Citation : 2024 Latest Caselaw 10696 P&H
Judgement Date : 3 July, 2024
Neutral Citation No:=2024:PHHC:082203
ARB-119-2022 -1-
IN THE HIGH COURT OF PUNJAB & HARYANA AT
CHANDIGARH
245 ARB-119-2022
Date of decision:03.07.2024
M/S ASHA SINGHAL ...PETITIONER
VS.
UNION TERRITORY OF CHANDIGARH AND OTHERS
...RESPONDENTS
CORAM: HON'BLE MR. JUSTICE SUVIR SEHGAL
Present: Mr. Prince Goyal, Advocate
for the petitioner.
Mr. Ashish Rawal, Advocate
for the respondents.
***
SUVIR SEHGAL J.
1. Instant petition has been filed under Section 11 of the
Arbitration and Conciliation Act, 1996, (for short "the Act"), for
appointment of an independent Arbitrator to decide the claim of the
petitioner.
2. Counsel for the petitioner submits that the petitioner was
allotted work of construction of Community Centre at Model Jail, U.T.,
Chandigarh, vide allotment letter dated 20.12.2012, Annexure A-1. He
submits that the general conditions of the contract for C.P.W.D. works -
1 of 9
Neutral Citation No:=2024:PHHC:082203
2010 formed a part and parcel of the contract agreement and Clause 25,
thereof, provides for settlement of disputes by way of arbitration. He
submits that the petitioner completed the work on 31.07.2016, but the
final bill remained unpaid and a communication dated 18.02.2021,
Annexure A-3, was sent to the respondent for balance payment, which
was followed by communications, Annexures A-4 and A-5. He submits
that vide memo dated 09.07.2021, Annexure A-7, respondents intimated
that no final bill or claim is pending with them. Petitioner by
communication dated 31.07.2021, Annexure A-8, sent a copy of the
measurement bill and requested for payment. When no response was
received, petitioner invoked the arbitration clause by serving a notice
dated 20.11.2021, Annexure A-9, which remained unattended.
3. Upon notice, petition has been contested by the respondents by
filing a reply, wherein it has been submitted that the petitioner was
unable to complete the work, which was withdrawn from him vide letter
dated 18.07.2016, Annexure R-1, and the remaining work was assigned
to another agency. It has been submitted that a gross amount of
Rs.1,17,58,159/- was sanctioned and after making deductions, the
balance amount was released to the petitioner. A categoric stand has
been taken that the measurement bill refer to by the petitioner was paid
in November, 2015, and the petitioner has raised a claim after the expiry
of the period of limitation.
4. Counsel for the respondents submits that as the claim is barred
by time, the petition deserves to be dismissed. He has placed reliance
2 of 9
Neutral Citation No:=2024:PHHC:082203
upon a judgment of the Supreme Court in Secunderabad Cantonment
Board Versus M/s B. Ramachandraiah & Sons 2021 AIR (SC) 1391.
5. I have heard counsel for the parties and considered their
respective submissions.
6. At the outset, arbitration clause deserves to be noticed and is
reproduced hereunder:-
"CLAUSE 25 Settlement of Disputes & Arbitration Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the specifications, design, drawings and instructions here-in before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter:
(i) If the contractor considers any work demanded of him to be outside the requirements of the contract, or disputes any drawings, record or decision given in writing by the Engineer-in-Charge on any matter in connection with or arising out of the contract or carrying out of the work, to be unacceptable, he shall promptly within 15 days
3 of 9
Neutral Citation No:=2024:PHHC:082203
request the Superintending Engineer in writing for written instruction or decision. Thereupon, the Superintending Engineer shall give his written instructions or decision within a period of one month from the receipt of the contractor's letter.
If the Superintending Engineer fails to give his instructions or decision in writing within the aforesaid period or if the contractor is dissatisfied with the instructions or decision of the Superintending Engineer, the contractor may, within 15 days of the receipt of Superintending Engineer's decision, appeal to the Chief Engineer who shall afford an opportunity to the contractor to be heard, if the latter so desires, and to offer evidence in support of his appeal. The Chief Engineer shall give his decision within 30 days of receipt of contractor's appeal. If the contractor is dissatisfied with this decision, the contractor shall within a period of 30 days from receipt of the decision, give notice to the Chief Engineer for appointment of arbitrator on prescribed proforma as per Appendix XV, failing which the said decision shall be final binding and conclusive and not referable to adjudication by the arbitrator.
(ii) Except where the decision has become final, binding and conclusive in terms of Sub Para
(i) above, disputes or difference shall be referred for adjudication through arbitration by a sole arbitrator appointed by the Chief Engineer, CPWD, in charge of the work or if there be no Chief Engineer, the Additional Director General of the concerned region of CPWD or if there be no
4 of 9
Neutral Citation No:=2024:PHHC:082203
Additional Director General, the Director General of Works, CPWD. If the arbitrator so appointed is unable or unwilling to act or resigns his appointment or vacates his office due to any reason whatsoever, another sole arbitrator shall be appointed in the manner aforesaid. Such person shall be entitled to proceed with the reference from the stage at which it was left by his predecessor.
It is a term of this contract that the party invoking arbitration shall give a list of disputes with amounts claimed in respect of each such dispute along with the notice for appointment of arbitrator and giving reference to the rejection by the Chief Engineer of the appeal.
It is also a term of this contract that no person, other than a person appointed by such Chief Engineer CPWD or Additional Director General or Director General of works, CPWD, as aforesaid, should act as arbitrator and if for any reason that is not possible, the matter shall not be referred to arbitration at all.
It is also a term of this contract that if the contractor does not make any demand for appointment of arbitrator in respect of any claims in writing as aforesaid within 120 days of receiving the intimation from the Engineer-in-charge that the final bill is ready for payment, the claim of the contractor shall be deemed to have been waived and absolutely barred and the Government shall be discharged and released of all liabilities under the contract in respect of these claims.
The arbitration shall be conducted in
5 of 9
Neutral Citation No:=2024:PHHC:082203
accordance with the provisions of the Arbitration and Conciliation Act, 1996 (26 of 1996) or any statutory modifications or re-enactment thereof and the rules made thereunder and for the time being in force shall apply to the arbitration proceeding under this clause.
It is also a term of this contract that the arbitrator shall adjudicate on only such disputes as are referred to him by the appointing authority and give separate award against each dispute and claim referred to him and in all cases where the total amount of the claims by any party exceeds Rs.1,00,000/-, the arbitrator shall give reasons for the award. It is also a term of the contract that if any fees are payable to the arbitrator, these shall be paid equally by both the parties.
It is also a term of the contract that the arbitrator shall be deemed to have entered on the reference on the date he issues notice to both the parties calling them to submit their statement of claims and counter statement of claims. The venue of the arbitration shall be such place as may be fixed by the arbitrator in his sole discretion. The fees, if any, of the arbitrator shall, if required to be paid before the award is made and published, be paid half and half by each of the parties. The cost of the reference and of the award (including the fees, if any, of the arbitrator) shall be in the discretion of the arbitrator who may direct to any by whom and in what manner, such costs or any part thereof shall be paid and fix or settle the amount of costs to be so paid."
6 of 9
Neutral Citation No:=2024:PHHC:082203
7. A perusal of the clause reproduced above shows that a
contractor is required to raise a claim within 120 days of receiving
intimation from the Engineer In-charge that the final bill is ready for
payment, failing which, it shall be deemed that he has waived his right.
Document appended by the respondents with reply, Annexure R-4,
shows the details of the running bills raised by the petitioner and the
payments made against them. Its perusal makes it apparent that the final
bill was never prepared. It cannot, therefore, be said that the petitioner at
any stage received any information from the Engineer In-charge that the
final bill has been prepared for payment. In any case, the period of 120
days as specified in the above reproduced clause is hit by Section 28 of
the Contract Act as has been held by the Supreme Court in Grasim
Industries Ltd. Versus State of Kerala, (2018) 14 SCC 265.
8. Coming to the objection of limitation raised by the
respondents, suffice is to mention that Supreme Court in Bharat
Sanchar Nigam Ltd. & Anr. Versus M/s Nortel Networks India Pvt.
Ltd. (2021) 5 SCC 738, has held that the issue of limitation pertains to
the maintainability or admissibility of the claim, which has to be decided
by the arbitral tribunal. As to whether the claim is barred by time or is
prohibited because of non-fulfillment of some condition in the
arbitration clause has to be decided by the arbitral tribunal either as a
preliminary issue or at the final stage after evidence is led by the parties.
9. This Court is, therefore, of the view that the petition deserves
to succeed. To be fair to the counsel for the respondents, it deserves to be
7 of 9
Neutral Citation No:=2024:PHHC:082203
noted that the judgment in Secunderabad Cantonment Board's case
(supra), would not be of any help to them as in the said matter, after
invoking the arbitration clause vide letter issued in November, 2006, the
claimant had filed a petition seeking appointment of an Arbitrator in the
year 2013. In this background, Supreme Court held that the petition
seeking appointment of an Arbitrator is barred by time. This judgment is
not applicable to the facts of the present case.
10. Consequently, petition is allowed. Mr. Sanjeev Kaushik,
former Member Judicial, Central Administrative Tribunal, Kothi
No.1033, Sector 12-A, Panchkula, Mobile No.9417233385 is appointed
as the sole Arbitrator to adjudicate the dispute between the parties,
subject to declaration to be made by him under Section 12 of the Act
with regard to his independence and impartiality to adjudicate the
dispute between the parties.
11. Parties are directed to appear before the learned Arbitrator on
05.08.2024 or on any day, time and place to be fixed and communicated
by the learned Arbitrator at his convenience.
12. The arbitrator shall be paid fee in accordance with the Fourth
Schedule of the Act, as amended.
13. The arbitrator is requested to complete the proceedings as per
time limit specified under Section 29-A of the Act.
14. Needless to mention that all the questions arising between the
parties in this matter shall remain open for determination in the arbitral
proceedings and any observation made hereinabove will not be binding on
8 of 9
Neutral Citation No:=2024:PHHC:082203
the learned Arbitrator.
15. Copy of the order be sent to the learned arbitrator.
03.07.2024 (SUVIR SEHGAL)
sheetal JUDGE
Whether Speaking/Reasoned Yes/No
Whether Reportable Yes/No
9 of 9
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!