Tuesday, 02, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Hil Limited vs M/S Sturdy Industries Limited
2024 Latest Caselaw 9058 P&H

Citation : 2024 Latest Caselaw 9058 P&H
Judgement Date : 29 April, 2024

Punjab-Haryana High Court

M/S Hil Limited vs M/S Sturdy Industries Limited on 29 April, 2024

Author: Suvir Sehgal

Bench: Suvir Sehgal

                                Neutral Citation No:=2024:PHHC:059266



                                          2024:PHHC:059266

ARB-137-2020                                         -1-


      IN THE HIGH COURT OF PUNJAB & HARYANA AT
                     CHANDIGARH


108                            ARB-137-2020
                               Date of decision:29.04.2024


M/S HIL LIMITED                                      ...PETITIONER

                               VS.

M/S STURDY INDUSTRIES LIMITED                         ...RESPONDENT


CORAM: HON'BLE MR. JUSTICE SUVIR SEHGAL


Present: Mr. Rohit Khanna, Advocate,
         Ms. Simran Sharma, Advocate &
         Mr. Siddharth Kohli, Advocate for the petitioner.

         Mr. Aashish Chopra, Senior Advocate
         through video conferencing with
         Ms. Rupa Pathania, Advocate and
         Ms. Nitika Sharma, Advocate for the respondent.

                    ***

SUVIR SEHGAL J.

1. By way of present petition filed under Section 11 of the

Arbitration and Conciliation Act, 1996, (for short "the Act"), petitioner

has approached this Court for appointment of an Arbitrator.

2. Counsel for the petitioner submits that under a lease deed

dated 06.09.2010, Annexure P-1, executed between the petitioner and the

respondent for a period of 10 years, petitioner took on lease the factory

premises and its assets. He submits that Clause 13 of the lease deed

provided for appointment of an Arbitrator to resolve the disputes

between the parties. The lease was terminated by the respondent by

1 of 7

Neutral Citation No:=2024:PHHC:059266

2024:PHHC:059266

notice dated 04.07.2013, Annexure P-2, and as some disputes arose

between the parties, on a petition filed by the respondent, this Court by

order dated 11.07.2014, Annexure P-3, appointed Mr. Justice M.

Jagannadha Rao, Retired Judge of the Supreme Court, as the sole

Arbitrator. He submits that the learned Arbitrator passed an award dated

06.11.2019, Annexure P-4, and petitioner was found entitled to

Rs.90,85,483/- alongwith interest. Counsel submits that respondent has

filed objections under Section 34 of the Act and the petitioner has filed

an execution petition, which is pending. He submits that in terms of the

award, respondent took back the physical possession of the factory

premises on 05.03.2020. Counsel submits that the petitioner had to bear

the expenses for maintaining of the plant from the date of termination of

the lease till its possession was taken over by the respondent. He submits

that the expenses have been quantified at Rs.1,51,00,429/- and the

petitioner issued legal notice dated 15.07.2020, Annexure P-11, invoking

the arbitration clause, to which the respondent submitted a reply dated

19.08.2020, Annexure P-12, denying its liability to make any payment.

3. Upon notice, petition has been opposed by the respondent by

filing a reply primarily on four grounds, which are discussed in the

succeeding paragraphs.

4. I have heard counsel for the parties and considered their

respective submissions.

5. The foremost objection raised by the respondent is that the

petitioner has failed to resort to mutual consultation before invoking the

arbitration clause. At this stage, it is necessary to notice the arbitration

2 of 7

Neutral Citation No:=2024:PHHC:059266

2024:PHHC:059266

clause, which is reproduced hereunder:-

"(13) Dispute Resolution:

The Parties shall make endeavors to settle by mutual consultation any claim, dispute, or controversy arising out of, or in relation or under this Agreement, interpretation of any Clause(s), performance of illegible (sic) hereunder or the breach or alleged breach of the Agreement or any part herein falling which the disputes would be resolved by means or (sic of) arbitration under the Arbitration and Conciliation Act, 1996. The arbitration proceedings shall be held in the English language and governed by the provisions of the Arbitration & Conciliation Act, 1996 and the place of arbitration shall be HYDERABAD. Further, the Courts in Chandigarh only will have jurisdiction to decide all disputes arising out of the present Lease Deed."

6. From a perusal of the above reproduced clause, it is evident

that it is not mandatory for the parties to attempt resolution of the dispute

by mutual consultation as the clause provides that endeavour be made to

settle the disputes, claims etc. by mutual consent. Resorting to mutual

consent cannot be said to be a pre-condition before invoking arbitration.

Consequently, the respondent cannot insist upon mutual consultation

prior to the reference of the dispute to the Arbitrator.

7. Secondly, it has been contended on behalf of the respondent

that the lease deed, Annexure P-1, was terminated by serving a notice

dated 04.07.2013, Annexure P-2, and the contract cannot be said to be

perpetuating. It is his argument that the arbitration clause, which is a part

3 of 7

Neutral Citation No:=2024:PHHC:059266

2024:PHHC:059266

of the terminated lease deed, cannot be invoked. This argument deserves

to be noticed and rejected. The settled legal position is that arbitration

clause, which forms part of a contract has to be treated as an agreement

independent of the other terms of the contract and can be separately

enforced. In National Agricultural Co-operative Marketing Federation

India Limited Vs. Gains Trading Limited (2007) 5 SCC 692, Supreme

Court has held that even if the performance of the contract comes to an

end on account of repudiation, frustration or breach of contract, the

arbitration agreement would survive for the purpose of resolution of

disputes arising under or in connection with the contract.

8. Thirdly, by referring to issue No.3 framed by the learned

Arbitral Tribunal, it has been argued on behalf of the respondent that on

a counter claim raised by the petitioner, the Tribunal had framed the

following issue:-

"Whether the respondent is entitled to reimbursement of all further expenses that may be incurred by the respondent till the factory is taken over by the claimant."

9. Counsel for the respondent submits that on the basis of the

material placed before the learned Arbitrator, the Tribunal did not award

any amount to the petitioner for the expenditure allegedly incurred by it

beyond November, 2015, as it failed to submit any documents. By

placing reliance on Tantia Construction Limited Versus Union of India

2021 SCC Online Crl. 2465, he asserts that petitioner is re-agitating the

claim, which is impermissible.

4 of 7

Neutral Citation No:=2024:PHHC:059266

2024:PHHC:059266

10. A perusal of the demand notice, Annexure P-11, served by the

petitioner shows that he is claiming expenditure incurred on the

maintenance of the factory premises from the date of termination till the

date of taking of its possession by the respondent on 05.03.2020. Award,

Annexure P-4, was passed by the Arbitrator on 06.11.2019, therefore, it

cannot be said that the claim had arisen before passing of the award.

Moreover, as has been held in Gammon India Limited and another

Versus National Highways Authority of India 2020 SCC Online Del

659, that filing of different claims at different stages of a contract or

project is permissible in law. As to whether there is a duplication of the

claims and whether they can be adjudicated, would lie within the ambit

of the Arbitrator. Therefore, this objection raised by the respondent

cannot be sustained.

11. The judgment in Tantia Construction Limited (supra) would

not be of any assistance to the respondent. The High Court had compared

the claim adjudicated by the Arbitrator and the claims being freshly

raised and came to the conclusion that there is no subsisting dispute

which requires consideration. This is not the situation in the case in hand

as part of the freshly raised claim has arisen after the previous reference

and determination by the Arbitral Tribunal.

12. Lastly, respondents have submitted that the dispute does not

fall within the realm of arbitration clause and is beyond the terms of the

lease deed. The respondent is de-barred from raising this objection as a

similar issue (issue No.3) was framed by the learned Arbitrator and

determined by it by its award, Annexure P-4, without any objection by

5 of 7

Neutral Citation No:=2024:PHHC:059266

2024:PHHC:059266

the respondent.

13. It will not be out of place to observe that on the previous

occasion, reference to arbitration was sought by the respondent and

accepted by this Court vide order, Annexure P-3. Now, when the

petitioner is raising claim and seeking reference, respondent cannot

volte-face and oppose the petition.

14. In view of the above discussion, all the objections raised by the

respondents are liable to be and are rejected. Prayer made in the petition

deserves to be acceded to.

15. Petition is allowed. Mr. Justice M. Jagannadha Rao, a former

judge of the Supreme Court, H.No.3-6-281/B, 2nd Floor, Above State

Bank of India, Opp. Old MLA Quarters, Himayatnagar, Hyderabad,

040-23224533, is requested to act as a sole Arbitrator to determine the

dispute between the parties.

16. Parties are directed to appear before the learned Arbitrator on a

day, time and place to be communicated by him.

17. It is clarified that it would be open to the parties to raise all the

claims, counter claims, defences, pleas etc. before the learned Arbitrator

and any observation made hereinabove shall not prejudice the arbitral

proceedings.

18. Needless to mention that all the questions arising between the

parties in this matter shall remain open for determination in the arbitral

proceedings and any observation made hereinabove will not be binding

on the learned Arbitrator.

6 of 7

Neutral Citation No:=2024:PHHC:059266

2024:PHHC:059266

19. A request letter alongwith a copy of this order be sent to

Mr. Justice (Retd.) M. Jagannadha Rao.


29.04.2024                                        (SUVIR SEHGAL)
sheetal                                               JUDGE

          Whether Speaking/Reasoned            Yes/No
          Whether Reportable                   Yes/No




                                7 of 7

 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter