Citation : 2025 Latest Caselaw 6317 P&H
Judgement Date : 15 December, 2025
CR-6970-2019 (O&M) [1]
252
IN THE HIGH COURT OF PUNJAB AND HARYANA AT
CHANDIGARH
CR-6970-2019 (O&M)
Date of decision: 15.12.2025
Suresh Kumar
...Petitioner
Versus
Madan Lal and others
...Respondents
CORAM: HON'BLE MR. JUSTICE VIKAS BAHL
Present: Mr. Chetan Bansal, Advocate for the petitioner.
Mr. Saurabh Arora, Advocate for respondent Nos.1 and 2.
Mr. Rishabh Gupta, Advocate for respondent Nos.3 and 4.
****
VIKAS BAHL, J. (ORAL)
1. This is a revision petition filed under Article 227 of the
Constitution of India for setting aside the order dated 01.10.2019 (Annexure
P-1) passed by the Civil Judge (Junior Division), Amritsar, whereby an
application (Annexure P-2) filed by respondent Nos.1 and 2 under the
provisions of Order 1 Rule 10 of CPC for impleading respondent Nos.1 and
2 as party to the civil suit (Annexure P-4) has been allowed.
ARGUMENTS ON BEHALF OF THE PETITIONER:-
2. Learned counsel for the petitioner has submitted that the
petitioner is dominus litis and he had not impleaded Madan Lal and Raju
Mehta-respondent Nos.1 and 2 in the suit as he is claiming no relief against
1 of 9
CR-6970-2019 (O&M) [2]
the said respondents. It is further submitted that the said respondents are
neither necessary nor proper parties yet the trial Court in a suit for
injunction filed by the petitioner against the Punjab State Power
Corporation Limited has impleaded the said respondent Nos.1 and 2 as
defendants in the said suit. It is argued that the order vide which the
application for impleadment has been allowed is illegal and deserves to be
set aside and the application filed under Order 1 Rule 10 CPC for
impleadment deserves to be dismissed.
ARGUMENTS ON BEHALF OF RESPONDENTS No.1 and 2:-
3. Learned counsel appearing on behalf of the contesting
respondent Nos.1 and 2 has argued that the present petitioner had earlier
filed a suit for permanent injunction against the present respondent Nos.1
and 2 on 09.02.2018 and in the said suit, injunction was sought against
respondent Nos.1 and 2 from dispossessing the plaintiff from the premises
in question. It is argued that it was the specific stand of respondent Nos.1
and 2 in the said proceedings that even respondent Nos.1 and 2 were doing
joint business in the demised premises as tenants for the last 40 years and
that the motor car sale and purchase and motorcar workshop was a
partnership concern and both the present petitioner and respondent No.1-
Madan Lal were partners in the same. It is further submitted that it was also
the case of respondent Nos.1 and 2 in the said suit that the petitioner had got
the name in the electricity connection changed from Surinder Kumar Madan
Lal to Suresh Kumar alone, which was an illegal act. It is submitted that
immediately thereafter, the petitioner filed the present suit for injunction on
15.03.2019 in which one of the prayers made was for restraining the
2 of 9
CR-6970-2019 (O&M) [3]
Corporation from changing the name in the electricity connection in
question from the name of the plaintiff/petitioner to that of any other name.
It is submitted that even a perusal of the plaint, more so paras 4 and 6,
would show that specific allegations have been levelled against the present
respondent Nos.1 and 2 in the same and thus, respondent Nos.1 and 2, who
are also claiming themselves to be co-tenants in the premises of which the
electricity connection is the subject matter of dispute and are also paying
electricity charges along with the plaintiff, are necessary parties and have a
right to be impleaded as parties. It is further submitted that defendant Nos.1
and 2 had filed written statement in the present suit and in the said written
statement, specific objections were raised by defendant Nos.1 and 2 to the
effect that the present respondent Nos.1 and 2 were necessary parties to the
suit as they were also tenants in the suit premises and the electricity
connection in question was not in the sole name of the plaintiff-petitioner. It
is submitted that since the application was filed within a period of 1 month
and 5 days of filing of the suit, thus, the suit was at the initial stage and
impleadment of respondent Nos.1 and 2 would help in properly and fully
adjudicating the case.
ANALYSIS AND FINDINGS:-
4. This Court has heard learned counsel for the parties and has
perused the paper book and finds that the impugned order deserves to be
upheld and the present revision petition being meritless, deserves to be
dismissed for the reasons stated hereinafter.
5. It is not in dispute that the present petitioner had earlier filed a
suit for permanent injunction against respondent Nos.1 and 2 namely
3 of 9
CR-6970-2019 (O&M) [4]
Madan Lal and Raju Mehta. The said suit was instituted on 09.02.2018.
Prayer made in the said suit is reproduced hereinbelow:-
"Under the circumstances, it is, therefore, prayed that a DECREE for permanent injunction restraining the defendants themselves or through any of their attorneys, privies, assignees, representatives, etc. from interfering and intermeddling into peaceful possession of the plaintiff or forcibly dispossessing the plaintiff from motor car workshop shed being run by plaintiff in Mission Compound, Court Road, Near Nanda Steel, Amritsar, belonging to Amritsar Diocesan Trust, Amritsar, as duly shown in site plan attached herewith as Mark-X; be passed in favour of the plaintiff and against defendants. Any other relief to which the plaintiff is found entitled under the law, may also be granted in his favour.
Dated: Through Counsel
Sd/- Ramesh Chaudhary
& Nitin Chaudhary, Advocates"
6. A perusal of the plaint (Annexure P-5) in the said suit would
show that it was the case of the present petitioner-plaintiff that respondent
Nos.1 and 2 herein, who were defendants in the said suit, had got some
documents prepared in their favour from the rival group of Amritsar
Diocesan Trust Office and had further averred that the electricity connection
was earlier in another name which was subsequently got changed by the
plaintiff. Although, written statement filed by respondent Nos.1 and 2, who
were defendants, in the said suit has not been annexed along with the
present revision petition but a perusal of the order dated 06.07.2018
(Annexure P-6), which was an order passed in an application filed under
4 of 9
CR-6970-2019 (O&M) [5]
Order 39 Rules 1 and 2 CPC by the petitioner in the said suit, would show
that it was the case of the present respondent Nos.1 and 2 in the said suit
that plaintiff-present petitioner and respondent Nos.1 and 2 were jointly
doing business in the demised premises as tenants of Amritsar Diocesan
Trust for the last 40 years and there was a partnership between them and
further that the present petitioner-plaintiff in order to create evidence in his
favour had got changed the name of the electricity connection in the
premises in question, in the Electricity Department from Surinder Kumar
Madan Lal to Suresh Kumar alone, although the electricity bills were paid
jointly by them.
7. On 15.03.2019, the plaintiff had filed the present suit while
impleading Punjab State Power Corporation Limited as defendant Nos.1
and 2 without impleading the present respondent Nos.1 and 2. Prayer in the
said suit is reproduced hereinbelow:-
"In the light of the facts stated above it is prayed that suit of the plaintiff may kindly be decreed with costs for permanent injunction restraining the defendants, its officials from disconnecting the electricity connection and from changing the name of plaintiff as subscriber/consumer of electricity connection account no.C16LR28/0624M to any other name. Any other relief to which the plaintiff is found entitled be also granted in favour of plaintiff with costs in the interest of justice, equity and fair play.
Plaintiff Suresh Kumar Through counsel Ashwani Bansal Advocate Manish Bansal Advocate"
5 of 9
CR-6970-2019 (O&M) [6]
8. A perusal of the said prayer would show that apart from
seeking injunction restraining the defendants, who are Punjab State Power
Corporation Limited, from disconnecting the electricity connection, further
prayer has been made for restraining the defendants from changing the
name of the plaintiff as subscriber/consumer of electricity connection
account No.C16LR28/0624M to any other name. Normally, in a simplicitor
suit for injunction, impleadment of a third party is not to be entertained,
however, in the peculiar facts and circumstances of the present case, more
so, when the above additional prayer has been made by the plaintiff-
petitioner, then, it cannot be said that respondent Nos.1 and 2 in the present
suit are neither necessary nor proper parties. In case, the petitioner-plaintiff
succeeds in getting the injunction on the second aspect i.e., restraining the
Department from changing the name of the plaintiff as consumer in the
electricity connection in question to any other name, then, the same can
cause serious prejudice to the rights of the respondent Nos.1 and 2, as it is
the case of respondent Nos.1 and 2 that the tenancy is joint and the
electricity charges are also being paid by them, in the earlier suit for
injunction filed by the plaintiff.
9. Further a perusal of the plaint in the present suit, which has
been annexed as Annexure P-4, would show that in paras 4 and 6, specific
pleadings with respect to the present respondent Nos.1 and 2 have been
made, which are to the effect that officials of the Punjab State Power
Corporation Limited are hand in glove with Madan Lal and Raju Mehta,
who were having dispute with the petitioner-plaintiff and who are trying to
dispossess the petitioner-plaintiff and that several complaints were given by
6 of 9
CR-6970-2019 (O&M) [7]
Madan Lal and Raju Mehta on account of which the Department is also
acting against the petitioner-plaintiff. However, in spite of the said specific
averments, the plaintiff had chosen not to implead respondent Nos.1 and 2
in the present case. A perusal of the impugned order would show that even
defendant Nos.1 and 2 i.e., Punjab State Power Corporation Limited had
taken a specific objection in the written statement that Madan Lal is a
necessary party to the present suit as he was also a tenant in the suit
property and the electricity connection in question is not in the sole name of
the plaintiff. It had further been observed by the trial Court in the impugned
order dated 01.10.2019 that certain documents filed on record by defendant
Nos.1 and 2 also showed that applicants-present respondent Nos.1 and 2 are
also tenants along with the petitioner-plaintiff. In the said circumstances, the
trial Court had allowed the application for impleadment.
10. It is not disputed before this Court that the stage at which the
application for impleadment was filed, was the stage prior to framing of the
issues, inasmuch as, the date of the plaint in the present suit is 15.03.2019
whereas the application for impleadment had been filed on 20.04.2019,
which had been allowed vide impugned order dated 01.10.2019. It is in the
present revision petition filed by the petitioner that an interim order was
passed by the Coordinate Bench of this Court on 16.12.2019 directing the
trial Court to adjourn the proceedings, on account of which the suit filed by
the petitioner-plaintiff is still at the initial stage. In the said peculiar facts
and circumstances of the case, this Court is of the opinion that respondent
Nos.1 and 2 cannot be stated to be neither necessary nor proper parties for
final and proper adjudication of the case. In fact, it would be in the interest
7 of 9
CR-6970-2019 (O&M) [8]
of the petitioner also to permit the present respondent Nos.1 and 2 to be
impleaded as parties, so that the matter can be finally and properly
adjudicated and in case the petitioner is to win then an effective decree
could be passed.
11. The Hon'ble Supreme Court in the case of "Shalini Shyam
Shetty and another Vs. Rajendra Shankar Patil", reported as (2010) 8
Supreme Court Cases 329, had observed that the High Courts cannot, at the
drop of a hat, in exercise of its power of superintendence under Article 227
of the Constitution, interfere with the orders of tribunals or courts inferior to
it. Nor can it, in exercise of this power, act as a court of appeal over the
orders of court or tribunal subordinate to it. It was also observed in the said
judgment that a statutory amendment with respect to Section 115 of the
Civil Procedure Code does not and cannot cut down the ambit of High
Court's power under Article 227 but at the same time, it must be
remembered that such statutory amendment does not correspondingly
expand the High Court's jurisdiction of superintendence under Article 227.
The power of interference under this Article is to be kept to the minimum to
ensure that the wheel of justice does not come to a halt and the fountain of
justice remains pure and unpolluted in order to maintain public confidence
in the functioning of the tribunals and courts subordinate to the High Court.
It was also observed that the power under Article 227 may be unfettered but
its exercise is subject to high degree of judicial discipline.
12. Keeping in view the above, this Court is of the opinion that the
impugned order does not call for any interference by this Court while
exercising its powers under Article 227 of the Constitution of India and
8 of 9
CR-6970-2019 (O&M) [9]
accordingly, the impugned order is upheld and the present revision petition
being meritless, deserves to be dismissed and is dismissed.
13. It would be relevant to note that the observations made in the
present order should not be construed as an expression on the merits of the
main case and the trial Court would decide the main case independently, as
the present observations have been made only to consider the correctness of
the impugned order vide which the application filed by respondent Nos.1
and 2 for impleadment under Order 1 Rule 10 CPC had been allowed and
the main suit would be decided independently by the trial Court after taking
into consideration the entire evidence and documents led by the parties.
14. All the pending miscellaneous applications, if any, shall stand
disposed of in view of the abovesaid order.
15.12.2025 (VIKAS BAHL)
Pawan JUDGE
Whether speaking/reasoned:- Yes/No
Whether reportable:- Yes/No
9 of 9
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!