Citation : 2023 Latest Caselaw 5541 Raj
Judgement Date : 3 August, 2023
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR S.B. Civil Writ Petition No. 19453/2022
M/s Singh And Associates, Through Its Sole Proprietor Sh. Harminder Singh S/o Kalwant Singh, Aged About 61 Years, Resident Of House No. 16, Basant Vihar, Sector No. 14, Udaipur.
----Petitioner Versus
1. State Of Rajasthan, Through The Principal Secretary, Administrative Department, Water Resources Department, Government Of Rajasthan, Jaipur.
2. The Chief Engineer, Water Resources Department, Government Of Rajasthan, Jaipur.
3. The Superintending Engineer, Water Resources Department, Water Resources Construction Circle, Dungarpur.
4. The Executive Engineer, Water Resources Division I, Dungarpur.
5. M/s. Pradeep Construction Company, Through Proprietor, House No. 248, T.p. House, Pratap Nagar Colony, Dungarpur.
----Respondents
For Petitioner(s) : Mr. Shridhar Mehta
For Respondent(s) : Ms. Abhilasha Bora, AGC a/w
Ms. Saloni Malpani
HON'BLE DR. JUSTICE PUSHPENDRA SINGH BHATI
Judgment
Reserved on 18/07/2023
Pronounced on 03/08/2023
1. This writ petition under Articles 226 & 227 of the Constitution
of India has been preferred seeking the following reliefs:
"It is, therefore, most respectfully prayed on behalf of petitioner that the writ petition may kindly be allowed and by an appropriate writ, order or direction:- I. The impugned orders dated 28.10.2022 (Annex-5) and 12.12.2022 (Annex-7) passed by the first appellate authority
(D.B. SAW/814/2023 has been filed in this matter. Please refer the same for further orders)
(2 of 7) [CW-19453/2022]
and the second appellate authority may kindly be quashed and set aside and the appeals so filed by the petitioners may kindly be allowed in toto;
II. The order dated 23.08.2022 (Annex-3) may kindly be quashed and set aside and that consequent to aforesaid, the respondents may kindly be directed to consider the bid of the petitioner as responsive and grant the work order in favour of the petitioner if found lowest. III. Any other appropriate order or direction, which this Hon'ble Court considers just and proper in the facts and circumstances of this case, may kindly be passed in favour of the Petitoner.
IV. Costs of the writ petition may kindly be awarded to the Petitioner."
2. As per the pleaded facts, the respondent-Department,
through its advertisement dated 22.07.2022, invited bids for
several works, including the work of renovation of BHE KA NAKA
Dam and LMC, RMC Canal, Tehsil Chhikali, District Dungarpur. The
petitioner accordingly filed its bid along with the requisite
documents (including the experience certificate dated 08.06.2021
for the works at Dhudhanriya Anicut). However, vide the
impugned order dated 23.08.2022, the petitioner's bid was
declared as non-responsive, on count of deficiency in regard to the
experience certificate.
2.1 Aggrieved by the aforesaid order, the petitioner filed First
Appeal before the Chief Engineer, Water Resources Department,
Jaipur. However vide the impugned order dated 28.10.2022, the
said appeal was rejected.
2.2 Thereafter, against the order of the First Appellate Authority,
a second appeal was filed by the petitioner before the Principal
Secretary, Water Resources Department, Jaipur on 31.10.2022;
(D.B. SAW/814/2023 has been filed in this matter. Please refer the same for further orders)
(3 of 7) [CW-19453/2022]
however, while the second appeal was pending, the respondent-
Department vide order dated 17.11.2022 granted the work order
to one M/s. Pradeep Construction Company and the work was to
begin from 27.11.2022; thus, the Second Appellate Authority
noticing that the bidder in whose favour the work order had been
granted had already started the work, rejected the second appeal
of the petitioner vide the impugned order dated 12.12.2022.
Hence, the present petition has been preferred claiming the afore-
quoted reliefs.
3. Learned counsel for the petitioner submitted that though the
work for construction of Dhundhariya Anicut was completed on
21.03.2020 (stipulated date of completion being 14.06.2014), the
experience certificate dated 08.06.2021 clearly stated under the
head of 'contractor performance' as 'satisfactorily completed' and
the same was stated even in the revised certificate dated
15.10.2022. In furtherance, it was submitted that the respondent-
Department failed to clarify as to why while the earlier experience
certificate was not acceptable, but the revised one was.
3.1. It was also submitted that the only reason for declaring the
bid of the petitioner as non responsive was that the experience
certificate was not having any endorsement for increase in the
contract period (i.e. the delay caused in completion of work was
yet to be approved); yet the work was said to be satisfactory by
the respondent-Department itself. In furtherance, the same is
pending approval before the concerned authority till date.
3.2. It was further submitted that while the second appeal was
pending before the appellate authority, the respondent-
(D.B. SAW/814/2023 has been filed in this matter. Please refer the same for further orders)
(4 of 7) [CW-19453/2022]
Department in a hasty manner vide order dated 17.11.2022
awarded the work order to M/s. Pradeep Construction (private
respondent) and noting that the private respondent had already
started the work on 27.11.2022, the Second Appellate Authority
vide the impugned order dated 12.12.2022 rejected the second
appeal of the petitioner; however, it is clear from the
measurement book that the work was started on 12.01.2023. In
furtherance, it was argued that the respondent-Department
awarded the contract to the private respondent even though the
bid costed the State Exchequer around Rupees 12 lakhs more.
3.3. Learned counsel also submitted that as per Section 39 (3) &
(6) of the Rajasthan Transparency in Public Procurement Act,
2012, the appeals preferred before the First Appellate Authority
and the Second Appellate Authority respectively were required to
be decided within one month from the date of filing, yet the
provisions were not complied with.
4. On the other hand, Ms. Abhilasha Bora, learned Additional
Government counsel assisted by Ms. Saloni Malpani, appearing for
the respondents, while opposing the aforesaid submissions made
on behalf of the petitioner, submitted that the experience
certificate so submitted by the petitioner was not in conformity
with the prescribed conditions mentioned in the Notice Inviting
Tender, and thus, the petitioner was rightly disqualified in the
tender process in question.
4.1. It was further submitted that the tender was approved by
the letter dated 31.10.2022 of the Competent Officer, Additional
Chief Engineer, Water Resources Department, Udaipur and the
(D.B. SAW/814/2023 has been filed in this matter. Please refer the same for further orders)
(5 of 7) [CW-19453/2022]
Letter of Acceptance (LoA) was issued on 02.11.2022 and the
work order was thus issued on 17.11.2022 to the private
respondent, fixing the date of commencement and date of
completion as 27.11.2022 and 26.05.2024 respectively. Thus, the
entire process took 17 days to complete and was not done hastily.
4.2. Learned Additional Government Counsel also submitted that
in relation to the tender work awarded to the petitioner for work
related to Repair and Renovation of Dam and RMC of Ghodhakhoj
Minor Irrigation Project, experience certificates of three works
were presented, out of which two works were completed
satisfactorily due to which the petitioner was declared qualified by
the Executive Engineer, Water Resources Department, Salumber;
however, in the present case, the experience certificate of
Dhundhariya Anicut work was presented and the extension of time
for the said work and the final bill were yet to be approved, and
thus the same could not be considered as satisfactory.
4.3. It was further submitted that by the communication dated
12.07.2023 from the Office of Executive Engineer Water Resources
Division First Dungarpur the work experience certificate of the
petitioner was not found to be satisfactory and currently the work
order issued to private respondent the said work is in progress
and till now 4th running bill of Rupees 139.93 lakhs has been
spent.
4.4. Learned Additional Government Counsel, to fortify her
submissions, placed reliance on the judgment rendered by the
Hon'ble Apex Court in the case of N.G. projects Limited v.
Vinod Kumar Jain and Ors., (2022) 6 SCC 127.
(D.B. SAW/814/2023 has been filed in this matter. Please refer the same for further orders)
(6 of 7) [CW-19453/2022]
5. Heard the learned counsel for the parties as well as perused
the record of the case alongwith the judgment cited at the bar.
6. This Court observes that the respondent-Department invited
bids for several works, including the work in question, for which
petitioner submitted its bid alongwith experience certificate for the
works of Dhudhanriya Anicut; however the petitioner's bid was
declared as non responsive; further both the appellate authorities
below rejected the appeals of the petitioner, vide the impugned
orders.
7. This Court further observes that the petitioner's bid was
declared as non-responsive, as the experience certificate so
submitted though stated satisfactory performance, there was no
endorsement for increase in the contract period for the delay the
petitioner had caused in completion of the work; while the
stipulated time was 14.06.2014, however the actual date of
completion of the work was 21.03.2020; since the approval by the
respondent-Department of the delay caused by the petitioner was
pending at the time of submission of experience certificate, the bid
of the petitioner was accordingly declared as non responsive.
8. This Court also observes that both the appellate authorities
below, in the impugned orders, have observed that the petitioner
took around 8 years to complete the work, that was required to be
completed in 18 months, as such though the respondent-
Department has stated satisfactory completion of work under the
head of contractor's performance, however, at the same time, no
approval of such delay has been given by the respondent-
Department.
(D.B. SAW/814/2023 has been filed in this matter. Please refer the same for further orders)
(7 of 7) [CW-19453/2022]
9. This Court further observes that the work has already been
awarded to the private respondent vide work order issued on
17.11.2022 and as per the communication dated 12.07.2023 of
the Executive Engineer Water Resources Division First Dungarpur,
the work has already started, and till now, 4 th running bill of
Rupees 139.93 lakhs has been prepared.
10. Thus, in light of the aforesaid observations and looking into
the factual matrix of the present case, this Court does not find it a
fit case so as to grant any relief to the petitioner in the present
petition.
11. Consequently, the present petition is dismissed. All pending
applications stand disposed of.
(DR. PUSHPENDRA SINGH BHATI), J.
SKant/-
(D.B. SAW/814/2023 has been filed in this matter. Please refer the same for further orders)
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!