Citation : 2026 Latest Caselaw 632 Raj
Judgement Date : 16 January, 2026
[2026:RJ-JD:1638]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
JODHPUR
S.B. Civil First Appeal No. 179/1997
1. The State of Rajasthan through the Collector, Jodhpur
(Rajasthan)
2. The Executive Engineer, 28th Division, I.G.N.P. Phalodi,
District Jodhpur (Raj.)
----Appellants
Versus
M/s Rama Road Career, Basant Bhawan, A/132, Nehru Nagar,
Jaipur (Rajasthan)
----Respondent
For Appellant(s) : Mr. L.K Purohit
For Respondent(s) : None present
HON'BLE MR. JUSTICE MUKESH RAJPUROHIT
Judgment
(i) Arguments concluded on: 12.01.2026
(ii) Judgment reserved on: 12.01.2026
(iii) Full judgment/Operative part: Full judgment
(iv) Judgment pronounced on : .01.2026
1. This civil first appeal under Section 96 of the Code of Civil
Procedure, 1908 has been preferred by the appellants-plaintiffs
against the Judgment and Decree dated 23.07.1997 passed by the
Additional District Judge, Phalodi in Civil Regular Suit No.68/1993
titled as "State of Rajasthan & Anr. vs. M/s Rama Road Career",
whereby civil suit for recovery of Rs. 2,05,882/- filed by the
appellants-plaintiffs was dismissed.
2. The facts which are germane for the present first appeal, in
nutshell, are that appellants-plaintiffs instituted a civil suit for
(Uploaded on 16/01/2026 at 06:05:07 PM)
[2026:RJ-JD:1638] (2 of 11) [CFA-179/1997]
recovery of Rs. 2,05,882/- against the respondent-defendant
before the court of Additional District Judge, Phalodi (hereinafter
referred to as "trial court"), which was registered as Civil Original
Suit No. 68/1993 (State of Rajasthan & Anr. vs. M/s Rama Road
Career). It was pleaded in the suit that as per Contract No. 6 of
the year 1983-84, plaintiffs allotted work of transporting 1250
M.T. cement from Nimbahera to Ramdevra to defendant-firm.
Under the contract, defendant-firm received 5100 bags of cement,
however, due to defendant's act of storing cement bags at Ahinsa
Nagar, Chittorgarh Chungi Naka without authorization, District
Supply Officer, Chittorgarh seized cement on 02.07.1983. The
defendant neither informed plaintiff about seizure nor obtained
prior permission of plaintiffs for storage. Despite repeated
requests by the plaintiffs, defendant failed to complete the
transportation work. By letter dated 20.11.1983, defendant was
informed that if the work was not completed, recovery would be
made at double rates. Since the cement was not transported as
per contract, Executive Engineer, 20th Division, Phalodi, by letter
dated 31.10.1984, requested the District Collector, Jaisalmer to
recover ₹2,05,882/- from defendant-firm. But no action was taken
despite reminders, including a final reminder dated 29.04.1990.
Therefore, present suit was filed by plaintiffs seeking a decree of
₹2,05,882/- along with interest against defendant-firm.
3. Respondent-defendant filed written statement denying
averments made in the suit and pleaded that contract for cement
transportation was under the orders of the Rajasthan Canal
Project, 20th Division and that 5100 bags of cement were
(Uploaded on 16/01/2026 at 06:05:07 PM)
[2026:RJ-JD:1638] (3 of 11) [CFA-179/1997]
dispatched to Ramdevra, required to reach by 30.06.1983. When
consignment reached Chittorgarh, route ahead was found blocked.
Due to compulsion, cement was stored in a rented godown at
Ahinsa Nagar, Chittorgarh. District Supply Officer, Chittorgarh,
illegally seized cement bags on 02.07.1983. Despite efforts, no
cooperation was given by the Executive Engineer, 20 th Division,
Rajasthan Canal Project to get the goods released. Because of the
seizure, timely delivery became impossible. On 10.05.1984,
appellate authority ordered release of the cement but no
departmental representative came for inspection, resulting in
deterioration of cement quality. It was further contended that
delay occurred due to negligence of the State Government and
departmental authorities. In the additional pleas, it was pleaded
that suit was barred by limitation, that Plaintiff No. 2 had no
authority to file the suit and that no person was duly authorized
by the State Government to institute the suit. The defendant
detailed expenses and losses, stating that value of cement was
₹1,70,850/-, freight charges ₹1,41,192/-, legal and seizure-
related expenses ₹5,000/-, godown rent ₹7,500/-, security
deposit ₹25,000/- and chowkidar expenses ₹1,400/-, totaling
₹1,80,092/-. After adjustment of ₹1,70,850/- towards cost of
cement, defendant claimed entitlement to ₹9,242/- from the
plaintiffs and filed a counter-claim accordingly.
4. In rejoinder, it was stated by the plaintiffs that due to
administrative reorganization, 20th Division, Phalodi later came
under the 28th Division, Phalodi, giving Plaintiff No. 2 authority to
file the suit. It was asserted that double freight liability for 5100
(Uploaded on 16/01/2026 at 06:05:07 PM)
[2026:RJ-JD:1638] (4 of 11) [CFA-179/1997]
bags of cement amounted to ₹3,44,250/- and after adjusting
payable amounts of ₹1,38,368/-, a sum of ₹2,05,882/- remained
recoverable from defendant. The plaintiff denied the defendant's
counter-claim.
5. On the basis of pleadings of the parties, trial court framed
following issues on 15.03.1995 & 14.02.1997 as under :-
"1 vk;k oknh }kjk çfroknh dks fuEckgsMk ls jkensojk rd 1250 ,e Vh- lhsesaV <qykbZ dk dk;Z vuqca/k laå 6 o"kZ 1983&84 }kjk vkoafVr fd;k x;k ?
2- vk;k çfroknh us 5100 Fksyk lhesaV dks QSDVªh ls çkIr dj fpÙkkSMx<+ pqaxh ukds vfgalk uxj ¼fpÙkkSMx<½ esa voS/k :i ls Hk.Mkj.k dj fn;k bl dkj.k nkok esa of.kZr vk/kkj ij oknh çfroknh ls 2]05]882@&:0 dh olwyh djus dk vf/kdkjh gS ?
3- vk;k oknh çfroknh ls mä jkf'k ij nk;jh nkok ls rkolwyh 16 çfr'kr okf"kZd dh nj ls C;kt çkIr djus dk vf/kdkjh gS ?
4- vk;k nkok oknh E;kn ckgj gS ?
5- vk;k vuqca/k oknh laå 2 ls ugha gqvk ds dkj.k oknh laå 2 dks nkok djus dk vf/kdkj ugha gS ?
6- vk;k tokc nkok ds c;ku ethn ds iSjk laå 6 esa of.kZr vuqlkj çfroknh QeZ ds Hkkxhnkjku vko';d i{kdkjku gS] ftUgsa i{kdkj cuk;s fcuk nkok pyus ;ksX; ugha gS ?
6,- vk;k çfroknh ds vfrfjä vfHkdFku ds en laå 3 ds vk{ksi vuqlkj oknh dks okn i= ij gLrk{kj djus ds fy, vf/kdkjh ugha Fkk ?
6ch- vk;k çfroknh vfrfjä dFku ds en laå 4 esa of.kZr rF;ksa ds vuqlkj dkmUVj Dyse ds vuqlkj çfroknh oknh ls 9]242@& :i;s çkIr djus dk vf/kdkjh gS ƒ 7- vuqrks"k ?"
6. In support of their case, appellants-plaintiffs examined P.W.1
- Kailash Gaur, P.W.2 - Sitaram, P.W.3 - R.K. Garg, P.W.4 -
Mukhsendra Gupta and P.W.5 - Hanuman Singh. On behalf of the
respondent-defendant firm, D.W.1 - Satish Chandra Gupta was
examined in rebuttal. Upon appreciation of the evidence on
(Uploaded on 16/01/2026 at 06:05:07 PM)
[2026:RJ-JD:1638] (5 of 11) [CFA-179/1997]
record, the trial court decided Issue No. 1 in favour of the
appellants-plaintiffs; Issue Nos. 2, 3, 4 and 5 against appellants-
plaintiffs and in favour of the respondent-defendant and Issue
Nos. 6, 6A and 6B against respondent-defendant. Consequently,
both the civil suit as well as counter-claim were dismissed.
Aggrieved by the findings recorded on Issue Nos. 4 and 5,
appellants-plaintiffs preferred present first appeal.
7. The relevant portion of findings on Issue Nos. 4 and 5 are
reproduced as under :-
"rudh la[;k 4 %& 11- çfroknh QeZ dh rjQ ls çLr`r tokc nkok ds eqrkfcd nkok e;kn ckgj gSA ;g Loh--r rF; gS fd fuEckgsM+k ls jkensojk rd 1250 ,e- Vh- lhesaV dh <qykbZ ls lacaf/kr vuqca/k la[;k 6 o"kZ 1983&84 dh vof/k fnukad 30-6-83 rd FkhA vuqca/k çn'kZ 1 ls Hkh Li"V gksrk gS fd bl vuqca/k dh vof/k fnå 26-3-83 ls 30-6-83 rd FkhA okni= ls Li"V ugha gksrk fd nkok oknhx.k fdl rjg ls e;kn Hkhrj gSA okni= ds iSjk laå 10 esa mYys[k gS fd vf/k'kk"kh vfHk;ark 20 oka [k.M Qyksnh us vius i= fnå 31-10-84 ds }kjk jkf'k olwyh gsrq ftyk/kh'k] tSlyesj dks fy[kk] tgka ls i= fnukad 14-11-84 bl vk{ksi ds lkFk çkIr gqvk fd yksd ekxZ olwyh vf/kfu;e 1952 ds rgr olwyh dk;Zokgh dh tkosaA bl ij vf/k'kk"kh vfHk;ark 20 oka [k.M Qyksnh us olwyh ds laca/k esa i= fnukad 5-11-85 dks ftyk/kh'k] t;iqj dks çsf"kr fd;kA vafre Lej.k i= fnukad 24-9-90 dks çsf"kr fd;k] ysfdu dksbZ tokc çkIr ugha gksus ij nkok is'k djuk iM+kA esjh jk; esa ftyk/kh'k] tSlyesj o ftyk/kh'k] t;iqj dks jkf'k olwyh ds laca/k esa i= fy[ks tkus dk dksbZ vkSfpR; ugha Fkk rFkk bl dk;Zokgh ls ;g nkok e;kn Hkhrj gksuk ugha dgk tk ldrkA ifjlheu vf/kfu;e ds fdlh çko/kku ds rgr oknhx.k us nsjh ekQ fd;s tkus dk fuosnu ugha fd;k gSA bl vf/kfu;e ds vuqPNsn 11 ds rgr Li"V çko/kku gS fd eky okgd ds fo#) {kfriwfrZ ckcr nkok eky fMyhojh dh rkjh[k ls 3 o"kZ ds Hkhrj is'k fd;k tkuk laHko gSA fopkjk/khu ekeys esa Lohd`r :i ls 5100 dês lhesaV jkensojk igqapkus dh vof/k fnå 30-6-83 dks lekIr gks x;h tcfd çkaroknh QeZ ds fo#) ;g nkok fnukad 19-1- 93 dks vR;f/kd nsjh ls is'k fd;k x;k gS ftl nsjh ckcr dksbZ mfpr otg Hkh ugha gSA ekeys dh bu ifjfLFkfr;ksa esa esjh jk; esa nkok oknh Li"Vr% e;kn ckgj gSA ;g rudh oknhx.k ds fo#) ,oa çfroknh QeZ ds i{k esa r; dh tkrh gSA
rudh la[;k 5 %& 12- ;g Hkh Loh--r rF; gS fd dfFkr vuqca/k oknh laå 2 ls ugha gqvkA oknh laå 2 dh rjQ ls çLrqr tokcwy tokc
(Uploaded on 16/01/2026 at 06:05:07 PM)
[2026:RJ-JD:1638] (6 of 11) [CFA-179/1997]
esa ;g mYys[k gS fd dkykUrj esa 20ok [k.M oknh la[;k 2 ds v/khu vk x;k] ysfdu bl laca/k esa dksbZ larks"ktud çek.k oknhx.k dh rjQ ls is'k ugha gqvk gSA oknhx.k dh rjQ ls is'k fd;s x;s fdlh xokg us bl laca/k esa fLFkfr dks Li"V ugha fd;k gSA ih- M- 3 vkj- ds- xxZ rRdkyhu vf/k'kk"kh vfHk;ark 20 oka [k.M us rks vius dFku esa tkfgj fd;k gS fd vHkh vkbZ- th- ,u- ih- dk 20 oka [k.M chdkusj esa gksuk pkfg,A tc jktLFkku ugj ifj;kstuk ds rgr dbZ [k.M gS rFkk çfoZoknh QeZ ds lkFk dfFkr vuqca/k 20 oka [k.M }kjk fd;k x;k rks fdlh rjg dh {kfriwfrZ ls lacaf/kr nkok is'k djus dk vf/kdkj 20 oka [k.M ;k jktLFkku ugj ifj;kstuk dks gh gks ldrk gSA oknh laå 2 ;g nkok is'k djus ds fy, jktLFkku ugj ifj;kstuk ;k dfFkr 20oka [k.M }kjk vf/k--r gksus ckcr i=koyh ij dksbZ vk/kkj ugha gSA ekeys dh ifjfLFkfr;ksa esa es jh jk; esa oknh laå 2 nkok is'k djus ds fy, vf/k--r ugha gS A oknh la[;k 1 jktLFkku jkT; tfj, ftyk/kh'k] tks/kiqj i{kdkj gS] ysfdu çFke rks jktLFkku ugj ifj;kstuk ;k blds v/khu 20 oka [k.M dh rjQ ls nkok is'k djus ds fy, jktLFkku jkT; tfj, ftyk/kh'k] tks/kiqj i{kdkj gksus dk vkSfpR; çrhr ugha gksrk] D;ksafd jktLFkku ugj ifj;kstuk ,d Lora= foHkkx gS] ftldk çfrfuf/kRo jkT; ljdkj dh rjQ ls ftyk/kh'k }kjk ugha fd;k tk ldrk] fnrh; okn i= ij jkT; ljdkj dh rjQ ls ftyk/kh'k] tks/kiqj ds gLrk{kj ugha gS rFkk u gh jkT; ljdkj dh rjQ ls nkok is'k djus ds fy, vf/k'kk"kh vfHk;ark 28 oka [k.M dks vf/k--r fd;s tkus ckcr~ dksbZ vk/kkj i=koyh ij ekStwn gSA ekeys dh ifjfLFkfr;ksa esa esjh jk; esa oknh la[;k 2 nkok is'k djus ds fy, vf/k--r ugha gSA ;g rudh çfroknh QeZ ds i{k esa r; dh vkrh gSA"
8. No one put in appearance on behalf of the respondent-
defendant despite service.
9. Heard learned counsel for the appellants.
10. Learned counsel for the appellants-plaintiffs has contended
that the trial court gravely erred in deciding Issue Nos. 4 and 5
against appellants-plaintiffs and in favour of the respondent-
defandant. It has been submitted that findings recorded are
vitiated by material irregularity and patent illegality, inasmuch as
the trial court failed to consider undisputed and admitted facts on
record.
With regard to Issue No. 4, it has been argued that the
appellants-plaintiffs had bonafide, diligently and in good faith
(Uploaded on 16/01/2026 at 06:05:07 PM)
[2026:RJ-JD:1638] (7 of 11) [CFA-179/1997]
pursued recovery proceedings under the provisions of the PDR Act
before the District Collectors, Jaisalmer and Jaipur. The said
proceedings remained pending for a considerable period and the
appellants-plaintiffs lastly issued a reminder dated 29.04.1990. It
has been contended that if limitation is computed from the date of
the last communication i.e. 29.04.1990, suit was clearly within the
prescribed period of limitation. It has been submitted that
appellants-plaintiffs, having prosecuted their remedy with due
diligence and in good faith before a wrong forum, were entitled to
the benefit of exclusion of time and condonation of delay under
Sections 5 read with Section 14 of the Limitation Act, 1963. The
learned trial court, however, failed to apply said statutory
provisions and dismissed the suit without excluding period during
which the proceedings remained pending under the PDR Act. It is
thus contended that suit was well within limitation or in the
alternative, any delay deserved to be condoned.
So far as Issue No. 5 is concerned, learned counsel has
submitted that the trial court erred in holding the suit to be not
maintainable, despite admitted position that contract in question
was executed on behalf of the State of Rajasthan and was
subsequently transferred to the 28th Division, IGNP, Phalodi,
pursuant to orders dated 01.11.1985. In view of the said transfer,
the suit was fully maintainable. It has been further urged that
State of Rajasthan being real and substantive plaintiff, suit having
been instituted through its duly authorised officer could not have
been dismissed on hyper-technical or procedural grounds. The
(Uploaded on 16/01/2026 at 06:05:07 PM)
[2026:RJ-JD:1638] (8 of 11) [CFA-179/1997]
findings of the trial court on Issue No. 5 are, therefore,
unsustainable in law and liable to be set aside.
11. I have considered the submissions advanced by learned
counsel for the appellants and perused the judgment impugned.
12. A perusal of the record reveals that admittedly, contract for
transportation of cement (Contract No. 6 of 1983-84) was
operative from 26.03.1983 to 30.06.1983. The obligation of the
respondent-defendant to deliver cement at Ramdevra stood
required to be completed by 30.06.1983. The appellants-plaintiffs'
entire cause of action was founded on the alleged failure of the
respondent-defendant to complete transportation work within the
contractual period. Thus, right to sue first accrued to the
appellants-plaintiffs immediately upon expiry of the contract
period i.e. on or about 30.06.1983. Under Article 11 of the
Limitation Act, 1963, which governs suits for compensation
against a carrier for loss or non-delivery of goods, limitation
prescribed is three years from the date when the goods ought to
have been delivered. Thus, the suit ought to have been filed on or
before 30.06.1986. However, in the case in hand, suit was
instituted only on 19.01.1993 i.e. nearly ten years after accrual of
cause of action, rendering it ex facie barred by limitation. So far
as effect of recovery proceedings under the PDR Act is concerned,
principal argument advanced by the appellants is that limitation
should be computed by excluding period during which recovery
proceedings were pursued before the District Collectors under the
Rajasthan Public Demands Recovery Act, 1952 and that benefit of
Sections 5 and 14 of the Limitation Act ought to have been
(Uploaded on 16/01/2026 at 06:05:07 PM)
[2026:RJ-JD:1638] (9 of 11) [CFA-179/1997]
granted. This contention is devoid of merit for the reason that
mere correspondence or administrative efforts for recovery under
the PDR Act do not have effect of extending or suspending
limitation for a civil suit. Section 14 ibid applies only where a
litigant has been prosecuting another civil proceeding before a
court or quasi-judicial forum which lacked jurisdiction. The
proceedings before the District Collector under the PDR Act are
executive in nature, not civil proceedings before a court. Hence,
the foundational requirement for invoking Section 14 is absent.
Further, there was no pleading or proof that recovery proceedings
were prosecuted with due diligence and in good faith. Even, no
application for condonation of delay under Section 5 of the
Limitation Act was ever filed. In the absence of any such pleadings
or a formal prayer, the trial court rightly declined to extend the
limitation period suo motu. In the considered opinion of this
Court, the trial court rightly concluded that suit was instituted
beyond the prescribed limitation period and that plaintiffs failed to
explain inordinate delay of nearly a decade. Therefore, findings on
Issue No. 4 suffers from no legal or factual infirmity.
13. With regard to Issue No. 5, from the pleadings and evidence
on record, it reveals that contract in question was executed by the
20th Division of the Indira Gandhi Nahar Project (IGNP). The IGNP
is a distinct and specialised department, functioning separately
from general administrative setup of the State. The suit,
therefore, ought to have been instituted either by the concerned
IGNP Division which entered into the contract or by the State of
Rajasthan through an officer specifically authorised to represent
(Uploaded on 16/01/2026 at 06:05:07 PM)
[2026:RJ-JD:1638] (10 of 11) [CFA-179/1997]
the IGNP. The appellants-plaintiffs sought to justify Plaintiff No. 2's
locus by pleading that 20th Division was later brought under the
28th Division, Phalodi, due to administrative reorganisation.
However, neither any government order or notification evidencing
such transfer nor any documentary evidence authorising Executive
Engineer, 28th Division, to institute suit relating to contracts
executed by the 20th Division, was placed on record before the
trial court. No notification or power of attorney authorising
Executive Engineer, 28th Division, to represent the State in
respect of IGNP contracts was produced. The law is well settled
that authorisation to sue on behalf of the State is not a mere
technicality, but a mandatory requirement, especially in
contractual matters. So far as copies of the orders dated
05.04.1984 and 01.11.1985 produced on record as Annexure-1 &
2 along with memo of appeal is concerned, same were not
brought on record before the trial court. Even, no application to
bring these additional documents on record has been filed by the
appellants-plaintiffs in the appeal. Although, the State of
Rajasthan was arrayed as Plaintiff No.1, the suit still suffered from
a defect as the plaint was not signed and verified by a duly
authorised officer of the State. The trial court, therefore, rightly
held that Plaintiff No. 2 lacked authority to institute the suit. In
view of the absence of proof of contractual privity, delegation or
authorisation, the trial court's findings that Plaintiff No. 2 was not
competent to file the suit, are based on correct appreciation of
facts, evidence and settled principles of law. Therefore, in the
(Uploaded on 16/01/2026 at 06:05:07 PM)
[2026:RJ-JD:1638] (11 of 11) [CFA-179/1997]
opinion of this Court, findings on Issue No. 5 suffers from no legal
or factual infirmity.
14. In view of the aforesaid discussion, this Court does not find
any ground to interfere in the well reasoned findings recorded by
the trial court.
15. Consequently, present first appeal fails and is hereby
dismissed. The judgment and decree impugned dated 23.07.1997
passed by the trial court is affirmed.
16. No order as to cost.
(MUKESH RAJPUROHIT),J
/Jitender//-
(Uploaded on 16/01/2026 at 06:05:07 PM)
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!