Citation : 2021 Latest Caselaw 3207 Patna
Judgement Date : 9 July, 2021
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No. 14700 of 2019
======================================================
BJCL Srinath (JV) having its Office at 103,Lane No.2,Kehar Singh Estate, Saidulajab, New Delhi 110030 through its Authorized Signatory namely Nitish Agarwal @ Nitish Kumar Agarwal, aged about 42 years, (Male),son of Sri Tulsi Prasad Agarwal, resident of F-217,Antriksha Apartment, Sector 14 Extension, Rohini, PS Rohini, Dist. North West Delhi 110085 and local resident at Flat No.304, 3rd Floor, Madhuban Apartment, L B S Shastri Nagar, PS Shashtri Nagar,Dist.Patna-800023.
... ... Petitioner/s Versus
1. The State of Bihar through the Chief Secretary,Govt. of Bihar,Patna
2. The Additional Chief Secretary, Water Resources Department,Govt. of Bihar,Patna
3. The Engineer in Chief Food Control and Water Resources,Department,Patna
4. The Chief Engineer, Floor Control and Drainage,Water Resources Department,Patna
5. The Superintending Engineer, Kosi Barrage Birpur Circle,Birpur,Bihar
6. The Superintending Engineer, Eastern Kosi Embankment,Saharsa,Bihar
7. The Executive Engineer, Western Embankment Division,Birpur,Bihar ... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s : Mr.Prabhat Ranjan, Advocate For the Respondent/s : Mr.Anjani Kumar ( AAG-4 ) Mr. Sanjay Kumar, AC to AAG-4 ====================================================== CORAM: HONOURABLE MR. JUSTICE MOHIT KUMAR SHAH C.A.V. JUDGMENT Date : 09-07-2021 The present petition has been taken up for consideration
through the mode of Video conferencing in view of the
prevailing situation on account of COVID 19 Pandemic,
requiring social distancing.
2. The present writ petition has been filed for quashing the
show cause notice dated 27.06.2019 issued by the Executive
Engineer, Western Embankment Division, Birpur, whereby and Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
whereunder the petitioner has been asked to file his show cause
reply as to why the agreement no. 01/SBD-2018-19 be not
rescinded. The petitioner has further prayed for quashing of the
order dated 04.07.2019 issued by the Executive Engineer,
Western Embankment Division, Birpur, whereby and
whereunder the agreement in question has been rescinded in
terms of clause-3 of the General Conditions of Contract forming
part of standard bidding documents.
3. The brief facts of the case are that a short re-tender notice
no. 6 of 2017-18 was issued vide letter dated 05.02.2018
inviting offers for the work pertaining to "residual work of
raising and strengthening of eastern and western Koshi
embankment, construction of bituminous road over it and
construction/ renovation/ restoration of structures". The
petitioner had participated in the tender process and being the
lowest bidder was awarded the tender and then the letter of
acceptance dated 11.04.2018 was issued with the stipulation that
the work was to be completed by 31.03.2019. An agreement
dated 18.04.2018 bearing agreement no. 01/SBD/2018-19 was
entered into between the respondent no. 7 and the petitioner. It
is the case of the petitioner that there was delay in providing
approved drawings, lay out plans etc. for starting the work in Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
question leading to slow progress of work. Nonetheless, without
issuing any show cause notice and without seeking any
explanation from the petitioner, the petitioner was saddled with
imposition of liquidated damages clause under the signature of
the Superintending Engineer vide letter dated 07.01.2019.
However, subsequently, the matter was sorted out and the
liquidated damages which was imposed against the petitioner
was withdrawn vide letter dated 02.02.2019. Thereafter the
petitioner was served with a letter dated 21.06.2019 intimating
the petitioner about the decision to rescind the agreement and
get the remaining work done at the risk and cost of the petitioner
firm. It appears that various communications were exchanged in
between the petitioner and the respondent with regard to the
submission of revised construction programme and grant of
extension of time, nonetheless the respondents decided to
withdraw the entire mobilization advance given to the petitioner
firm and decided to invoke the bank guarantee, whereafter the
concerned bank was directed to en-cash the same in favour of
the respondents. The petitioner had then challenged the decision
of the respondents to invoke the bank guarantee before this
Court by filing a writ petition bearing CWJC No. 12998 of 2019
but the same was dismissed vide order dated 28.06.2019, Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
however, with liberty to the petitioner to seek remedy, in
accordance with law.
4. It is the further case of the petitioner that as soon as the
aforesaid writ petition was dismissed, the petitioner was served
with a show cause notice dated 27.06.2019, whereby and
whereunder the petitioner was directed to submit itsreply within
a week, as to why the agreement in question by not rescinded, to
which the petitioner had filed a detailed reply dated 01.07.2019.
In the meantime, the respondents had proceeded to re-advertise
the work in question by issuing a notice inviting tender dated
02.07.2019. The respondent no. 7 had then vide letter dated
04.07.2019 rescinded the agreement of the petitioner.
5. The learned counsel for the petitioner has submitted that
firstly the show cause notice dated 27.06.2019 does not mention
the grounds on which the show cause notice has been issued and
steps have been initiated for rescinding the agreement in
question. The learned counsel for the petitioner has further
submitted that though the petitioner by its show cause reply
dated 01.07.2019 had submitted a detailed reply, however, the
same has not been considered while passing the impugned order
dated 04.07.2019, rescinding the agreement of the petitioner.
Thus, it is submitted that the impugned order dated 04.07.2019 Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
is an unreasoned order as well as does not deal with the
submissions made by the petitioner in its show cause reply dated
01.07.2019, hence on this ground alone the impugned order
dated 04.07.2019 is vitiated. In this connection, the learned
counsel for the petitioner has relied on a judgment rendered by
the Hon'ble Apex Court in the case of ORYX Fisheries Private
Limited vs. Union of India & Ors., reported in (2010) 13 SCC
427.
6. The learned counsel for the petitioner has further
submitted that the impugned order dated 04.07.2019 also suffers
from another fallacy inasmuch as the Executive Engineer,
Western Embankment Division, Birpur, who is the competent
authority under the contract to terminate the contract in question
has not applied his independent mind and has not decided for
himself, by exercising his independent mind and unfettered
judgment, as to whether the contract is required to be
terminated or not inasmuch as he has acted in light of the
departmental directions given by the Joint Secretary
(Engineering), Water Resources Department, Bihar, Patna vide
letter No. 2229 dated 04.07.2019, as mentioned in last
paragraph of the impugned letter dated 04.07.2019. It is
submitted that the said letter dated 04.07.2019 written by the Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
Joint Secretary (Engineering) Water Resources Department,
Bihar, Patna clearly contains a direction to cancel the agreement
of the petitioner herein under clause-14 of the General
Conditions of Contract and then issue a tender for execution of
the remaining work at the risk and cost of the petitioner. It is
thus submitted that the Executive Engineer, Western
Embankment Division, Birpur, has passed the impugned order
dated 04.07.2019, rescinding the agreement of the petitioner, in
compliance of the letter of the Joint Secretary (Engineering),
Water Resources Department, Bihar, Patna dated 04.07.2019,
hence on this ground as well the impugned order dated
04.07.2019 is fit to be set aside. In this connection, the learned
counsel for the petitioner has referred to a judgment rendered
by this Court in the case of Kashish Developers Private
Limited vs. The State of Bihar & Ors., reported in (2021) 1
PLJR 642, paragraph nos. 14 and 17 whereof are reproduced
herein below:-
"14. The learned Senior Counsel for the petitioner has also pointed out that the impugned order dated 02.07.2020 suffers from another fallacy inasmuch as the last paragraph thereof would show that the Executive Engineer, Construction Division No. 2, Building Construction Department, Bihar, Patna, who is the competent authority under the contract to terminate the Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
contract in question, has not applied his mind and has not decided for himself by exercising his independent mind and unfettered judgment as to whether the contract is required to be terminated or not inasmuch as he has acted in light of the departmental directions given by the Chief Engineer (Patna), Building Construction Department, Patna vide letter no. 581 dated 02.07.2020 and by the Superintending Engineer, Construction Circle, Building Construction Department, Patna, vide letter no. 300 dated 02.07.2020, hence, on this ground alone, the impugned order dated 02.07.2020 is fit to be set aside. In this connection, the learned Senior Counsel for the petitioner has referred to a judgment reported in AIR 1952 SC 16 (Commissioner of Police v. Gordhandas Bhanji), paragraph no. 44 to 46 whereof are reproduced herein below:-
44. We have held that the Commissioner did not in fact exercise his discretion in this case and did not cancel the license he granted. He merely forwarded to the respondent an order of cancellation which another authority had purported to pass. It is evident from these facts that the Commissioner had before him objections which called for the exercise of the discretion regarding cancellation specifically vested in him by Rule 250. He was therefore bound to exercise it and bring to bear on the matter his own independent and unfettered judgment and decide for himself whether to cancel the license or reject the objections. That duty he can now be ordered to perform under section 45.
Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
45. It was objected as to this that there is no specific law which compels him to exercise the discretion. Rule 250 merely vests a discretion in him but does not require him to exercise it. That is easily met by the observations of Earl Cairns L.C. in the House of Lords in Julius v. Lord Bishop of Oxford [5 App. Cas. 214 at 222, 223.], observations which have our full and respectful concurrence:--
"There may be something in the nature of the thing empowered to be done, something in the object for which it is to be done, something in the conditions under which it is to be done, something in the title of the person or persons for whose benefit the power is to be exercised, which may couple the power with a duty, and make it the duty of the person in whom the power is reposed, to exercise that power when called upon to do so."
46.The discretion vested in the Commissioner of Police under Rule 250 has been conferred upon him for public reasons involving the convenience, safety, morality & welfare of the public at large. An enabling power of this kind conferred for public reasons and for the public benefit is, in our opinion, coupled with a duty to exercise it when the circumstances so demand. It is a duty which cannot be shirked or shelved nor can it be evaded; performance of it can be compelled under section 45.
Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
17. The impugned order dated 02.07.2020 is also bad in law, for the reason that the Executive Engineer, Construction Division No. 2, Building Construction Department, Bihar, Patna, who is the competent authority under the contract to terminate the contract in question, has not applied his mind and has not decided for himself by exercising his independent mind and unfettered judgment as to whether the contract is required to be terminated or not inasmuch as he has acted in light of the departmental directions given by the Chief Engineer and the Superintending Engineer, as aforesaid, hence, on this ground as well, the impugned order dated 02.07.2020 is fit to be set aside, more so being squarely covered by the law laid down by the Hon'ble Apex Court in the aforesaid decision rendered in the case of Gordhandas Bhanji (Supra)."
7. Per contra, the learned counsel for the respondent State
Shri Sanjay Kumar, AC to AAG-4 has submitted that the
Executive Engineer, Western Embankment Division, Birpur, had
on several occasions requested the petitioner to start the work
immediately, however, the petitioner had delayed in starting the
work with oblique motives. It is also stated that the approved
design of structure and FRL of the western embankment was
made available to the representatives of the petitioner including
the scope of work TBM etc. pertaining to the eastern
embankment on 01.06.2018 itself and as far as the western Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
embankment is concerned, the requisites were made available to
the petitioner on 29.10.2018. In fact a review meeting was held
on 23.07.2018, wherein the Chief Engineer had warned the
representatives of the petitioner that action would be taken in
terms of the agreement if the work is not started immediately.
Thereafter, several warnings were given to the petitioner to
execute the work as per the work programme, failing which
appropriate action would be taken. In fact the progress of the
work was reviewed by the Chief Engineer in the meetings held
on 17.11.2018 and 17.12.2018 and the progress of the work qua
the petitioner was found to be very slow. In nutshell, it is the
case of the respondent State that after the issuance of the work
order, firstly the petitioner started the work after a great delay
and then also its progress regarding completion of the work was
found to be very slow on account of inadequate plant and
machinery, personnel, construction materials at the work site,
etc.. The learned counsel for the respondent-State has further
submitted that till the agreement of the petitioner was rescinded
the petitioner had completed only 11% work, hence the Minister
of the Department and the Additional Chief Secretary, upon
having inspected the site on 12.06.2019/13.06.2019 had also
found that not only 11 percent of the work had only been Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
completed but the petitioner had also not executed any work
since January, 2019, thus the Chief Engineer was directed to
issue separate notice inviting tender for execution of the
remaining works at the eastern and western Koshi embankment,
at the risk and cost of the petitioner, whereafter the Executive
Engineer had communicated the said direction to the petitioner
vide letter dated 21.06.2019. It is under such compelling
circumstances that a show cause notice dated 27.06.2019 was
issued to the petitioner calling upon him to submit his show
cause reply as to why the agreement be not rescinded. The
petitioner had then filed his reply and upon consideration of the
same, the agreement in question has been cancelled vide order
dated 04.07.2019 issued by the Executive Engineer. The learned
counsel for the State has further submitted that the impugned
order dated 04.07.2019 is a self speaking and a reasoned order
and it clearly spells out the reasons for cancellation of the
agreement in question i.e. huge delay on the part of the
petitioner in starting the work, the petitioner engaging in very
slow execution of work and having completed only 11 per cent
of the total work during the contract period despite having been
requested several times to increase the pace of work. It is also
submitted that clause-6 of the SBD (General Conditions of Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
Contract) provides for dispute redressal system and according to
clause-6.1 such disputes are to be referred to the empowered
standing committee for settlement, whose decision shall be final
and binding upon the contractor. It is pointed out that clause-
6.2.1 debars arbitration in view of the said provision of disputes
redressal mechanism. Thus, it is submitted that there is no merit
in the present writ petition and the same is fit to be dismissed.
8. I have heard the learned counsel for the parties and gone
through the materials on record. This Court finds that though the
impugned order dated 04.07.2019 is not entirely unreasoned but
then this Court finds that the decision of the Executive
Engineer-cum-Nodal Officer, Western Embankment Division,
Birpur, to rescind the agreement of the petitioner vide the
impugned order dated 04.07.2019 has been taken in compliance
of the letter no. 2229 dated 04.07.2019 issued by the Joint
Secretary (Engineering), Water Resources Department, Bihar,
Patna, whereby and whereunder he had directed to cancel the
agreement in question and get the balance work executed by re-
tendering the same at the risk and cost of the petitioner, hence it
is clear that the Executive Officer, Western Embankment
Division, Birpur, who is the competent authority under the
contract to terminate the contract in question, has not applied his Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
mind and has not decided for himself by exercising his
independent mind and unfettered judgment as to whether the
contract is required to be terminated or not inasmuch as he has
acted in light of the departmental directions given by the Joint
Secretary (Engineering), Water Resources Department, Bihar,
Patna dated 04.07.2019, hence on this ground alone the
impugned order dated 04.07.2019 is fit to be set aside more so
the said issue being squarely covered by the law laid down by
the Hon'ble Apex Court in a decision rendered in the case of
Gordhandas Bhanji (supra). Accordingly, the impugned order
dated 04.07.2019, as contained in letter dated 442, issued by the
Executive Engineer, Western Embankment Division, Birpur,
rescinding the agreement of the petitioner is set aside, however,
liberty is reserved to the Executive Engineer, Western
Embankment Division, Birpur, to issue a fresh show cause
notice to the petitioner, detailing therein the grounds on which
the respondent Department seeks to rescind the agreement so
that appropriate opportunity is granted to the petitioner to rebut
the same and put forth his defence, whereafter the Executive
Engineer, Western Embankment Division, Birpur, upon receipt
of the reply of the petitioner, shall apply his mind and pass a
reasoned and a self-speaking order. It is expected that the entire Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
exercise, as aforesaid, shall be completed within a period of six
months from today.
9. Another issue which arises for consideration is that though
the petitioner was served with a show cause notice dated
27.06.2019 wherein one week time was granted to the petitioner
to furnish explanation as to why the agreement in question be
not rescinded, however, without even waiting for the said period
to lapse, the respondents proceeded to re-advertise the balance
work in question and a notice inviting tender dated 02.07.2019
was issued thus making it apparent that before issuance of the
impugned order dated 04.07.2019, rescinding the agreement of
the petitioner, the respondent authorities had already taken a
decision to rescind the agreement of the petitioner, hence the
show cause notice was issued to the petitioner with a
premeditated mind, hence on this score as well the impugned
order dated 04.07.2019 is vitiated and is fit to be set aside.
10. As far as the objection taken by the respondent State to
the effect that the present writ petition is not maintainable in
view of clause-6 of the standard bidding document (General
Conditions of Contract), it is clear from the said clause-6.1 of
the SBD (General Conditions of Contract), that majority of the
members of the Standard Empowered Committee to which any Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
dispute, which has arisen out of the contract, is required to be
referred to, are officials of the respondent State. This Court is of
the view that in light of the amendment made in Section 12 of
the Arbitration and Conciliation Act, 1996 and in view of the
judgment rendered by the Hon'ble Apex Court in the case of
Voestalpine Schienen GMBH v. Delhi Metro Rail Corpn. Ltd.,
reported in (2017) 4 SCC 665, the Arbitrator cannot be an
official of the State Government, hence the contention of the
respondents that the dispute ought to be referred to the Standard
Empowered Committee, has got no force in the eyes of Law.
11. Nonetheless, this Court further finds that in case the
action of the respondent is illegal and without jurisdiction, if the
principles of natural justice have been violated and if the
fundamental rights of the petitioner has been violated, a writ
petition would definitely be maintainable, even in a contractual
matter. Reference in this regard be had to judgments rendered
by the Hon'ble Apex Court in the case of Whirlpool
Corporation vs The Registrar of Trade Marks Mumbai & Ors.,
reported in (1998) 8 SCC 1, the one rendered in the case of
Harbanslal Sahnia v. Indian Oil Corpn. Ltd., reported in
(2003) 2 SCC 107, the one rendered in the case of Sanjana M.
Wig vs. Hindustan Petro Corporation Limited, reported in Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
(2005) 8 SCC 242 and the one rendered in the case of Joshi
Technologies International Inc. vs. Union of India & Ors.,
reported in (2015) 7 SCC 728. Admittedly in the present case
the impugned order has been passed in violation of the
principles of natural justice inasmuch as firstly proper show
cause notice, setting out the reasons/grounds on which the
respondents propose to rescind the agreement of the petitioner
have not been furnished and the show cause notice dated
27.06.2019 is absolutely silent on this aspect and secondly the
Executive Engineer, Western Embankment Division, Birpur,
who is the competent authority under the agreement to rescind
the agreement has not applied his mind and has instead
rescinded the agreement in question by the impugned order
dated 04.07.2019 on the dictate of the Joint Secretary,
(Engineering), Water Resources Department, Bihar, Patna. Thus,
in such a case as the present one, the alternative remedy being
harped upon by the learned counsel for the respondents for the
purposes of settlement of disputes shall not be a bar to the
maintainability of the present writ petition, hence the said
contention of the respondents that the present writ petition is not
maintainable, is not tenable in the eyes of law, hence is rejected.
In fact, even an arbitration clause in an agreement is not a bar to Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
invocation of writ jurisdiction in case injustice has been caused
inasmuch as the same has to be struck down as an anathema to
the rule of law and the provisions of the Constitution. Moreover,
the constitutional powers vested in the High Court under Article
226 of the Constitution of India, cannot be fettered by any
alternative remedy available to the parties. Reference in this
connection be had to a judgment rendered by the Hon'ble Apex
Court in the case of Union of India & Ors. vs. Tantia
Construction Private Limited, reported in (2011) 5 SCC 697. In
this regard, it would also be apposite to refer to a Judgment
rendered by the Hon'ble Apex Court in the case of Uttar Pradesh
Power Transmission Corporation Ltd. and Another Versus CG
Power and Industrial Solutions Limited and Another, reported in
2021 SCC OnLine SC 383, paragraphs No. 67 and 68 whereof
are reproduced herein below:-
"67. Even though there is an arbitration clause, the Petitioner herein has not opposed the writ petition on the ground of existence of an arbitration clause. There is no whisper of any arbitration agreement in the Counter Affidavit filed by UPPTCL to the writ petition in the High Court. In any case, the existence of an arbitration clause does not debar the court from entertaining a writ petition.
68. It is well settled that availability of an alternative remedy does not prohibit the High Court from entertaining a writ petition in an appropriate case. The Patna High Court CWJC No.14700 of 2019 dt.09-07-2021
High Court may entertain a writ petition, notwithstanding the availability of an alternative remedy, particularly (1) where the writ petition seeks enforcement of a fundamental right; (ii) where there is failure of principles of natural justice or (iii) where the impugned orders or proceedings are wholly without jurisdiction or (iv) the vires of an Act is under challenge. Reference may be made to Whirlpool Corporation v. Registrar of Trade Marks, Mumbai reported in (1998) 8 SCC 1 : AIR 1999 SC 22 and Pimpri Chinchwad Municipal Corporation v. Gayatri Construction Company, reported in (2008) 8 SCC 172, cited on behalf of Respondent No. 1."
12. Having regard to the facts and circumstances of the case
and for the reasons mentioned hereinabove, the impugned order
dated 04.07.2019, as contained in letter dated 442, issued by the
Executive Engineer, Western Embankment Division, Birpur,
rescinding the agreement of the petitioner is set aside, however,
liberty is reserved to the Executive Engineer, Western
Embankment Division, Birpur, to proceed afresh in the matter,
as aforesaid.
13. The writ petition stands allowed.
(Mohit Kumar Shah, J) S.Sb/-
AFR/NAFR AFR CAV DATE 05.07.2021 Uploading Date 14.07.2021 Transmission Date
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!