Citation : 2021 Latest Caselaw 4068 Patna
Judgement Date : 11 August, 2021
IN THE HIGH COURT OF JUDICATURE AT PATNA
REQUEST CASE No.59 of 2020
======================================================
M/s Star Construction Through its Proprietor Parwez Ahmad Khan, aged about 48 years Gender Male, Son of Haseen Ahmad Khan, Resident of Mohalla- Balua Tal, P.S.- Motihari Town, District- Motihari.
... ... Petitioner/s Versus
1. The State of Bihar Through the Principal Secretary, Department of Road Construction, Government of Bihar, Patna.
2. The Engineer-in- Chief Department of Road Construction, Government of Bihar, Patna.
3. The Chief Engineer N.H. Circle, Muzaffarpur.
4. The Superintending Engineer N.H. Circle, Muzaffarpur.
5. The Executive Engineer N.H. Division, Sitamarhi.
... ... Respondent/s ====================================================== Appearance :
For the Petitioner/s : Mr. Ranjeet Kumar, Advocate Mr. Kundan Kumar, Advocate Mr. Yogesh Kumar, Advocate For the Respondent/s : Mr.Manoj Kumar Ambastha, SC-26 ======================================================
(The proceedings of the Court are being conducted by Hon'ble the Chief Justice/Hon'ble Judges through Video Conferencing from their residential offices/residences. Also the Advocates and the Staffs joined the proceedings through Video Conferencing from their residences/offices.) ===================================================
CORAM: HONOURABLE THE CHIEF JUSTICE ORAL JUDGMENT Date : 11-08-2021
The petitioner has prayed for the following relief/s :-
"That by means of captioned application, the petitioner herein invokes the jurisdiction of this Hon'ble Court under section 11(6) of the Arbitration and Conciliation Act, 1996 praying inter alia, for directions and orders for the appointment of sole arbitrator on behalf of the petitioner for Patna High Court REQ. CASE No.59 of 2020 dt.11-08-2021
adjudication of certain disputes, differences and claim that have arisen between the parties hereto out of or in relation to their legal relationship on the ground that the respondent has failed to act in accordance with the contractual stipulation in that regard."
The parties to the lis entered into an agreement for
construction of certain public works. To such effect, an
agreement no. 06-SBD 2009/10 dated 20.07.2009 was entered
into between the parties. The said agreement contains an
Arbitration Clause ( Clause 25). Certain disputes having arisen
inter se the parties, the petitioner approached this Court for
payment of dues under the agreement. Vide order dated 22 nd of
September, 2015 passed in CWJC No. 24507 of 2013, titled as
M/s Star Construction Through its Proprietor Parwez Ahmad
Khan Vs. The State of Bihar and Ors., the petition was disposed
of granting liberty to the petitioner to approach the Chief
Engineer, NH, Circle. The petitioner invoked the arbitration
clause and approached the special adjudicatory authority
constituted to adjudicate dispute in relation to public works
contracts. The said authority, namely, Bihar Public Works
Contract Disputes Arbitration Tribunal (hereinafter referred to
as the 'Tribunal') dismissed the petitioner's application vide Patna High Court REQ. CASE No.59 of 2020 dt.11-08-2021
order dated 29th of January, 2020 on the ground that the same
was not maintainable in view of the law laid down by the
Hon'ble Supreme Court in State of Bihar v. Brahmaputra
Infrastructure Limited, (2018) 17 SCC 444 :AIR 2018 (SC)
2640.
Left with no option, the petitioner filed the instant
petition under section 11(6) of the Arbitration and Conciliation
Act, 1996 seeking appointment of the Arbitrator.
The respondents-State is now opposing the application
on the ground that the provisions of the Bihar Public Works
Contracts Disputes Arbitration Tribunal Act, 2008 (hereinafter
referred to as the 'Act') stands amended and that all disputes
arising out of the public works contracts, including the subject
matter of the instant lis, is now to be adjudicated by the
Tribunal.
The petitioner has no objection subjecting to the
jurisdiction of the Tribunal constituted under the said Act. As
such, the petitioner is permitted to file a fresh application/ file
an application seeking revival of the earlier application for
adjudication by the Tribunal, for now, in view of the
amendment, there is no legal impediment as is so claimed by the
State, in the Tribunal adjudicating the disputes.
Patna High Court REQ. CASE No.59 of 2020 dt.11-08-2021
This Court finds the parties to be subjecting
themselves to the jurisdiction of the Tribunal and as such allow
the petitioner's prayer granting liberty to either file a fresh
petition (reference case) seeking adjudication of the disputes
arising out of agreement referred to (supra) or seek revival of
old case being Reference Case No.168 of 2017.
Considering the fact that the dispute pertains to the
agreement executed in the year 2009 and the petitioner has been
pursuing the remedy before this Court, it is expected from the
Tribunal to decide the matter as and when filed, expeditiously
and preferably within a period of nine months thereafter.
Petition disposed of in the aforesaid terms.
Interlocutory application, if any, shall stand disposed
of.
(Sanjay Karol, CJ)
Ashwini/Sujit/-
AFR/NAFR CAV DATE Uploading Date Transmission Date
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!