Citation : 2024 Latest Caselaw 9058 P&H
Judgement Date : 29 April, 2024
Neutral Citation No:=2024:PHHC:059266
2024:PHHC:059266
ARB-137-2020 -1-
IN THE HIGH COURT OF PUNJAB & HARYANA AT
CHANDIGARH
108 ARB-137-2020
Date of decision:29.04.2024
M/S HIL LIMITED ...PETITIONER
VS.
M/S STURDY INDUSTRIES LIMITED ...RESPONDENT
CORAM: HON'BLE MR. JUSTICE SUVIR SEHGAL
Present: Mr. Rohit Khanna, Advocate,
Ms. Simran Sharma, Advocate &
Mr. Siddharth Kohli, Advocate for the petitioner.
Mr. Aashish Chopra, Senior Advocate
through video conferencing with
Ms. Rupa Pathania, Advocate and
Ms. Nitika Sharma, Advocate for the respondent.
***
SUVIR SEHGAL J.
1. By way of present petition filed under Section 11 of the
Arbitration and Conciliation Act, 1996, (for short "the Act"), petitioner
has approached this Court for appointment of an Arbitrator.
2. Counsel for the petitioner submits that under a lease deed
dated 06.09.2010, Annexure P-1, executed between the petitioner and the
respondent for a period of 10 years, petitioner took on lease the factory
premises and its assets. He submits that Clause 13 of the lease deed
provided for appointment of an Arbitrator to resolve the disputes
between the parties. The lease was terminated by the respondent by
1 of 7
Neutral Citation No:=2024:PHHC:059266
2024:PHHC:059266
notice dated 04.07.2013, Annexure P-2, and as some disputes arose
between the parties, on a petition filed by the respondent, this Court by
order dated 11.07.2014, Annexure P-3, appointed Mr. Justice M.
Jagannadha Rao, Retired Judge of the Supreme Court, as the sole
Arbitrator. He submits that the learned Arbitrator passed an award dated
06.11.2019, Annexure P-4, and petitioner was found entitled to
Rs.90,85,483/- alongwith interest. Counsel submits that respondent has
filed objections under Section 34 of the Act and the petitioner has filed
an execution petition, which is pending. He submits that in terms of the
award, respondent took back the physical possession of the factory
premises on 05.03.2020. Counsel submits that the petitioner had to bear
the expenses for maintaining of the plant from the date of termination of
the lease till its possession was taken over by the respondent. He submits
that the expenses have been quantified at Rs.1,51,00,429/- and the
petitioner issued legal notice dated 15.07.2020, Annexure P-11, invoking
the arbitration clause, to which the respondent submitted a reply dated
19.08.2020, Annexure P-12, denying its liability to make any payment.
3. Upon notice, petition has been opposed by the respondent by
filing a reply primarily on four grounds, which are discussed in the
succeeding paragraphs.
4. I have heard counsel for the parties and considered their
respective submissions.
5. The foremost objection raised by the respondent is that the
petitioner has failed to resort to mutual consultation before invoking the
arbitration clause. At this stage, it is necessary to notice the arbitration
2 of 7
Neutral Citation No:=2024:PHHC:059266
2024:PHHC:059266
clause, which is reproduced hereunder:-
"(13) Dispute Resolution:
The Parties shall make endeavors to settle by mutual consultation any claim, dispute, or controversy arising out of, or in relation or under this Agreement, interpretation of any Clause(s), performance of illegible (sic) hereunder or the breach or alleged breach of the Agreement or any part herein falling which the disputes would be resolved by means or (sic of) arbitration under the Arbitration and Conciliation Act, 1996. The arbitration proceedings shall be held in the English language and governed by the provisions of the Arbitration & Conciliation Act, 1996 and the place of arbitration shall be HYDERABAD. Further, the Courts in Chandigarh only will have jurisdiction to decide all disputes arising out of the present Lease Deed."
6. From a perusal of the above reproduced clause, it is evident
that it is not mandatory for the parties to attempt resolution of the dispute
by mutual consultation as the clause provides that endeavour be made to
settle the disputes, claims etc. by mutual consent. Resorting to mutual
consent cannot be said to be a pre-condition before invoking arbitration.
Consequently, the respondent cannot insist upon mutual consultation
prior to the reference of the dispute to the Arbitrator.
7. Secondly, it has been contended on behalf of the respondent
that the lease deed, Annexure P-1, was terminated by serving a notice
dated 04.07.2013, Annexure P-2, and the contract cannot be said to be
perpetuating. It is his argument that the arbitration clause, which is a part
3 of 7
Neutral Citation No:=2024:PHHC:059266
2024:PHHC:059266
of the terminated lease deed, cannot be invoked. This argument deserves
to be noticed and rejected. The settled legal position is that arbitration
clause, which forms part of a contract has to be treated as an agreement
independent of the other terms of the contract and can be separately
enforced. In National Agricultural Co-operative Marketing Federation
India Limited Vs. Gains Trading Limited (2007) 5 SCC 692, Supreme
Court has held that even if the performance of the contract comes to an
end on account of repudiation, frustration or breach of contract, the
arbitration agreement would survive for the purpose of resolution of
disputes arising under or in connection with the contract.
8. Thirdly, by referring to issue No.3 framed by the learned
Arbitral Tribunal, it has been argued on behalf of the respondent that on
a counter claim raised by the petitioner, the Tribunal had framed the
following issue:-
"Whether the respondent is entitled to reimbursement of all further expenses that may be incurred by the respondent till the factory is taken over by the claimant."
9. Counsel for the respondent submits that on the basis of the
material placed before the learned Arbitrator, the Tribunal did not award
any amount to the petitioner for the expenditure allegedly incurred by it
beyond November, 2015, as it failed to submit any documents. By
placing reliance on Tantia Construction Limited Versus Union of India
2021 SCC Online Crl. 2465, he asserts that petitioner is re-agitating the
claim, which is impermissible.
4 of 7
Neutral Citation No:=2024:PHHC:059266
2024:PHHC:059266
10. A perusal of the demand notice, Annexure P-11, served by the
petitioner shows that he is claiming expenditure incurred on the
maintenance of the factory premises from the date of termination till the
date of taking of its possession by the respondent on 05.03.2020. Award,
Annexure P-4, was passed by the Arbitrator on 06.11.2019, therefore, it
cannot be said that the claim had arisen before passing of the award.
Moreover, as has been held in Gammon India Limited and another
Versus National Highways Authority of India 2020 SCC Online Del
659, that filing of different claims at different stages of a contract or
project is permissible in law. As to whether there is a duplication of the
claims and whether they can be adjudicated, would lie within the ambit
of the Arbitrator. Therefore, this objection raised by the respondent
cannot be sustained.
11. The judgment in Tantia Construction Limited (supra) would
not be of any assistance to the respondent. The High Court had compared
the claim adjudicated by the Arbitrator and the claims being freshly
raised and came to the conclusion that there is no subsisting dispute
which requires consideration. This is not the situation in the case in hand
as part of the freshly raised claim has arisen after the previous reference
and determination by the Arbitral Tribunal.
12. Lastly, respondents have submitted that the dispute does not
fall within the realm of arbitration clause and is beyond the terms of the
lease deed. The respondent is de-barred from raising this objection as a
similar issue (issue No.3) was framed by the learned Arbitrator and
determined by it by its award, Annexure P-4, without any objection by
5 of 7
Neutral Citation No:=2024:PHHC:059266
2024:PHHC:059266
the respondent.
13. It will not be out of place to observe that on the previous
occasion, reference to arbitration was sought by the respondent and
accepted by this Court vide order, Annexure P-3. Now, when the
petitioner is raising claim and seeking reference, respondent cannot
volte-face and oppose the petition.
14. In view of the above discussion, all the objections raised by the
respondents are liable to be and are rejected. Prayer made in the petition
deserves to be acceded to.
15. Petition is allowed. Mr. Justice M. Jagannadha Rao, a former
judge of the Supreme Court, H.No.3-6-281/B, 2nd Floor, Above State
Bank of India, Opp. Old MLA Quarters, Himayatnagar, Hyderabad,
040-23224533, is requested to act as a sole Arbitrator to determine the
dispute between the parties.
16. Parties are directed to appear before the learned Arbitrator on a
day, time and place to be communicated by him.
17. It is clarified that it would be open to the parties to raise all the
claims, counter claims, defences, pleas etc. before the learned Arbitrator
and any observation made hereinabove shall not prejudice the arbitral
proceedings.
18. Needless to mention that all the questions arising between the
parties in this matter shall remain open for determination in the arbitral
proceedings and any observation made hereinabove will not be binding
on the learned Arbitrator.
6 of 7
Neutral Citation No:=2024:PHHC:059266
2024:PHHC:059266
19. A request letter alongwith a copy of this order be sent to
Mr. Justice (Retd.) M. Jagannadha Rao.
29.04.2024 (SUVIR SEHGAL)
sheetal JUDGE
Whether Speaking/Reasoned Yes/No
Whether Reportable Yes/No
7 of 7
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!