Citation : 2021 Latest Caselaw 8692 Raj
Judgement Date : 1 April, 2021
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
JODHPUR
D.B. Spl. Appl. Writ No. 1420/2019
M/s. Mohan Traders, Through Its Proprietor Rajkumar Chitora
S/o Shri Pyar Chand Aged About 50 Years, R/o 144, Krishi Mandi
District Udaipur, Rajasthan.
----Appellant
Versus
1. Raj. Rajya Sahkari Upbhokta Sangh Ltd., Through Its
Managing Director, 237, Second Floor, Nehru Sahkar
Bhawan, Bhawani Singh Road, Jaipur.
2. The Directors And Joint Secretary (Admn.), Department
Of Social Justice And Empowerment, Ambedkar Bhawan,
Civil Lines Crossing, Jaipur.
3. Administrator And Registrar, Cooperative Societies,
Rajasthan Rajya Sahkari Upbhokta Sangh Limited, Jaipur.
----Respondents
For Appellant(s) : Mr. N.M.Lodha, Senior Advocate with
Mr.V.D.Dadhich
For Respondent(s) : Mr. Dhanpat Choudhary
HON'BLE MR. JUSTICE SANGEET LODHA
HON'BLE MR. JUSTICE RAMESHWAR VYAS
Judgment
1st April, 2021
PER HON'BLE MR. SANGEET LODHA,J.
1. This intra-court appeal is directed against order dated
30.10.19 of the learned Single Judge of this court, whereby the
writ petition preferred by the appellant questioning the legality of
order dated 17.10.19 passed by the Managing Director, Rajasthan
Rajya Sahakari Upbhokta Sangh Limited ('CONFED'), Jaipur,
whereby while withdrawing the certificate of satisfactory
(2 of 10) [SAW-1420/2019]
completion of the work, the appellant has been blacklisted and
debarred from entering into business with CONFED for a period of
three years.
2. The relevant facts in nutshell are that the appellant, a
proprietorship concern, engaged in sales and supply of grains,
pulses and other commodities was awarded the contract by the
CONFED for supply of specified branded items as per the bid
conditions all over Rajasthan in hostels/residential schools of
Social Justice & Empowered Department. The agreement was
executed between the appellant and CONFED on 13.7.16 which
was valid upto 15.7.17. The appellant was served with the notice
dated 25.7.17 alleging that the appellant had submitted the bills
of 13 challans for payment twice with intention to derive double
benefit. Yet another notice dated 1.6.17 was issued with the
similar allegation and explanation was sought. The appellant
submitted the explanation vide communication dated 11.7.17.
Thereafter, the term of the contract was extended upto 15.10.17.
On 2.1.19, a certificate of satisfaction completion of supply in
terms of the contract was issued to the appellant by the Managing
Director, CONFED. Later, on the basis of the inquiry conducted in
the back of the appellant, vide order dated 17.10.19 issued by the
Managing Director, CONFED, the certificate of completion of
satisfactory supply of the commodities issued as aforesaid was
withdrawn and the appellant was debarred from entering into
contract with the CONFED for a period of three years.
3. Aggrieved by the order dated 17.10.19, the writ petition
preferred by the appellant has been dismissed by the learned
Single Judge by the order impugned on the ground of availability
(3 of 10) [SAW-1420/2019]
of remedy of appeal, observing that the writ petition involve a
horde of disputed question of fact and therefore, the Court is not
inclined to exercise its extra ordinary jurisdiction under Article 226
of the Constitution of India.
4. Learned Senior counsel appearing for the appellant
contended that the learned Single Judge has seriously erred in
dismissing the appeal on the ground of availability of remedy of
appeal. Drawing the attention of the Court to the provisions of
Section 38 of Rajasthan Transparency in Public Procurement Act,
2012 (for short "RTPP Act"), learned Senior counsel submitted that
the appeal as provided under Section 38 of the RTPP Act is
available in respect of the dispute relating to initial bidding
process and not in respect of the dispute that may arise after
award of the contract in favour of the bidder or after completion of
such contract. Learned Senior counsel submitted that the 'Bidder'
is defined under Section 2 (ii) of the RTPP Act as 'any person
participating in a procurement process with a procuring entity'.
The role of the bidder comes to an end after expiry of the
procurement process which ends on award of the contract or
cancellation of the process. Learned Senior counsel submitted that
once the certificate for satisfactory completion of supply was
issued, there was no occasion for the respondents to initiate the
penal action. Learned Senior counsel submitted that after issuing
the notices seeking explanation, no notice was issued to the
appellant proposing blacklisting and straight away after lapse of
more than two years since issuance of the notice, the order
impugned was passed by the respondent authority and thus,
apparently, the order impugned passed without extending an
(4 of 10) [SAW-1420/2019]
opportunity of hearing to the appellant, is ex facie violative of
principles of natural justice and thus, the learned Single Judge has
seriously erred in dismissing the writ petition on the ground of
availability of remedy of appeal under the relevant statute.
Learned Senior counsel submitted that after issuance of the notice
in the year 2017, the term of the contract was extended and the
appellant was issued a certificate of completion of the work and
thus, solely on the basis of the inquiry report submitted by the
Purchase Committee unilaterally without extending an opportunity
of hearing to the appellant, is ex facie illegal and arbitrary.
5. On the other hand, learned counsel appearing for the
respondent submitted that the order passed by the competent
authority under Section 43 of the RTPP Act debarring any bidder
from participating in tender process is appealable under Section
38 of the RTPP Act and thus, taking into consideration the fact
that the petition involves seriously disputed questions of facts, the
learned Single Judge has committed no error in dismissing the
petition on the ground of availability of remedy of appeal. Learned
counsel submitted that vide notice dated 1.6.17, the action was
proposed against the appellant under Section 11 read with Section
46 of the RTPP Act and therefore, the contention sought to be
raised that order impugned has been passed without giving an
opportunity of hearing is absolutely baseless. However, learned
counsel fairly submitted that before passing the order on the
recommendation made by the Purchase Committee in its meeting
held on 16.10.19, no notice was issued to the appellant against
the proposed action. Learned counsel submitted that the
allegation of appellant withdrawing the double payment of 7 bills
(5 of 10) [SAW-1420/2019]
stands proved on the basis of the documentary evidence on record
and thus, the action of the respondent in blacklisting the appellant
after due notice, cannot be faulted with.
6. We have considered the rival submissions and perused the
material on record.
7. It is well settled that ordinarily when a dispute between the
parties requires adjudication of the disputed question of facts,
where parties are required to lead evidence which can be
determined by the domestic forum chosen by the parties, the writ
court would refuse to exercise the discretionary jurisdiction. But
then, the rule of exclusion of writ jurisdiction on account of
availability of alternative remedy is a rule of discretion and not
rule of compulsion and therefore, the availability of the alternative
remedy by itself, does not fetter the extra ordinary jurisdiction of
the court under Article 226 of the Constitution, which is plenary in
nature and is not limited by any other provisions of the
Constitution.
8. As laid down by the Constitution Bench of the Hon'ble
Supreme Court in the matter of 'A.V.Venkateswaran, Collector of
Customs, Bombay vs. Ramchand Sobhraj Wadhwani & Anr.", AIR
1961 SC 1506, the rule that party who applies for issue of a high
prerogative writs should before he approaches the court have
exhausted the remedies open to it under the law is not one which
bars the jurisdiction of the High Court to entertain the petition or
to deal with it, but it is rather, a rule which courts have laid down
for the exercise of their discretion.
9. Suffice it to say that the availability of alternative remedy
to the petitioner, does not operate as bar to the jurisdiction of the
(6 of 10) [SAW-1420/2019]
High Court under Article 226 of the Constitution of India and the
court can always exercise its discretion taking into consideration
facts and circumstances of the case.
10. Coming to the question regarding observance of principles of
natural justice and fair opportunity of hearing to the person
against whom the action of blacklisting is contemplated, it needs
to be emphasised that the rules of natural justice are assurance of
justice and fair play and therefore, any action which has evil and
civil consequences, should be taken only after following the
principles of natural justice. Further, the observance of principle of
natural justice is a rule and exclusion an exception and therefore,
unless exceptional circumstances exists, departure therefrom is
not permissible under the law.
11. Indisputably, the action in blacklisting of the awardee of the
contract on account of malpractices casts stigma and many civil
and evil consequences flow therefrom and therefore, such an
action could only be taken after following the principles of natural
justice.
12. In "M/s. Erusian Equipment & Chemicals Ltd. vs. State of
West Bengal & Anr", (1975) 1 SCC, 70, the Hon'ble Supreme
Court observed:
"20. Blacklisting has the effect of preventing a person from the privilege and advantage of entering into lawful relationship with the Government for purposes of gains. The fact that a disability is created by the order of blacklisting indicates that the relevant authority is to have an objective satisfaction. Fundamentals of fair play require that the person concerned should be given an opportunity to represent his case before he is put on the blacklist." (emphasis supplied)
13. Similarly, in "Raghunath Thakur vs. State of Bihar & Ors.",
(1989) 1 SCC 229, the Hon'ble Supreme Court observed that
(7 of 10) [SAW-1420/2019]
blacklisting any person in respect of business ventures has civil
consequences for future business of the person concerned and
therefore, even if the rules do not express so, it is an elementary
principle of natural justice that parties affected by any order
should have right of being heard and making representation
against the order.
14. In Gorkha Security Services vs. Government of NCT of Delhi
& Ors.: (2014) 9 SCC, 105, the Hon'ble Supreme Court while
relying upon the decisions in M/s. Erusian Equipment & Chemicals
Ltd's case and Raghunath Thakur's case (supra), observed that
the action of the blacklisting must be preceded by show cause
notice setting up the precise case which noticee is required to
meet. The court observed that this would require the statement of
imputations detailing out the alleged breaches and defaults
committed so that he gets an opportunity to rebut the same.
Another requirement as pointed out by the Court is the nature of
action which is proposed to be taken for such breach inasmuch as,
it is incumbent upon the authority concerned to provide adequate
and meaningful opportunity to the person concerned. The court
further observed that when it comes to the action of blacklisting
which is termed as 'civil death', a harshest possible action, it
would be difficult to accept the proposition that without even
putting the noticee to such a contemplated action and giving him
a chance to show cause as to why such an action be not taken,
final order can be passed blacklisting such a person only on the
premise that this is one of the actions so stated in the provisions
of NIT.
(8 of 10) [SAW-1420/2019]
15. Thus, in the backdrop of the settled position of law noticed
as above, it needs to be examined as to whether while passing the
order blacklisting the appellant, the respondents have followed the
principles of natural justice and extended fair opportunity of
hearing to the appellant.
16. Indisputably, in the instant case, in the first instance vide
notice dated 25.5.17 with reference to provisions of Section 11 of
the RTPP Act, the explanation of the appellant was sought
regarding submission of 13 challans for preparation of the bill
twice whereas, on the basis of the challans earlier filed, the bill
was already prepared by the Department. The said notice was
followed by notice dated 1.6.17 with reference to the provisions of
Section 11 & Section 46 of RTPP Act. The explanation was
submitted by the appellant vide communication dated 11.7.17
explaining that it was only an inadvertent error and there was no
intention to obtain the payment of the bills twice. It was clarified
that 'errors and omissions' are always accepted. After submission
of the reply by the appellant as aforesaid, vide communication
dated 9.8.17 the term of the contract awarded to the appellant
which was expiring on 15.7.17, was further extended upto
15.10.17. Thereafter, after completion of the contract, a certificate
of satisfactory completion of the work was issued to the appellant
by the Managing Director, CONFED and no further proceedings
pursuant to the notice issued as aforesaid was taken. A perusal of
the order impugned in the writ petition dated 17.10.19 has been
passed on the basis of the following allegations being found
proved against the appellant:
(9 of 10) [SAW-1420/2019]
"1- lR;fu"Bk dk mYya?ku & 8 ¼vkB½ vkiwfrZ pkykuksa dk nks ckj Hkqxrku izkIr dj vuqfpr rjhds ls ykHk izkIr djuk] 23 ¼rschl½ ewy pkyku dks ykHk izkIr djus dh ea'kk ls /kks[kkiwoZd iqu% nksckjk izLrqr djuk ,oa 17 ¼l=g½ pkyku ifjofrZr dj izLrqr dj nks"k fl) gksuk ik;k x;kA 2- fufonk ,oa vuqcU/k dh 'krksZa dk mYya?ku djuk & lkekftd U;k; ,oa vf/kdkfjrk foHkkx] jktLFkku ljdkj] t;iqj }kjk lkexzh ds Lohd`r ,oa fu/kkZfjr czk.M dh vkiwfrZ ugha dj mlds LFkku ij vU; czk.M dh vkiwfrZ dj foHkkx ds vkns'k Øekad 38845 fnukad 23-06-2016 dh ?kksj vogsyuk djus ds nks"kh ik;s x;sA 3- nksgjk Hkqxrku izkIr djuk & 7 ¼lkr½ pkykuksa dh jkf'k 8]99]432-06 dks nksgjk Hkqxrku dkWuQSM+ ds ek/;e ls izkIr dj xaHkhj foÙkh; vfu;ferrk djus ds nks"kh jgs gSA"
17. It is pertinent to note that in the notice issued, the
explanation of the appellant was sought only in respect of 13
challans submitted twice. There was no allegation that by way of
submission of the challans of the supply made twice, the appellant
unauthorisedly drawn the payment of Rs.8,99,432.06 twice. There
was no allegation either that the supply of the materials made was
not of the specification and brand agreed upon. As a matter of
fact, the aforesaid allegations are found to be proved solely on the
basis of the conclusion arrived at by the Purchase Committee of
CONFED in its meeting held on 16.10.19. It is not disputed before
this Court that before directing blacklisting of the appellant as
aforesaid, vide order dated 17.10.19, no notice was issued to the
appellant seeking explanation regarding the allegations alleged to
be found proved against him and thus, the order impugned is
apparently based on the inquiry made by the respondents in the
back of the appellant, the fact which is not disputed by the
counsel appearing for the respondents before this Court. Even the
reply to the notice earlier issued filed by the appellant has also not
(10 of 10) [SAW-1420/2019]
been taken note of by the respondents while passing the order
impugned.
18. In view of the discussion above, we are firmly of the opinion
that the order impugned passed by the respondent-Managing
Director, CONFED without affording a fair opportunity of hearing to
the appellant, is ex facie violative of elementary principle of
natural justice and therefore, not sustainable in the eyes of law.
19. In view of the conclusion arrived at as aforesaid, we need
not enter into the question raised on behalf of the appellant as to
whether against the order impugned, the appeal under Section 38
of the RTPP Act is maintainable or not.
20. In the result, the special appeal succeeds, it is hereby
allowed. The order impugned dated 30.10.19 passed by the
learned Single Judge is set aside. The writ petition preferred by
the appellant is allowed. The order impugned in the writ petition
dated 17.10.19 passed by the Managing Director, CONFED, is
quashed. It will be open for the respondents to pass the order
afresh after giving an opportunity of hearing to the appellant in
accordance with law. No order as to costs.
(RAMESHWAR VYAS),J (SANGEET LODHA),J
89-Aditya/-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!