal

has been supported by the judgment of the Hon‟ble Supreme

Court in Dewan Chand Builders (supra).

34. In Dewan Chand Builders (supra), the Hon‟ble

Supreme Court examined the judgment rendered by the

High Court of Delhi in which it was held that the BOCW Act,

1996, the BOCW Rules, 1998, the Cess Act, 1996 and the

BOCW Cess Rules, 1998 were constitutionally valid and

within the competence of the Parliament as the levy was a

fee referable to Schedule VII List 1 Entry 97 of the

Constitution of India. While doing so, the Hon‟ble Supreme

Court surveyed the relevant provisions of both the Acts and

the Rules. The Hon‟ble Supreme Court was of the view that

from the scheme of the BOCW Act, 1996 its sole aim is the

welfare of building and construction workers, directly

relatable to their constitutionally recognized right to live

with basic human dignity, enshrined in Article 21 of the

Constitution of India. It was held that it envisages a network

of authorities at the Central and State Levels to ensure that

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

the benefit of the legislation is made available to every

building and construction worker, by constituting welfare

boards and clothing them with sufficient powers to ensure

enforcement of the primary purpose of the BOCW Act, 1996.

It was held that the means of generating revenues for

making effective the welfare provisions of the BOCW Act,

1996 is through the Cess Act, 1996. The Hon‟ble Supreme

Court held that it is manifest from the overarching schemes

of the BOCW Act, 1996, the Cess Act, 1996 and the Rules

made thereunder that the sole object is to regulate the

employment and conditions of service of building and other

construction workers, traditionally exploited section in the

society and to provide for their safety, health and other

welfare measures. It was held that the BOCW Act, 1996 and

the Cess Act, 1996 break new ground in that, the liability to

pay cess falls not only on the owner of the building or

establishment, but under Section 2(1)(i)(iii) of the BOCW Act,

1996, the contractor as well. The extension of the liability on

to the contractor is with a view to ensure that, if for any

reason it is not possible to collect cess from the owner of the

building at a stage subsequent to the completion of the

construction, it can be recovered from the contractor. It was

held that the Cess Act, 1996 and the BOCW Cess Rules,

1998 ensure that the cess is collected at source from the

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

bills of the contractors to whom payments are made by the

owner. The Hon‟ble Supreme Court opined that the burden

of cess is passed on from the owner to the contractor.

35. Both the Arbitral Tribunal as well as the learned

Commercial Court referred to the decision of the Hon‟ble

Supreme Court in A. Prabhakara Reddy (supra). The Arbitral

Tribunal concluded that the appellant was duty bound to

collect the cess from the respective running account bills of

the contractor after (a) the Cess Act 1996 and the Rules

came into effect and (b) the Board was constituted. The

Arbitral Tribunal was also of the view that similar view had

been taken by the Hon‟ble Supreme Court in Dewan Chand

Builders (supra). This was not correct as would be clear from

a reading of both the judgments.

36. In A. Prabhakara Reddy (supra), the appellants

therein who were engaged in the business of construction of

buildings, etc. raised a grievance against demand of cess

under the Cess Act, 1996. The agreements of contracts for

construction of projects were finalised and work order

issued to contractors between December 2002 to March

2003. However, Madhya Pradesh Building & Other

Construction Workers Welfare Board (in short, the MP

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

Welfare Board) came to be constructed on 09.04.2003

followed by Gazette Notification on 10.04.2003. Therefore, it

was contended that there could be no provision in the

contracts as to who shall bear the burden of paying cess

under the Cess Act, 1996. It was contended that the

Assistant Labour Commissioner in his letter to the Chief

Engineer of the Project concerned in Jabalpur had

communicated that cess is to be recovered w.e.f.,

01.04.2003. It was therefore contended that no cess could

be levied for the tenders, contracts and work orders for

construction that came into existence before the MP Welfare

Board was constituted on 09.04.2003/10.04.2003. It was

also contended that if demand of cess is made on

construction works undertaken or even contemplated on

account of issue of work order before the constitution of the

MP Welfare Board, then such demand would amount to

making the Cess Act, 1996 operate retrospectively and that

would be unwarranted, illegal and unjust. Repelling this

contention, the Hon‟ble Supreme Court held:

"12. Although the learned Senior Counsel for the appellants had taken us through the entire scheme of the main Act as well as the Cess Act and also the Rules framed thereunder, but nothing helps the appellants' case and in view of the limited issues arising for determination, we do not feel persuaded to go into details of the Cess Act and the Rules unnecessarily. We are of the considered view that after the Cess Act and the Rules came into effect and the Board was constituted, with the notification specifying the rate of cess to be levied upon the cost of construction incurred by the

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

employer already in place, the respondents were duty-bound to collect the cess by raising the demands in respect of the ongoing construction works if the workers in such construction activities were eligible for the benefits under the BOCW Act.

13. The fact that the task of registering the workers and providing them the benefit may take sometime, would not affect the liability to pay the levy as per the Cess Act. Any other interpretation would defeat the rights of the workers whose protection is the principal aim or primary concern and objective of the BOCW Act as well as the Cess Act. Cess is a fee for service and hence, its calculation, as per settled law is not to be strictly in accordance with quid pro quo rule and does not require any mathematical exactitude. The scheme of the BOCW Act, the Cess Act and the Rules warrant that the lawfully imposable cess should be imposed, collected and put in the statutory welfare fund without delay so that the benefits may flow to the eligible workers at the earliest. The scheme of the BOCW Act or the Cess Act does not warrant that unless all the workers are already registered or the welfare fund is duly credited or the welfare measures are made available, no cess can be levied. In other words the service to the workers is not required to be a condition precedent for the levy of the cess. The rendering of welfare services can reasonably be undertaken only after the cess is levied, collected and credited to the welfare fund.

14. We also find no merit in other submission advanced on behalf of the appellants that there is a legal impediment in charging levy on the cost of construction incurred by the employer from a particular period on account of constitution of the Board from a particular date or for any other reason. This argument is fallacious. Such beneficial measures for the welfare of the workers are applicable even to the construction activity which may have commenced before coming into force of the BOCW Act and the Cess Act, if they are subsequently covered by the provisions of these Acts. There can be no legal obstacle in ignoring the construction cost incurred before the cess became leviable by distinguishing it from the cost of construction incurred later, from a date when the Board is available to render service to the building and other construction workers. The levy of cess in these facts and circumstances cannot be faulted for any reason. The demand of cess in the given facts cannot amount to retrospective application of the Cess Act. Hence the appeals must fail."

37. The Hon‟ble Supreme Court in A. Prabhakara

Reddy (supra) also opined that in Dewan Chand Builders

(supra) it had dismissed the challenge to the

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

constitutionality of the Cess Act, 1996 and the Rules framed

thereunder and held that the levy is in fact "fee" and not a

tax.

38. The clear and unequivocal pronouncement of the

Hon‟ble Supreme Court in A. Prabhakara Reddy (supra) as

seen in paragraphs 12, 13 and 14 quoted above and in

Dewan Chand Builders (supra) was unfortunately

misinterpreted by the Arbitral Tribunal in favour of the

respondents who were contractors. The Arbitral Tribunal‟s

conclusion that it would not be proper to charge the

respondents for the cess which had become applicable in the

State of Sikkim in the year 2009-2010 and therefore the

amount of cess should directly be borne by the appellant is

contrary to public policy as the award is contrary to the

fundamental policy of Indian law. It also suffers from patent

illegality which goes to the root of the matter and appears on

the face of the award, is so unfair and unreasonable that it

shocks the conscience of the Court. It was not within the

jurisdiction of the Arbitral Tribunal to give directions for

payment of the cess to the appellant contrary to the liability

imposed by section 3 of the Cess Act, 1996 upon the

respondents and what was not even prayed for by the

respondents. The Arbitral Tribunal travelled beyond the

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

confines of its jurisdiction to arbitrate upon the dispute

raised by the respondents and gave directions contrary to

the Cess Act, 1996. It also suffers from the vice of

disregarding the judgment of the Hon‟ble Supreme Court in

A. Prabhakara Reddy (supra) and Dewan Chand Builders

(supra) which were binding upon the Arbitral Tribunal. The

direction of the Arbitral Tribunal for the appellant to bear

the entire cost of cess and further as no recovery of cess had

been made, the same shall not be made hereinafter from the

respondents and other consortium members either from

their due payments or through encashment of bank

guarantees is contrary to section 3 of the Cess Act, 1996

which mandates that it is to be paid by the respondents as

„contractors‟. This is clear not only from the reading of

section 3 of the Cess Act, 1996 but also from paragraph 17

of the judgment of the Hon‟ble Supreme Court in Dewan

Chand Builders (supra) which unfortunately was ignored by

both the Arbitral Tribunal and the learned Commercial

Court. The said paragraph 17 of Dewan Chand Builders

(supra) reads thus,

"17. It is manifest from the overarching schemes of the BOCW Act, the Cess Act and the Rules made thereunder that their sole object is to regulate the employment and conditions of service of building and other construction workers, traditionally exploited sections in the society and to provide for their safety, health and other welfare measures. The BOCW Act and the Cess Act break new ground in that, the liability to

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

pay cess falls not only on the owner of a building or establishment, but under Section 2(1)(i)(iii) of the BOCW Act

"in relation to a building or other construction work carried on by or through a contractor, or by the employment of building workers supplied by a contractor, the contractor";

The extension of the liability on to the contractor is with a view to ensure that, if for any reason it is not possible to collect cess from the owner of the building at a stage subsequent to the completion of the construction, it can be recovered from the contractor. The Cess Act and the Cess Rules ensure that the cess is collected at source from the bills of the contractors to whom payments are made by the owner. In short, the burden of cess is passed on from the owner to the contractor."

39. The learned Commercial Court instead of

appreciating what was the issue before the Hon‟ble Supreme

Court and the ratio thereof, was swayed by the analogy of a

statement made in the judgment of the Hon‟ble Supreme

Court in Dewan Chand Builders (supra) in paragraph 18

thereof with the present case to come to the conclusion that

even in Sikkim, the State Government implemented the

BOCW Act, 1996 and the Cess Act, 1996 only from

06.09.2010, i.e., the date of issuance of the Circular by the

Labour Department, GOS. For convenience, paragraph 18 of

Dewan Chand Builders (supra) is reproduced below:-

"18. Although both the statutes were enacted in 1996, the Central Government in exercise of its powers under Section 62 of the BOCW Act notified the Delhi Building and Other Construction Workers' (Regulation of Employment and Conditions of Service) Rules, 2002 (for short "the Delhi Rules") vide Notification No. DLC/CLA/BCW/01/19 dated 10-1-2002.

Accordingly, the Government of NCT of Delhi constituted the Delhi Building and Other Construction Workers' Welfare Board vide Notification No. DLC/CLA/BCW/02/596 dated 2-9-2002. Thus, the

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

Cess Act and the Cess Rules are operative in the whole of NCT of Delhi w.e.f. January 2002."

40. As noted earlier, the BOCW Act, 1996 and the

Cess Act, 1996 has come into effect on 01.03.1996 and

03.11.1995 respectively, much prior to the date of

submission of the price bids, i.e., 13.02.2007, by the

respondents and the execution of the contract agreement

dated 12.09.2007. Clause 17.4 including sub-clause (xv)

thereof of the GCC clearly mandated that the respondents as

the contractors shall abide at all times the labour laws

including the BOCW Act, 1996 and the Cess Act, 1996. A

reading of the definition of the words „contractor‟, „employer‟

and „establishment‟ as defined in section 2(g), 2(i) and 2(j)

respectively in the BOCW Act, 1996, along with the Cess

Act, 1996 and the Rules framed thereunder, it becomes

clear that the respondents as contractors were liable to pay

the cess. Section 3 of the Cess Act, 1996 imposed a liability

upon the contractors to pay the cess. Therefore, the

contractors were liable under section 3 of the Cess Act, 1996

from the date of enforcement. On 26.09.1996, the

Government of India, Ministry of Labour notified the rate of

cess @ 1% of the cost of construction incurred by an

employer under the Cess Act, 1996. Thus, the respondents

were liable to pay 1% of the cost of construction, w.e.f., from

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

the date of the contract agreement, i.e., 12.09.2007, as by

then the BOCW Act, 1996, the Cess Act, 1996 as well as the

rate of cess Notification dated 26.09.1996 had already been

enforced. Rule 4 of the BOCW Cess Rules, 1998 which

provides for time and manner of collection of cess when

applied to the facts of this case, it is apparent that the

respondents were liable to pay the cess within thirty days of

completion of one year from the date of commencement of

work and every year thereafter at the notified rates on the

cost of construction incurred during the relevant period till

the completion of the project in 2017.

41. Clause 49 of the GCC clearly stipulates that it is

only changes to any law or the introduction of any such law

which causes additional or reduced cost to the contractor

that would be considered as change in law. In the facts of

the present case, we find that there has been no change in

either the BOCW Act, 1996 or the Cess Act, 1996 or the

Rules framed thereunder. The respondents were fully aware

that under clause 17.4 they were liable to pay the cess.

Section 3 of the Cess Act, 1996 also fixed the liability upon

the respondent as contractors. The rate of cess had also

been fixed in the year 1996 itself and therefore, the

respondents were aware of that too. The coming into force of

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

the Sikkim Rules, 2010, w.e.f., 27.02.2009, would not

change the liability of the respondents to pay the cess. The

constitution of the Sikkim Building & Other Construction

Workers‟ Welfare Board in 2010 also would not change the

situation for the respondents‟ liability under section 3 of the

Cess Act, 1996. The liability under the Cess Act, 1996 to pay

the cess upon the respondents as contractors is not

consequent to the constitution of the Sikkim Building and

other Construction Workers‟ Welfare Board. The failure of

the State Government to take effective steps under the

BOCW Act, 1996, the Cess Act, 1996 and constitute the

Sikkim Building and Other Construction Workers‟ Welfare

Board cannot reverse the liability of the respondents to pay

the cess and impose it upon the appellant.

42. We are of the view that the BOCW Act, 1996, the

Cess Act, 1996 and the Rules framed thereunder constitute

the fundamental policy of Indian law. The objects and

reasons of these enactments make it abundantly clear that

it was a policy of the Government of India to regulate the

services of the building and other construction workers. The

BOCW Act, 1996 was enacted to regulate the employment

and conditions of service of millions of building and other

construction workers and to provide for their safety, health

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

and welfare which was hitherto before one of the most

vulnerable segments of the unorganised labour in our

country. These building and other construction workers‟

work is characterised by their inherent risk to the life and

limb of the workers. The work is also characterised by

casual nature, temporary relationship between employer

and employee, uncertain working hours, lack of basic

amenities and inadequacy of welfare facilities. Similarly, the

Cess Act, 1996 was enacted for the levy and collection of a

cess on the cost of construction incurred by the employers

with a view to augmenting the resources of the Building and

Other Construction Workers‟ Welfare Boards. The Building

and Other Construction Workers‟ Welfare Boards are

constituted under section 18 of the BOCW Act, 1996. The

functions of the Building and Other Construction Workers‟

Welfare Boards are enumerated in section 22 and quite

evidently it is to provide financial and other assistance to the

building and other construction workers. The BOCW Cess

Rules, 1998 provides in rule 3 thereof that for the purpose of

the levy of cess under sub-section (1) of section 3 of the Cess

Act, 1996, the cost of construction shall include expenditure

incurred by an employer in connection with building and

other construction work but shall not include the cost of

land, any compensation paid or payable to a worker or his

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

kin under the Workmen‟s Compensation Act, 1923. Rule 4

thereof is relevant and already reproduced hereinabove. Rule

4 makes the time and manner of collection of cess amply

clear. Therefore, the arbitral award passed by the arbitral

tribunal nullifying the respondents‟ liability to pay cess

under the Cess Act, 1996 violated the fundamental policy of

India by depriving the building and other construction

workers of their benefits under the welfare schemes.

43. The learned Commercial Court failed to examine

the perversity of the award rendered by the Arbitral

Tribunal. The Arbitral Tribunal conclusion to the issue

framed by it is perverse and against the law. The date of

enforcement or coming into force of the BOCW Act, 1996 is

clearly spelt out in section 1(3) thereof, which states that it

shall be deemed to have "come into force on 1st day of March

1996". Thus, the respondents‟ submission that it came into

force after the period of 30 days of opening of the

respondents bid was a non-issue. This Court is of the

opinion that the learned Commercial Court ought to have

set aside the award on the grounds of patent illegality,

contravention with the fundamental policy of Indian law,

and disregarding the judgments of the Hon‟ble Supreme

Court which were all available to it under section 34 of the

M/s Sikkim Urja Ltd. (formerly Teesta Urja Limited) vs. M/s Abir Infrastructure Pvt. Ltd. & Ors.

Arbitration Act. The failure has resulted in perpetuating the

perversity which shocks the conscience of this Court. This

Court, therefore, in exercise of the powers conferred upon it

under section 37 of the Arbitration Act, sets aside the

impugned judgment dated 14.08.2023, passed by the

learned Commercial Court as well as the award passed by

the Arbitral Tribunal.

44. Accordingly, the appeal is allowed and stands

disposed of.

45. In the facts of the present case, we are also of the

considered view that the cost of arbitration including the

present appeal shall be borne by the respondents. It is

accordingly ordered.





     (Bhaskar Raj Pradhan)                                      (Biswanath Somadder)
           Judge                                                     Chief Justice




     Approved for reporting : Yes
     Internet: Yes
bp
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter