Citation : 2025 Latest Caselaw 6476 Ori
Judgement Date : 26 August, 2025
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBP No.01 of 2025
M/s. Anand Granites Exports Private .... Petitioner
Limited.
-Versus-
Mr. Prabhudayal Agrawal .... Opposite Party
Advocates appeared in this case:
For Petitioner: Mr. Gautam Misra, Senior Advocate
Mr. J.R. Deo, Advocate
For Opposite Party : Mr. Vaibhav Shukla, Advocate
CORAM:
THE HON'BLE THE CHIEF JUSTICE
JUDGMENT
26th August, 2025
HARISH TANDON, CJ.
1. An application under Section 11 of the Arbitration and
Conciliation Act, 1996 (in short, „the Act‟) filed by the petitioner is
resisted by the opposite party primarily on the premise that the dispute
raised in the notice invoking arbitration clause contained in the raising
contact dated 18th March, 2010 is beyond the purview of the arbitration
agreement/arbitration clause contained therein.
2. Undeniably, the opposite party was granted mining lease for an
area covering 262.27 acres of land situated in Tantra (Khata No.35),
Rangua (Khata No.31) and Bandhal (Khata Nos.30 and 39) under Bonai
Sub-Division of Sundargarh district in the State of Odisha on the basis
of a mining lease deed dated 25th January, 2002. Previous to entering
into the said raising contract dated 18th March, 2010, a similar contract
was entered into between the opposite party and one M/s. Gayatri
Mining Pvt. Limited on 14th August, 2009 but that could not materialize
and subsequently, the opposite party cancelled the said previous
contract and approached the petitioner to operate and run the said mine
on the terms and conditions embodied in the raising contract dated 18 th
March, 2010. Indubitably, the said raising contract dated 18th March,
2010 contains an arbitration agreement/clause in the event any disputes
arise between the parties thereto in relation to or touching upon any of
the terms and conditions embodied therein. Simultaneously, a tripartite
agreement of the even date was also executed between the parties
hereto and the said M/s. Gayatri Mining Private Limited for discharge
of several statutory dues including the dues of the said M/s. Gayatri
Mining Private Limited to the tune of Rs.14.00 crores. The validity of
the said raising contract dated 18th March, 2010 was agreed till the
ultimate end of the mining lease which includes renewal and/or revival
period or till the complete exhaustion of the detected mineral deposited
in the schedule land, whichever is earlier.
3. In order to facilitate the smooth and continuous extraction of the
minerals from the said mining lease which is commonly known as
Tantra Bauxite Mines, a power of attorney was also executed in favour
of an employee of the petitioner on 10th May, 2010 wherein clause 36
thereof provides that the same is irrevocable and cannot be revoked at
the sweet will of the opposite party. Apropos the same, several
affidavits were also executed and affirmed by the opposite party so that
the period of mining lease can be renewed and/or extended to be
transferred in favour of the petitioner and it appears from the documents
annexed and from the stand of the parties that considerable amount of
money was also paid both to the statutory authorities and also to a 3 rd
party in discharge of the obligation imposed upon the opposite party.
4. Amidst the aforesaid action and/or steps being taken, the
Government of Odisha adopted a policy to enhance the tenure of lease
to 50 years subject to fulfillment of the terms and conditions
incorporated therein and to avail such opportunity, the petitioner
engaged M/s. Earth and Environment Consultancy Services, a service
provider to process the application for renewal and/or extension of lease
and also to have clearances from various departments upon payment of
the statutory dues.
5. It is a specific stand of the petitioner that despite having complied
with all the statutory impositions including deposit of the statutory
amount, the opposite party was putting an obstacle and in fact, resiled
from the said raising contract and thus, the dispute arose between the
parties in relation thereto. The litigations were also ensued by the
opposite party by approaching the civil Court touching upon the
cancellation of the irrevocable power of attorney, which is pending.
6. Perceiving the dispute having arisen touching upon the respective
obligations of the parties to the proceeding, the arbitration
agreement/arbitration clause contained in the said agreement provides
for an amicable resolution which was, in fact, resorted to. The said
arbitration agreement/arbitration clause postulates that in the event the
amicable resolution to a dispute fails, the parties may invoke the
arbitration clause for determination of the said dispute by an arbitrator.
Interestingly, the notice invoking arbitration was issued on 04.02.2023
seeking concurrence on the appointment of the arbitrator; the same was
replied by the opposite party through an e-mail contending that he is
unable to recollect of having signed any such raising agreement and
called upon the petitioner to send the fully scanned copy of the said
raising agreement dated 18th March, 2010 for his knowledge. The said
e-mail reply was duly responded to by the petitioner on 10 th February,
2023 showing their concern on the content of the said e-mail and to
refresh the memory of the opposite party also forwarded the copy of the
agreement. The opposite party replied to such letter on 2nd March, 2023
taking a specific stand that the approach has already been made to
Court and the matter being subjudice, it is not possible for the opposite
party to concur on the arbitration. It was further indicated in the said
letter that the dispute does not come within the periphery of the
arbitration agreement.
7. Since the opposite party denied to agree on the arbitrators named
in the letter invoking the arbitration agreement/clause, the petitioner
was advised to move the High Court of Judicature at Madras as the part
of the cause of action has arisen within the territorial jurisdiction of the
said High Court, which was registered as ARB. O.P. (Com. Div.)
No.215/23 and O.A. No.364 of 2023. The opposite party took a stand
that the High Court at Madras had no territorial jurisdiction as the cause
of action pleaded in the said application had not arisen within the
territorial limits of the said High Court. The said High Court ultimately
held that entire cause of action has arisen either within the jurisdiction
of this High Court or the High Court at Andhra Pradesh and rejected the
said application filed by the petitioner on the ground of the jurisdiction
on 16th August, 2023. The said order is annexed to the application
wherefrom it revealed that an application under Section 9 of the said
Act was also taken out by the petitioner and both the applications were
decided by the said common order dated 16th August, 2023.
8. The present application is taken out by the petitioner as this
Court has the territorial jurisdiction in relation to a cause of action
arisen between the parties and the opposite party is resisting the said
application on the ground indicated in the opening paragraph of the
instant judgment.
9. Both the counsels appearing for the respective parties made their
oral submissions and also filed the written note of submission in
support of their respective stands and relied upon the several judgments
of the apex Court in support thereof.
10. Mr. Gautam Misra, learned Senior Advocate appearing for the
petitioner has strenuously argued that the disputes so raised is in
relation to a raising contract dated 18th March, 2010 and in view of
clause 12 of the said agreement, the same is required to be decided by
an arbitrator and, therefore, the Court may refer the parties to arbitration
for determination thereof. Mr. Misra would submit that Section 11(6-A)
of the Act restricts the scrutiny and/or determination to the existence of
an arbitration agreement and, therefore, whether the dispute is
sustainable or not cannot be decided at the stage of appointment of the
arbitrator. He fervently submits that the moment the Court finds the
prima facie existence of an arbitration agreement, application for
appointment of the receiver is required to be allowed. Placing reliance
upon the judgment of the apex Court in the case of Goqii Technologies
(P) Ltd. vs. Sokrati Technologies Pvt. Ltd. reported in (2025) 2 SCC
192, Mr. Misra further submits that the ancillary agreement or
connected agreements executed by the parties in furtherance of the
main agreement which contains an arbitration clause and if the dispute
has cropped up, it would be decided by invoking the arbitration clause
and placed reliance upon a judgment of the apex Court in the case of
Ameet Lalchand Shah and others Vs. Rishabh Enterprises reported in
(2018) 15 SCC 678. Mr. Misra, further submits that the arbitration
agreement/clause shall be regarded to have incorporated in the
subsequent agreement if the reference of the contract/agreement
containing the arbitration clause can be seen and placed reliance upon a
judgment of the apex Court in case of Inox Wind Limited vs.
Thermocables Limited reported in (2018) 2 SCC 519. Lastly, it is
submitted that the High Court in exercise of power under Section 11 of
the Act, restricts the determination and/or scrutiny only to the
arbitration agreement and not into the validity and/or frivolity of the
dispute as held in SBI General Insurance Company Limited vs. Krish
Spinning reported in 2024 SCC OnLine SC 1754.
11. On the other hand, the counsel for the opposite party submits that
the Court exercising powers under Section 11 of the Act should confine
its scrutiny within the four corners of an agreement containing an
arbitration clause and disputes arising therefrom and placed reliance
upon the judgment of the apex Court in the case of M/s. KSS KSSIIPL
Consortium vs. M/s. Gail (India) Limited reported in (2015) 4 SCC
210, it is vociferously submitted that the dispute raised in an application
invoking the arbitration clause is basically founded upon the
cancellation of the power of attorney executed in favour of the agent by
the opposite party, which is beyond the scope and purview of the
raising contract dated 18th March, 2010. The counsel for the opposite
party strenuously argues that the disputes raised by the petitioner is
untenable in view of the raising agreement dated 18th March, 2010 and
there is no fetter on the part of the Court to enter into the nature of the
dispute with the limited scrutiny whether it comes within the purview of
the arbitration agreement/clause and placed reliance upon a judgment of
the apex Court in the case of Duro Felguera S.A. vs. Gangavaram Port
Ltd. reported in (2017) 9 SCC 729. To sum up, it is contended that the
disputes raised by the petitioner is beyond the scope and purview of the
raising agreement dated 18th March, 2010 and, therefore, it is not
obligatory on the part of the High Court to appoint the arbitrator by
invoking the arbitration agreement/clause contained in the raising
contract dated 18th March, 2010.
12. On the conspectus of the facts and the submissions advanced by
the respective counsels, the first and foremost point emerged therefrom
relates to the scope and jurisdiction exercised by the High Court for
appointment of the arbitrator under Section 11(6) of the Act.
13. The arbitration agreement is defined under Section 7 of the Act to
mean an agreement by the parties to submit to arbitration all or certain
disputes which have arisen or which may arise between them in respect
of a legal relationship, whether contractual or not. It would be apposite
to quote the said provision, which reads thus:
"7. Arbitration agreement.-- (1) In this Part, "arbitration agreement" means an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not.
(2) An arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement.
(3) An arbitration agreement shall be in writing. (4) An arbitration agreement is in writing if it is contained in
(a) a document signed by the parties;
(b) an exchange of letters, telex, telegrams or other means of telecommunication 1[including communication through electronic means] which provide a record of the agreement; or
(c) an exchange of statements of claim and defence in which the existence of the agreement is alleged by one party and not denied by the other.
(5) The reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the contract is in writing and the reference is such as to make that arbitration clause part of the contract."
14. On the meaningful reading of the provision as mentioned
hereinabove, the definition ascribed to arbitration agreement is of wide
import. Apart from a conventional way of execution of an agreement as
known in common parlance, such agreement can also be perceived in
the form of an arbitration clause in the contract. It further engulfed the
exchange of letters, telex, telegrams and other means of
telecommunication, recording the agreement and can also be construed
from the pleadings, if the existence of the arbitration agreement is not
denied by the other. The arbitration agreement can also be presumed or
be treated in existence by way of a reference in a contract to a
document containing an arbitration clause in specified eventualities.
15. Section 11 of the Act contains an exhaustive provision relating to
appointment of an arbitrator by the authority/Court mentioned therein.
Sub-section (6) of Section 11 postulates that in the event the procedure
for appointing an arbitrator is agreed upon by the parties and in the
event a party fails to act thereupon or to reach an agreement expected
from them or to perform any functions entrusted upon them, the
appointment, if any, can be made on an application by any party. The
cumulative effect of the provisions contained in Sections 7 and 11 of
the Act is that once the parties have entered into a contract which is
legally enforceable, agreeing upon the determination of the dispute that
has arisen or to be arisen to be decided by the private fora; in the event
such dispute crops up, if the party fails to appoint the arbitrator
mutually, no fetter can be seen on the part of the High Court to appoint
the arbitrator.
16. Of late, the question invariably comes before the Court for
determination is whether the High Court exercising jurisdiction under
Section 11 of the Act can enter into the existence of a dispute or a
dispute covered under the arbitration agreement even for recording the
prima facie finding which in this case appears to have been projected
by the opposite party. The reliance is placed upon the decision of the
apex Court in the case of KSS KSSIIPL Consortium (supra) wherein it
is held that the Court before appointing an arbitrator will have to decide
on the existence of an arbitrable dispute/enforceable claim of the parties
to the contract in the following:
"9. There can be no manner of doubt that before exercising the power under Section 11(6) of the Arbitration Act to make appointment of an arbitrator the Court will have to decide on the existence of an arbitrable dispute/enforceable claim by and between the parties to the contract. The existence of a claim and denial thereof giving rise to a dispute is required to be determined on the basis of what the parties had agreed upon as embodied in the terms of the contract and only for the purpose of a decision on the question of arbitrability and nothing beyond. It is from the aforesaid standpoint that the issues raised in the present proceedings will have to be considered."
17. In M/s. Gail (India) Limited (supra) a tender was floated for
pipeline laying and terminal works for Dabhol-Bangalore Pipeline
project and two companies, one of foreign origin and one of India
constituted a consortium to participate in the said tender and in the
event the work is awarded those have to be undertaken on the basis of
the terms and conditions mentioned therein. Since one of the
constituents of consortium failed to provide engineering inputs and
were indulged in frequent modifications with respect to drawing, extra
work and delays in providing free issue materials, the compensatory
claim in the form of extended stay compensation was made, which gave
rise to a dispute within one of the several agreements entered into by
and between the parties. In the backdrop of the above, the Court found
that if the dispute has arisen from a contract and claim of compensation
is made, it gives rise to arbitral dispute and proceeded to appoint the
arbitrator for resolution. While considering the nature of the claim, the
Court held that there is no fetter on the part of the Court exercising
power under Section 11(6) of the Act to decide the existence of an
arbitral dispute and/or enforceable claim, which would always be
tentative.
18. The larger Bench Coram of the Supreme Court in Cox and Kings
Limited vs. SAP India (P) Limited and another, reported in (2024) 4
SCC 1 was basically deciding a reference whether the doctrine of group
of companies, a modern theory which conventionally runs counter to
the notion of an arbitration law, has any manner of applicability in the
jurisprudence of the Indian arbitration though sees its origin a century
ago, but was embraced by some and dissented by others. The larger
Bench was posed with a challenge to figure out whether there can be
any reconciliation between the group of companies doctrine vis-a-vis,
the well settled legal principles of corporate law and the contract law.
Though the reference was limited as it appeared from the narration of
the facts discerned therefrom, yet the Court in pursuit of answering the
said reference also took into consideration, which in my opinion, was
inevitable and would set the standard of the determination at the referral
stage in the perspective of Sections 8 and 11 of the said Act.
19. The Constitution Bench of the Supreme Court in the case of SBP
and Co. v. Patel Engineering Limited reported in (2005) 8 SCC 618
held that it is imperative on the part of the Chief Justice or the
designated Judge not only to determine the jurisdiction to entertain the
request but shall also determine the existence of a valid arbitration
agreement existence of live claim etc. The larger Bench noticed the
amendment having brought in the year 2015 by introducing Section 11
(6-A) of the Act, wherein the High Court and/or Supreme Court while
exercising the powers under Sub-Sections 4, 5 or 6 shall confine to the
examination of the existence of an arbitration agreement
notwithstanding any judgment, decree or order of any Court. Though
the said amended section impliedly whittle down the proposition laid
down in the SBP and Co. (supra) where the existence of a dispute or a
live claim including the validity of the agreement was also conferred
upon the Court under Section 11 but the said section was subsequently
omitted in the year 2009 by the Parliament when Arbitration And
Conciliation (Amendment) Act, 2019 was passed, but the operation and
effect of the said amended act has not been notified as yet, as a
resultant affect the said amended provision still continued to hold the
field.
20. The larger Bench was conscious on the principle of competence-
competence as well known in the parlance of arbitration law emanating
from Section 16 of the said Act. The said section empowers the arbitral
tribunal to rule its own jurisdiction including the existence or validity of
the arbitration agreement and it does not create any fetter on the part of
arbitral tribunal to decide the same as a preliminary issue. The
enlightening observation of the larger Bench is quoted as under:
"163. Section 16 of the Arbitration Act enshrines the principle of competence-competence in Indian arbitration law. The provision empowers the Arbitral Tribunal to rule on its own jurisdiction, including any ruling on any objections with respect to the existence or validity of arbitration agreement. Section 16 is an inclusive provision which comprehends all preliminary issues touching upon the jurisdiction of the Arbitral Tribunal. [Uttarakhand Purv Sainik Kalyan Nigam Ltd. v. Northern Coal Field Ltd., (2020) 2 SCC 455 :
(2020) 1 SCC (Civ) 570] The doctrine of competence-competence is intended to minimise judicial intervention at the threshold stage. The issue of determining parties to an arbitration agreement goes to the very root of the jurisdictional competence of the Arbitral Tribunal."
21. Although the judgment of the larger Bench rendered in Cox and
Kings (supra) was not taken into consideration in a subsequent
judgment rendered in case of Goqii Technologies (P) Ltd. (supra), but
the observation as quoted above was restated and reapplied in the
following:
"19. The scope of inquiry under Section 11 of the 1996 Act is limited to ascertaining the prima facie existence of an arbitration agreement. In the present case, the High Court exceeded this limited scope by undertaking a detailed examination of the factual matrix. The High Court erroneously proceeded to assess the auditor's report in detail and dismissed [Goqii Technologies (P) Ltd. v. Sokrati Technologies (P) Ltd., 2024 SCC OnLine Bom 3530] the arbitration application. In our view, such an approach does not give effect to the legislative intent behind the 2015 Amendment to the 1996 Act which limited the judicial scrutiny at the stage of Section 11 solely to the prima facie determination of the existence of an arbitration agreement.
20. As observed in Krish Spg. [SBI General Insurance Co. Ltd. v. Krish Spg., (2024) 12 SCC 1 : 2024 SCC OnLine SC 1754 :
2024 INSC 532] , frivolity in litigation too is an aspect which the referral court should not decide at the stage of Section 11 as the arbitrator is equally, if not more, competent to adjudicate the same.
21. Before we conclude, we must clarify that the limited jurisdiction of the referral courts under Section 11 must not be misused by parties in order to force other parties to the arbitration agreement to participate in a time consuming and costly arbitration process. This is possible in instances, including but not limited to, where the claimant canvasses the adjudication of non-existent and mala fide claims through arbitration.
22. With a view to balance the limited scope of judicial interference of the referral courts with the interests of the parties who might be constrained to participate in the arbitration proceedings, the Arbitral Tribunal may direct that the costs of the arbitration shall be borne by the party which the Tribunal ultimately finds to have abused the process of law and caused unnecessary harassment to the other party to the arbitration.
Having said that, it is clarified that the aforesaid is not to be construed as a determination of the merits of the matter before us, which the Arbitral Tribunal will rightfully be equipped to determine.
E. Conclusion
23. The existence of the arbitration agreement in Clause 18.12 of the MSA has not been disputed by the respondent. The question whether there exists a valid dispute to be referred to arbitration can be addressed by the Arbitral Tribunal as a preliminary issue."
22. An argument was advanced dissenting one sentence or paragraph
from the later invoking the arbitration clause that the dispute revolves
around a non-signatory to an agreement which contains an arbitration
clause and in this prospective whether the doctrine of Group of
Companies can be applied. Several judgments were referred to but the
larger Bench in Cox and Kings (supra) in an unequivocal terms held
that such doctrine may have its application in the event non-signatory
have a positive, direct and substantial involvement in the negotiation,
performance or termination of a contract. It is further held that the
incidental involvement is insufficient to bind a non-signatory and such
doctrine does not extend to the non-signatory merely because they are
the members of the same Group of Companies.
23. On a factual matrix, we find a patent distinction in this regard for
a reason that none of the parties to the proceedings have included the
non-signatory of an agreement dated 18th March, 2010. The opposite
party construed the letter invoking the arbitration where it is asserted
that the said opposite party has created an obstacle in renewal and/or
extension of the lease despite an irrevocable power of attorney having
executed in favour of the employee of the company as the said dispute
is beyond the scope of the said agreement containing arbitration clause.
It would not be proper course for the High Court at the stage of Section
11 of the said Act to dissect the claim raising a dispute but must confine
its scrutiny on the existence of an arbitration clause. The moment the
Court found that there exists an arbitration clause between the parties
which is not denied, it must leave the question of arbitrability of the
dispute to the arbitral tribunal, who is competent to decide its own
jurisdiction.
24. Letter dated 4th February, 2023 invoking the arbitration clause
contains various allegations constituting a dispute between the parties
which includes the huge loss suffered by the companies because of the
conduct of the opposite party in clear violation of the terms and
conditions of the said raising contract dated 18th March, 2010.
Astonishingly, despite having received such letter the opposite party
while sending email categorically asserted that he does not recollect
having signed any such raising agreement and demanded such
agreement to be forwarded to him for his knowledge. Though the said
agreement was forwarded by the petitioner vide letter dated 10th
February, 2023 but the same was responded on 2nd March, 2023
claiming that the issues are not part of the subject agreement and there
is already a civil suit pending relating to the cancellation of the power
of attorney and, therefore, the matter being subjudice, there cannot be a
parallel trial by an arbitrator.
25. The conjoint reading of the correspondences exchanged between
the parties manifestly leads to an inescapable conclusion that the
opposite party has not denied the existence of an arbitration clause in a
raising agreement dated 18th March, 2010. In view of the law
pronounced in Goqii Technologies (P) Ltd. (supra) the moment the
High Court finds the existence of an arbitration agreement whether the
dispute raised by the petitioner is touching upon the contract or arising
therefrom or in relation thereto, can be decided by an arbitral tribunal
under the theory of competence-competence. Section 16 of the Act is
not squeezed to the extent that once the parties are referred to
arbitration, the question of arbitral dispute cannot be decided by the
arbitral tribunal. Section 16 is exposit that despite the parties having
referred to arbitral tribunal, the arbitral tribunal can decide its own
jurisdiction and as a preliminary issue may take a decision whether the
disputes are covered under the said arbitration agreement or not.
26. Section 11(6-A) of the Act though omitted by an amended Act of
2019 yet occupies the field of valid provision as the effect of the said
amended provision has not been notified by the Central Government. In
view of the restricted scrutiny in a latter provision introduced by way of
Section 11(6-A) of the Act once the Court finds the existence of the
arbitral agreement, it should not expand its horizon unless the said
amended Act is notified and the provision is taken up from the
legislative document. Thus, this Court does not find any justification
and/or force in the objection raised by the opposite party.
27. Mr. Justice B.P. Das, Former Judge of this Court is hereby
appointed as a sole Arbitrator, who shall decide the dispute between the
parties immediately upon communication of the instant judgment and
determine the dispute raised by the parties. The arbitration shall take
place under the aegis of the High Court of Orissa Arbitration Centre.
Remuneration of the Arbitrator shall be equally paid by the parties as
per the 4th Schedule appended to the said Act. The Arbitrator shall
make efforts to adhere the time limit set forth in Section 29A of the said
Act
28. The arbitration petition is disposed of accordingly. A copy of this
judgment be communicated to the learned Arbitrator forthwith.
( Harish Tandon ) Chief Justice
Location: High Court of Orissa, Cuttack.
SK Jena/Secy.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!