Tuesday, 02, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S R.S. Builders vs Municipal Corporation Amritsar And Ors
2024 Latest Caselaw 9108 P&H

Citation : 2024 Latest Caselaw 9108 P&H
Judgement Date : 29 April, 2024

Punjab-Haryana High Court

M/S R.S. Builders vs Municipal Corporation Amritsar And Ors on 29 April, 2024

Author: Suvir Sehgal

Bench: Suvir Sehgal

                               Neutral Citation No:=2024:PHHC:058436



ARB-488-2023 (O&M)                                              -1-


                               Neutral Citation No. 2024:PHHC:058436

     IN THE HIGH COURT OF PUNJAB AND HARYANA AT
                    CHANDIGARH

277                                          ARB-488-2023 (O&M)
                                             Date of Decision:29.04.2024



M/s R.S. Builders
                                                              ... Petitioner


                                       Vs

Municipal Corporation, Amritsar and others
                                                          .... Respondents


CORAM: HON'BLE MR. JUSTICE SUVIR SEHGAL

Present: Mr. Dheeraj Mahajan, Advocate for the petitioner.

            Mr. Sarthak Soni, Advocate for
            Mr. Sanjeev Soni, Advocate for the respondents.

                                   ***

SUVIR SEHGAL, J. (ORAL)

1. Instant petition has been filed under Section 11(6) of the

Arbitration and Conciliation Act, 1996 (for short 'the Act') for

appointment of an Arbitrator to adjudicate the dispute between the

parties.

2. Counsel for the petitioner submits that the petitioner was

given a work vide order dated 22.01.2020, Annexure P-1, for

augmentation of water supply pipe line of Amritsar Town under

AMRUT (Package-I). He submits that a contract agreement was

signed between the parties and clause 25 of the conditions of the

contract provides for reference of dispute to arbitrator/arbitral

1 of 3

Neutral Citation No:=2024:PHHC:058436

ARB-488-2023 (O&M) -2-

Tribunal. He submits that in terms thereof, petitioner approached the

Executive Engineer by notice dated 14.06.2023, Annexure P-3, who

did not respond. He submits that after waiting for almost 3 months,

petitioner served a legal notice dated 08.09.2023, Annexure P-4,

invoking the arbitration clause without any result.

3. Written statement has been filed on behalf of the

respondents, which is taken on record, wherein it has been submitted

that the claim has not been submitted within a period of six months of

the date of completion as certified by the Engineer. Still further

another objection has been taken that the claim raised by the petitioner

is more than Rs.15 Crores.

4. Counsel for the petitioner has invited the attention of the

Court to para 10 of the petition, which is supported with an affidavit

of the petitioner to submit that the approximate value of the claim is

around Rs.2 Crores and the notice invoking the arbitration clause,

Annexure P-4 has been served by raising an escalated claim. Counsel

further submits that the petitioner would file an appropriate claim

before the Arbitrator. He has also placed reliance upon the judgment

of the Supreme Court in Grasim Industries Ltd. Versus State of

Kerala, 2018 (14) SCC 265.

5. I have heard counsel for the parties and have considered

their respective submissions.

6. In Grasim Industries's case (supra), interpreting Section

28(b) of the Contract Act, 1872, Supreme Court has held that if a

restricted period for raising an arbitral dispute has been provided, the

2 of 3

Neutral Citation No:=2024:PHHC:058436

ARB-488-2023 (O&M) -3-

same has to be treated as void. Consequently, the objections raised by

the respondents are rejected.

10. Petition is allowed.

11. Mr. Justice (Retd.) Darshan Singh, Former Judge of Punjab

and Haryana High Court, H.No.56, Sector 16-A, Chandigarh,

08558809940 is requested to act as an Arbitrator to adjudicate the

dispute between the parties, subject to compliance of statutory

requirements.

12. Parties are directed to appear before the learned Arbitrator

on date, time and place to be fixed by the Arbitrator at his

convenience.

13. Parties will be at liberty to raise all the

claims/defences/counter claims/pleas before the Arbitrator.

14. Needless to mention that all the questions arising between

the parties in this matter will remain open for determination in the

arbitration proceedings and any observation made hereinabove will

not be binding on the learned Arbitrator.

15. A request letter along with a copy of this order be sent to

Mr. Justice (Retd.) Darshan Singh.




29.04.2024                                                   (SUVIR SEHGAL)
pooja saini                                                      JUDGE

         Whether Speaking/Reasoned                  Yes/No
         Whether Reportable                         Yes/No




                                     3 of 3

 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter