Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Chakadola Construction Pvt. Ltd vs State Of Odisha And Others .... Opposite ...
2025 Latest Caselaw 8520 Ori

Citation : 2025 Latest Caselaw 8520 Ori
Judgement Date : 20 September, 2025

Orissa High Court

Chakadola Construction Pvt. Ltd vs State Of Odisha And Others .... Opposite ... on 20 September, 2025

Author: Murahari Sri Raman
Bench: Murahari Sri Raman
       IN THE HIGH COURT OF ORISSA AT CUTTACK
                        W.P.(C) No. 4192 of 2025

Chakadola Construction Pvt. Ltd.                   ....               Petitioners
and another

                                    -Versus-
State of Odisha and others                         ....       Opposite Parties


Advocates appeared in this case:
     For Petitioner             : Mr. Sidhant Dwibedi,
                                  Advocate

     For Opposite Parties       : Ms. Suman Pattanayak,
                                  Addl. Government Advocate



                     CORAM:
           HON' BLE THE CHIEF JUSTICE
                       AND
     HON'BLE MR. JUSTICE MURAHARI SRI RAMAN

                            JUDGMENT

-------------------------------------------------------------------------------- Date of Hearing and Judgment : 20th September, 2025

---------------------------------------------------------------------------------- HARISH TANDON, CJ.

1. The work awarded to the petitioner-company was

undertaken by it not only in terms of the tender, but to the

satisfaction of the authorities yet. The RA bill submitted was not

paid which constrained the petitioners to move the writ petition

before this Court.

2. At the time of admission of the instant writ petition, the

attention of the learned Additional Government Advocate

representing the State-opposite parties was drawn and an

opportunity to file an affidavit was afforded to them. The counter

affidavit filed by the State reveals inconsistent statements and a

submission is advanced that whatever bill is submitted by the

petitioners has been paid off.

3. The petitioners raise a point that though the RA bill has now

been paid, the authorities have not prepared the final bill after taking

the measurement upon completion of the work and, therefore, they

are still in default.

4. Interestingly, a stand is taken by the State-opposite parties

before us that since the petitioners did not submit the final bill, there

was no occasion to make any payments. After the attention is drawn

to Clause-7 of the conditions of contract, it is sought to be contended

taking shelter under the averments made in paragraphs-15, 16 and

17 of the counter affidavit that the entire measurement was

undertaken by the authorities and the payment has been released on

the basis thereof, and, therefore, there is no subsisting claim which

is required to be paid. It is sought to be contended that Clause-6 of

the conditions of contract provides for measurement and after taking

the measurement, the amount has been determined which would be

regarded as a full and final settlement of the claim of the petitioners.

5. We are unable to accept such stand taken by the State-

opposite parties. Clause-6 provides that a bill shall be submitted by

the contractor every month on or before the date fixed by the

Engineer-in-Charge or his sub-ordinate and a requisite measurement

for such purpose of verification of the claim shall be taken and in the

event, such bill is not submitted on a monthly basis, the said

authority shall take a measurement of the said work in presence of

the contractor, who is required to countersign on the measurement

sheet which shall be binding on him. The said Clause is quoted as

under:

"Payment of Clause -6 : A bill shall be submitted intermediate by the contractor each month on or certificate to be regarded as before the date fixed by the Engineer- advances and in-Charge or his sub-ordinate shall bill to be submitted. take the requisite measurement for the purpose of having the same verified and the claim, as far as admissible, adjusted, if possible, before the expiry of ten days from the representation of

the bill. If the contractor does not submit the bill within the time fixed as aforesaid, the Engineer-in-Charge or his subordinate shall measure up the said work in the presence of the contractor whose countersignature of the measurement list will be sufficient warrant, and the Engineer-in-charge or his sub-ordinate shall prepare a bill from such list which shall be binding on the contractor in all respects.

Provided that, if any balance of 10% security is outstanding from each such payment shall be deducted so much, not exceeding 5% as may be necessary to make up the balance of the security. All such intermediate payments to the contractor shall be regarded as payments by way of advance against the final payment only and not as payments for work actually done and completed, and shall not preclude the requiring of bad, unsound and imperfect or unskillful work to be removed and taken away and reconstructed or re-

erected, or be considered as an

admission of the due performance of the contract, or any part thereof in any respect, or the actual of any claim nor shall it conclude, determine, of effect in any way the powers of the Engineer in-charge under these conditions or any of them as to the final settlement or adjustment of the accounts or otherwise, or in any other way vary or affect the contract."

6. On the meaningful reading of the said Clause, it appears that

since construction is done uninterruptedly and/or continuously, the

running bill is required to be submitted on a monthly basis for the

works done during the said month and the payments are to be

released after the measurement is taken by the concerned officer

mentioned in Clause-6 of the said condition of contract. It further

postulates that in the event such bill is not submitted, yet a duty is

cast upon the said officer to take a measurement and invite the

attention of the contractor to put the countersignature thereupon with

the restrictions that later on the contractor will not raise any

objection thereto. The said Clause is applicable in relation to an

ongoing construction work and cannot be regarded as a final bill. By

no stretch of imagination, any interpretation can be assigned to such

Clause in relation to the final bill which comes under Clause-7 of

the said conditions of contract. Clause-7 provides the final bill to be

prepared by the offices of the Rural Works Department in

accordance with the rules of the Department in presence of the

contractor within one month of the date fixed for completion of the

work. It conveys a clear intention of the contracting parties that

Clause-6 is applicable with regard to the ongoing construction and

Clause-7 is relatable to a final bill to be prepared by the office after

the said work is completed. The authority was conscious of such

aspect and clearly averred in paragraph-17 of the counter affidavit

that since the final bill was not submitted by the contractor, the

payment could not be made. There lies a fallacy in the stand of the

State-opposite parties. Clause-7 does not mandate the submission of

final bill by the contractor, but it is a duty cast upon the Office of the

Rural Works Department to prepare the final bill and to make the

payments thereupon.

7. Though the learned counsel for the State tried to interpret the

averments made in the counter affidavit taking a circuitous route,

but we do not find any ambiguity in the aforesaid Clause for the

reason that it operates in a different contingency and/or eventuality.

The payment of the last RA bill cannot be construed as the payment

of final bill. Preparation of final bill is a paramount duty of the

office and, therefore, the stand of the State-opposite parties before

us is unsustainable and unacceptable.

8. We direct the Office of the Rural Works Department to

undertake an exercise as contemplated in the said Clause-7 within a

month from the date of communication of this order and shall raise

the final bill and in the event, any amount is owed to the

Department, the same shall be paid within a month therefrom.

9. With these observations, the writ petition is disposed of. No

order as to costs.

                                             (M.S. Raman)                          (Harish Tandon)
                                               Judge                                 Chief Justice



                   S.K. Guin/ PA








Location: High Court of Orissa, Cuttack
Date: 24-Sep-2025 11:50:09
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter