Citation : 2023 Latest Caselaw 4136 Raj
Judgement Date : 5 May, 2023
[2023/RJJD/013041]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR S.B. Civil Writ Petition No. 6020/2023
Sanjay Singh S/o Vijendra Snigh Shekhawat, Aged About 37 Years, Khuri Chhoti, Khuri Badi, Sikar, Lachhamangarh, Rajasthan.
----Petitioner Versus
1. State Of Rajasthan, Through Principal Secretary To Government Of Rajasthan, Department Of Mines And Geology, Government Of Rajasthan, Jaipur.
2. Directorate Of Mines And Geology, Through The Director, Mines And Geology, Khanij Bhawan, Shastri Circle, Udaipur (Rajasthan).
3. Additional Director (Mines), Department Of Mines And Geology, Jaipur Range, Jaipur.
4. Mining Engineer, Department Of Mines And Geology, Jaipur, Rajasthan.
----Respondents
S.B. Civil Writ Petition No. 5914/2023
Pradeep Baloda S/o Jeet Singh, Aged About 35 Years, R/o 563 Dolatpur, Hijranwa Kala 41, Tehsil Hajrawan Kallan, District Fatehabad, Hariyana.
----Petitioner Versus 1 State Of Rajasthan, Through Principal Secretary To Government Of Rajasthan, Department Of Mines And Geology, Government Of Rajasthan, Jaipur. 2 Directorate Of Mines And Geology, Through The Director, Mines And Geology, Khanij Bhawan, Shastri Circle, Udaipur (Rajasthan).
3 Additional Director (Mines), Department Of Mines And Geology, Jaipur Range, Jaipur.
4 Mining Engineer, Department Of Mines And Geology, Jaipur, Rajasthan.
----Respondents
For Petitioner(s) : Mr. Girish Joshi
For Respondent(s) : Mr. Sandeep Shah, Sr. Advocate &
AAG assisted by Ms. Akshiti Singhvi
HON'BLE DR. JUSTICE PUSHPENDRA SINGH BHATI
Judgment
Reserved on 02/05/2023 Pronounced on 05/05/2023
[2023/RJJD/013041] (2 of 7) [CW-6020/2023]
1. Since the both instant petitions involve a common
controversy, though with marginal variation in the contextual
facts, therefore, the above-numbered SBCWP No.6020/2023, was
tagged with SBCWP No. 5914/2023. Arguments in both petitions
were heard together and the same are being decided by this
common judgment.
2. These writ petitions under Article 226 of the Constitution of
India have been preferred claiming the following reliefs:
S.B. Civil Writ Petition No. 6020/2023:
"It is, therefore, humbly prayed before this Hon'ble Court that it may be pleased to call for the entire record of the case and after examining the same, the Hon'ble Court may be pleased to issue a writ, order or directions in the nature of directing:
(i) The respondents be directed to extend the contract of the petitioner for a period of one year in due consonance with amendment so brought to Rule 36(5) of Rajasthan Minor Mineral Concession Rules, 2017 respectively.
(ii) The e-auction advertisement dated 08.03.2023 (Annex-
5) for award of ERCC contract so issued by the respondents for the location of Rishabhdev, Khairwada DISTRICT Udaipur be quashed and set aside.
(iii) Any other writ, order or directions which this Hon'ble Court deems fit in the interest of justice may kindly be passed in favour of the petitioner.
(iv) Cost of the litigation may also be passed in the favour of the petitioner."
S.B. Civil Writ Petition No. 5914/2023:
"It is, therefore, most humbly prayed before this Hon'ble Court that it may be pleased to call for the entire record of the case and after examining the same, the Hon'ble Court may be pleased to issue a writ, order or directions in the nature of directing:-
(i) The respondents be directed to extend the contract of the petitioner for a period of one year in due consonance with amendment so brought to Rule 36(5) of Rajasthan Minor Mineral Concession Rules, 2017 respectively.
(ii) The e-auction advertisement dated 08.03.2023 for award of ERCC contract so issued by the respondents for the location of the Phalodi, Bap, Lohavat and Bapini (Denok, Barsingo ka Bas, Aau, Suwap and Santosh Nagar (Ishru) District Jodhpur be quashed and set aside.
[2023/RJJD/013041] (3 of 7) [CW-6020/2023]
(iii) Any other writ, order or directions which this Hon'ble Court deems fit in the interest of justice may kindly be passed in favour of the petitioner.
(iv) Cost of the litigation may also be awarded in the favour of the petitioner."
3. For the sake of brevity and convenience, the facts are being
taken from the above-numbered SBCWP No.6020/2023.
4. Brief facts of the case, as placed before this Court by learned
counsel for the petitioner, are that the respondents issued a
tender for award of ERCC Contract for collection of Excess Royalty
-cum- DMFT, RSMET & other fees in relation to the excavation of
Mineral Masonry Stone taking place in the Mines situated at Tehsil
Rishabhdev & Khairwada, District Udaipur. The petitioner was
declared as the highest bidder, and accordingly, a sanctioned in
favour of the petitioner was granted vide order dated 26.03.2021;
whereupon, the petitioner entered into an agreement with the
respondent no.4 on 26.03.2021 itself; term of the contract was
from 01.04.2021 to 31.03.2023.
4.1 The respondents, in light of the amendments so brought in
Rule 36(5) of the Rajasthan Minor Mineral Concession Rules, 2017
(hereinafter referred as 'Rules of 2017'), passed an order on
10.01.2022, formulating the guidelines for extension of the
contract, keeping into consideration the Covid-19 pandemic.
4.2. Thereafter, the respondents issued an e-auction
advertisement dated 08.03.2023 for grant of ERCC contract, and
the auction was scheduled to be held on 13.04.2023; however,
now the auction has been scheduled to be held in the first week of
May. The petitioner wrote a letter dated 20.03.2023 to the
respondent no.4 seeking extension of the contract in question; the
respondent no.4 vide order dated 29.03.2023, extended the
[2023/RJJD/013041] (4 of 7) [CW-6020/2023]
contract period for 90 days or till execution of a new contract, and
further, the contract price was increased by 10% of the original
bid amount; subsequently, a supplementary deed was entered on
31.03.2023 between the petitioner and the respondent no.4.
5. As averred in the writ petitions, the petitioners, being
aggrieved by the aforementioned e-auction advertisement dated
08.03.2023 issued by the respondents, have preferred these
petitions, claiming the afore-quoted reliefs.
6. Learned counsel for the petitioners submitted that the
respondents extended the contract period of the petitioner only for
a period of 90 days or till execution of a new contract, but without
any justifiable reason, the respondents are not extending the
contract period to the extent of one year, which is arbitrary and
illegal.
6.1. Learned counsel further submitted that Rule 36 (5) of the
Rule of 2017 provides for extension of the contract for a period of
one year, and therefore the impugned action of the respondents is
clearly violative of the provisions as contained in the Rules of
2017.
6.2. Learned counsel also submitted that the respondents vide
order dated 30.03.2022 have already extended the contract period
of 41 other similarly situated contractors for a period of one year,
and therefore, the petitioners ought to have been given the same
treatment. It was further submitted that the petitioners have also
submitted the consent letter -cum- affidavit for extension of the
contract for a period of one year, but the respondents, without
taking the same into due consideration, took the impugned action,
which is not sustainable in the eye of law.
[2023/RJJD/013041] (5 of 7) [CW-6020/2023]
6.3. In support of his submissions, learned counsel referred to
the interim orders passed by the Coordinate Benches of this
Hon'ble Court at Jaipur Bench in the following cases:
(a) M/s Konasth Infrastructure Private Limited Vs. State of
Rajasthan (S.B. Civil Writ Petition No. 6132/2023); order dated
20.04.2023;
(b) M/s Shri Balaji Constructions Vs. State of Rajasthan & Ors.
(S.B. Civil Writ Petition No. 6421/2023); order dated 27.04.2023;
(c) M/s Green Star Minerals Vs. State of Rajasthan (S.B. Civil
Writ Petition No. 6428/2023); order dated 26.04.2023.
7. On the other hand, Mr. Sandeep Shah, learned Senior
Advocate and Additional Advocate General assisted by Ms. Akshiti
Singhvi, appearing on behalf of the respondents, while opposing
the aforesaid submissions made on behalf of the petitioners,
submitted that in the amended Rule 36 (5) of the Rules, 2017, the
word 'may' was used, which clearly means that the extension of
the ERCC Contract is discretionary in nature, and such
discretionary power as per the Rules is vested with the State
Government, and thus, it was not mandatory for the State to
extend the period of the contract, for a period of one year, as
claimed by the present petitioners.
7.1. It was further submitted that the petitioners failed to submit
the requisite application 15 days prior to expiry of the original
contract period, as also failed to deposit 10% of the increased
amount within the stipulated period, and therefore, on that count
alone, the extension as sought for by the petitioners does not
deserve to be granted.
[2023/RJJD/013041] (6 of 7) [CW-6020/2023]
7.2. It was also submitted that the respondents however,
extended the ERCC Contract of the petitioners for a period upto 90
days or until the new contract is executed by the way of
agreement, and thus, the petitioners cannot claim the extension of
the contract for a particular period, as a matter of right.
7.3. It was further submitted that the interim orders referred on
behalf of the petitioners are not applicable to the present case, as
in those matters, reply was not filed on the date of passing of the
interim orders, while in the present case, reply to the petitions has
been filed.
8. Heard learned counsel for the parties as well as perused the
record of the case, as also perused the interim orders referred on
behalf of the petitioners.
9. This Court observes that the petitioners' ERCC Contract was
valid from 01.04.2021 to 31.03.2023, and thereafter, due to
Covid-19 pandemic, a proviso was incorporated in Rule 36 (5) of
the Rules, 2017. The respondent no.4 extended the petitioners'
contract for a period of 90 days or till execution of the new
contract. Meanwhile, the respondents issued an e-auction
advertisement dated 08.03.2023 for awarding the ERCC Contract.
10. This Court further observes that it was provided in the new
proviso added to Rule 36 (5) of the Rules, 2017, that, "period of
existing contract may be extended by the Government for a
period upto one year subject to condition that the contractor shall
pay ten percent of increased amount to the existing contract
amount and a rider agreement shall be executed within a period
of fifteen days from the dated of receipt of the order of extension
[2023/RJJD/013041] (7 of 7) [CW-6020/2023]
or before expiry of the original contract period whichever is
earlier".
10.1. The Court also observes that it is clear from the aforesaid
Rule that extension of period of the contract lies well within the
discretionary power of the State Government, and therefore, the
petitioners cannot claim, as a matter of right, the extension of the
contract in question, that too for a particular period of time, more
particularly, when the contract period was already extended by the
respondents for a certain period i.e. 90 days or till execution of a
new contract.
11. This Court further observes that the petitioners failed to
submit the requisite application, as also failed to deposit 10% of
the increased amount, within the stipulated period. Therefore,
while keeping into due consideration the fact that it was
discretionary for the State to extend the contract, this Court does
not find any reason to sustain the claim of the petitioners in the
present petitions.
12. The interim orders, as referred on behalf of the petitioners,
do not render any assistance to their case.
13. Thus, in light of the aforesaid observations and looking into
the factual matrix of the present case, this Court does find any
ground to be made out, so as to grant any relief to the petitioners
in the present petitions.
14. Consequently, the present petitions are dismissed. All
pending applications stand disposed of.
(DR. PUSHPENDRA SINGH BHATI), J.
skant/-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!