Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Executive Engineer vs M/S. Budharaja Mining And
2023 Latest Caselaw 6532 Ori

Citation : 2023 Latest Caselaw 6532 Ori
Judgement Date : 19 May, 2023

Orissa High Court
Executive Engineer vs M/S. Budharaja Mining And on 19 May, 2023
                                             THE HIGH COURT OF ORISSA AT CUTTACK
                                                       ARBA No.6 of 2021
                                                               and
                                                      W.P.(C) No.429 of 2022
                                    (From the Judgment dated 18.02.2021 passed by the Learned
                                   District Judge, Angul in Arbitration Case No.18 of 2018 arising
                                   out of award dated 23.04.2018 passed in Arbitration Proceeding
                                   No.51 of 2016 by the learned Sole Arbitrator)
                                 In ARBA No.6 of 2021

                                       Executive Engineer, Head Work           ....          Appellants
                                       Division, Samal Barrage & Ors.
                                                                 -versus-
                                       M/s. Budharaja Mining and               ....         Respondent
                                       Construction Limited, Jharpada,
                                       Bhubaneswar
                                       Advocates appeared in the case:
                                       For Appellant             :             Mr. Tarun Patnaik, ASC
                                                                 -versus-

                                       For Respondents           :       Mr. Yashobanta Dash, Sr. Adv.
                                                                                   Mr. Avijit Pal, Adv.

                                 W.P.(C) No.429 of 2022

                                       M/s. Budharaja Mining and               ....           Petitioner
                                       Construction Limited, Jharpada,
                                       Bhubaneswar
                                                                 -versus-
                                       State of Odisha and Ors.                ....        Opp. Parties

                                       Advocates appeared in the case:
                                       For Petitioner            :      Mr. Yashobanta Dash, Sr. Adv.
                                                                                  Mr. Avijit Pal, Adv.
                                                                 -versus-

                                       For Respondents           :             Mr. Tarun Patnaik, ASC

Signature Not Verified
Digitally Signed
Signed by: BHABAGRAHI JHANKAR
                                                                                                  pg. 1
Designation: SECRETARY
Reason: Authentication
Location: Orissa High Court, Cuttack
Date: 25-May-2023 12:19:13
                                                CORAM:
                                               DR. JUSTICE S.K. PANIGRAHI

                                                 DATE OF HEARING:-16.02.2023
                                                DATE OF JUDGMENT:-19.05.2023

                               Dr. S.K. Panigrahi, J.

1. Since both the ARBA and the Writ Petition arose out of arbitral

award dated 23.04.2018 passed in Arbitration Case No.51 of 2016

by the learned Sole Arbitrator, this Court proposed to hear both

the matters together and passes a common order.

2. This ARBA under Section 37 of the Arbitration and Conciliation

Act, 1996 (hereinafter referred to as "A & C Act") has been filed

by the judgment debtors, the present Appellants, seeking setting

aside of the judgment dated 18.02.2021 passed by the Learned

District Judge, Angul in Arbitration Petition No.18 of 2018 arising

out of arbitral award dated 23.04.2018 passed in Arbitration Case

No.51 of 2016 by the learned Sole Arbitrator.

3. The Writ Petition has been filed by the decree holder, the present

Respondent, challenging the order dated 21.12.2021 passed in

Execution Case No.1 of 2019 (arising out of Arbitration Appeal

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 2 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 No.6 of 2021) by the learned District Judge, Angul rejecting its

application for release of the amount of Rs.3.50 crore deposited

by the judgment debtors, the present Appellants, before the

learned District Judge, Angul pursuant to the order dated

01.09.2021 passed by this Court in I.A. No.12 of 2021 arising out

of ARBA No.6 of 2021.

I. FACTUAL MATRIX OF THE CASE:

4. The Department of Water Resources, Government of Odisha

through its Executive Engineer invited tenders for execution of

"Balance New Works of Left Bank Canal from R.D. 17.60 Km. to

23.00 Km. including structures other than H.R. and C.R. and C.D.

at R.D. 20.888 Km. and N.H. Crossing - (Package No. 15)".

5. Respondent's bid was found most competitive and the tender

was awarded to the present Respondent for a contract value of

Rs.6,00,94,462/- vide Letter of Acceptance dated 24.5.1997.

Requisite performance security of Rs.30,04,723/- was furnished by

the present Respondent and thereafter a formal agreement vide

Contract No.2NCB/97-98/PCD dated 26.05.1997 was entered into

Signature Not Verified pg. 3 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 between the parties herein. Accordingly, the present Respondent

commenced work on the stipulated date of commencement i.e.

26.5.1997. The work so awarded was to be completed within 30

months from the date of commencement of work in terms of the

contract.

6. During the execution of the contract, there were hindrances and

impediments which resulted in delay in execution of the work.

There also appears to be a change in the scope of work which led

to variation in the quantities of items. A supplementary

agreement was also executed on 24.01.2002 bearing No.2/2001-

2002 between the parties which approved the execution of extra

items and deviated quantities on agreed upon rates.

7. Upon regular representations being made to the authorities, the

present Respondent was granted extension of time on six

separate occasions, i.e. from 26.11.1999-24.11.2000, 25.11.2000 -

23.11.2000, 24.11.2001 - 24.12.2002, 25.12.2002 - 21.3.2003,

01.04.2003 - 30.6.2003, 01.07.2003 - 31.12.2003.

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 4 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13

8. During the extended period from 24.11.2001 - 24.12.2002, the

Head Works Division issued a termination letter on 02.11.2002.

Upon receiving a representation from the present Respondent

requesting time till 31.03.2003 to complete the work, though the

present Appellants granted the same and even proceeded to

grant two further extensions, it was submitted that the contract

stood closed and fresh bids were invited.

9. As the matter stood thus, vide letter dated 10.02.2004, the

Appellants intimated the present Respondent that the contract

had been terminated as per the General Conditions of Contract.

10.Aggrieved, the Respondent made a representation to the

nominated Adjudicator Er. N.C. Rout in terms of the contract

entered into between the parties but the same was not accepted.

Thereafter, the present Respondent approached this Court in

W.P.(C) No.4419 of 2005 wherein vide order dated 18.01.2012, the

Chairman, Institute of Engineers (India), Orissa State Centre was

directed to appoint an Adjudicator in lieu of Er. N.C. Rout within

Signature Not Verified pg. 5 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 two weeks. Consequently, Er. Ajit Kumar Ray, Retd. Chief

Engineer was appointed as the Adjudicator.

11.The present Respondent submitted a total of 15 claims before the

Learned Adjudicator. The present Appellants in return raised 6

claims in their counter claim.

12.The Learned Adjudicator with reference to the documents on

record in his award dated 13.05.2016, rejected all the counter

claims of the present Appellant. He proceeded to allow six of the

present Respondent's claims in full, two in part and rejected

seven.

13.Both the parties were not satisfied with the award dated 13.5.2016

of the Learned Adjudicator for different reasons and therefore,

the present Respondent approached this Court in an application

under Section 11(6) of the A & C Act numbered as ARBP No.41 of

2016. The said application was disposed of on 21.9.2016

nominating Sri Justice L. Mohapatra (Retd.) as the Sole Arbitrator.

14.The Arbitral Tribunal entered into reference and a claim

statement was filed by the present Respondent seeking

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 6 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 confirmation of the award of the Learned Adjudicator dated

13.5.2016 and award an amount of Rs.2,55,77,488.72 towards

interest at 12% per annum from 01.07.2004 till the date of the

award apart from seeking future interest at 18% per annum from

the date of the award till payment.

15.While the arbitration was pending as such, the present

Appellants approached this Court in an application under Section

11(6) of the A & C Act numbered as ARBP No.9 of 2017 seeking

the appointment of an Arbitrator to adjudicate the dispute

between the parties afresh. The said application was disposed of

vide order dated 20.03.2017 wherein the present Appellants were

asked to file their counter claims before the Learned Sole

Arbitrator and the same was directed to be considered on merits.

16.Thereafter, the present Appellants challenged the award of the

Learned Adjudicator and also claimed a total sum of

Rs.9,31,75,793.78/- against the present Respondent before the

Learned Sole Arbitrator.

Signature Not Verified pg. 7 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13

17.It is pertinent to mention that the present Respondent was

satisfied with the quantum of money allowed in its favour by the

Learned Adjudicator and wanted only confirmation of the same

apart from interest. Whereas, the present Appellants had

countered the same with the claims that no item of claim should

have been awarded in favour of the present Respondent and also

sought the grant of their own counter claim. Therefore, the

Learned Sole Arbitrator has examined the submissions of the

parties only with respect to the claims that were awarded in

favour of the present Respondent either in part or full and all the

counter claims raised by the present Appellants.

18.Multiple witnesses were produced from both sides, various

documents were brought on record and after hearing both

parties, the Learned Arbitral Tribunal was pleased to pass an

award totaling Rs.1,77,50,015.87/- excluding pre reference interest

at the rate of 12% from 01.07.2004 till the date of the award and

future interest at the rate of 18% per annum from the date of

award till payment in favour of the present Respondent. The

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 8 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 Learned Sole Arbitrator also awarded a total of Rs.1,94,439/-

excluding pre reference interest at the rate of 12% per annum

from 28.02.2017 till date of award and future interest at the rate of

18% per annum from the date of award till payment in favour of

the present Appellants.

19.Aggrieved by the said arbitral award, the present Appellants filed

ARBP No.18 of 2018 under Section 34 of the A & C Act before the

Court of the learned District Judge, Angul. The learned District

Judge after hearing both parties, vide order dated 18.02.2021 set

aside the arbitral award to the extent that pre reference interest

computed at 12 % per annum and future interest at 18% per

annum on Rs.1,77,50,015.87/- awarded to the present Respondent

was reduced to simple interest at 9% per annum on

Rs.1,77,50,015.87/- i.e. the total amount awarded, from 01.07.2004

till the date payment is made.

20.Being still aggrieved, the present Appellants have approached

this Court in ARBA No.6 of 2021,challenging the judgment and

order of the learned District Judge dated 18.2.2021.

Signature Not Verified pg. 9 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13

21.At this juncture, it is relevant to note that vide order dated

24.08.2021 in I.A. No.11 of 2021 in the present Appeal, this Court

had condoned the delay in filing the present appeal. Thereafter,

while issuing the notice to the Respondent this Court vide order

dated 01.09.2021 passed in I.A. No.12 of 2021 granted stay further

proceeding in Execution Proceeding No.1 of 2019 pending before

the learned District Judge, Angul subject to deposit of a sum of

Rs.3.50 crore by the Appellants before the executing Court. The

Respondent being the decree holder filed an application i.e. I.A.

No.29 of 2021 in this Appeal for withdrawal of the said amount.

This Court vide order dated 23.11.2021 permitted the

Respondent, decree holder to move such application before the

executing court. Accordingly, the Respondent, decree holder,

filed an application for release of the security amount in its

favour by furnishing adequate security before the learned District

Judge, Angul on 29.11.2021. However. the learned District Judge,

Angul without considering the order dated 23.11.2021 passed by

this Court in the ARBA rejected the application filed by the

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 10 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 Respondent/ decree holder observing that the Executing Court

was denuded with the power to deal with the security money in

any way without the direction of this Court. Being aggrieved, the

Respondent/ decree holder has filed W.P.(C) No.429 of 2022.

Later, the order dated 24.08.2021 passed in I.A. No.11 of 2021 by

this Court condoning the delay in filing the present Appeal was

belatedly sought to be recalled by the present Respondent in I.A.

No.28 of 2022 in the present Appeal. Vide order dated 21.10.2022

passed in I.A. No.28 of 2022 wherein this Court had rejected the

present Respondent's prayer for recall of the order dated

24.08.2021 passed in I.A. No.11 of 2021 in the present Appeal

whereby delay was condoned. As the matter stands decided thus,

the issue of limitation and condonation of delay in filing the

present Appeal shall not be taken up in the present judgment,

having already been decided.

22.Now the facts leading to the instant Appeal have been laid down,

this Court shall make endeavour to summarise the contentions of

the Parties and the broad grounds that have been raised to seek

Signature Not Verified pg. 11 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 the exercise of this Court's rather limited jurisdiction available

under Section 37 of the A&C Act.

II. APPELLANTS' SUBMISSIONS:

23.The counsel for the Appellants assails the arbitral award and the

judgment of the Learned District Judge mainly on the ground

that there has been improper consideration of evidence by the

Learned Tribunal. The same, according to the Learned Counsel is

in contravention to the public policy of India and was

erroneously not looked into by the Learned District Judge. It is

contended that the arbitral award contravenes the terms of the

contract entered into between the parties. It is further contended

that the Respondent is not entitled to any amount awarded to it

as the Learned Sole Arbitrator has misinterpreted certain clauses

of the contract.

24.Furthermore, it is also alleged that the counter claim of the

present Appellants pertaining to loss of the farmers was genuine

and should have been awarded in their favour.

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 12 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 III. RESPONDENT'S SUBMISSIONS:

25.Per contra, learned counsel for the present Respondent states that

the Appellants have not been able to present any reasonable

ground for interfering with the impugned judgment apart from

making bald assertions. It was vehemently submitted that the

scope of interference of this Court in an application under Section

37 of the A&C Act is extremely limited and this Court cannot

reappreciate evidence at this stage. It was also further contended

that the Learned District Judge ought not to have reduced the

rate of interest awarded to the present Respondent as such a

modification is unsustainable in law.

IV. ISSUES FOR CONSIDERATION:

26.Having heard the parties and perused the materials available on

record, this Court here has identified the following issues to be

determined:

A. What is the scope of this Court's power under Section 37 of the A

& C Act and whether the arbitral award is in contravention of the

Signature Not Verified pg. 13 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 public policy of the State under Section 34(2)(b)(ii) as alleged by

the Appellants?

B. Whether the District Court erred in reducing the rate of interest

awarded to the present Respondent i.e. pre reference and future

interest from 12% and 18% respectively to 9% simple interest

while choosing to uphold the award otherwise?

ISSUE A: WHAT IS THE SCOPE OF THIS COURT'S POWER UNDER SECTION 37 OF THE A&C ACT AND WHETHER THE ARBITRAL AWARD IS IN CONTRAVENTION OF THE PUBLIC POLICY OF STATE UNDER SECTION 34(2)(B)(II) AS ALLEGED BY THE APPELLANTS?

27.In the present matter, this Court is solely concerned with an

application preferred under Section 37(1)(c) A & C Act which

states that an appeal lies under Section 37 from an order setting

aside or refusing to set aside an arbitral award under Section 34 A

& C Act.

28. It may be noted that the present position of law, as laid down by

the Supreme Court confines the supervisory role of the courts

while testing the validity of an Arbitration Award. The Supreme

Court, has repeatedly reiterated in Mcdermott International

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 14 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 Inc. v. Burn Standard Co. Ltd.1, UHL Power Co. Ltd. v. State of

H.P.2, NHAI v. M. Hakeem3 and K. Sugumar v. Hindustan

Petroleum Corpn. Ltd.4among others, that the 1996 Act makes

provision for the supervisory role of courts, for the review of the

arbitral award only to ensure fairness. The intervention of the

court is envisaged in few circumstances only, like, in case of fraud

or bias by the Arbitration Tribunals, violation of natural justice,

etc. The court cannot correct errors of the Arbitration Tribunals. It

can only quash the award leaving the parties free to begin the

arbitration again if it is desired.

29.The contours of judicial scrutiny under Section 34 of the A&C Act

are limited and the scope of interference is narrow. Under Section

37 of the A & C Act, the extent of judicial scrutiny and scope of

interference is further narrower. An appeal under Section 37 is

like a second appeal, the first appeal being to the court by way of

objections under Section 34. Where there are concurrent findings

(2006) 11 SCC 181

(2022) 4 SCC 116

(2021) 9 SCC 1

(2020) 12 SCC 539 Signature Not Verified pg. 15 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 of facts and law, first by the Arbitral Tribunal which are then

confirmed by the court while dealing with objections under

Section 34, in an appeal under Section 37, the Appellate Court

should be very cautious and reluctant to interfere in the findings

returned in the award by the Arbitral Tribunal and confirmed by

the court under Section 34.

30.Furthermore, it is no longer res integrathat an arbitral award may

be set aside only if it is against the public policy of India, that is to

say, if it is contrary to:

(a) fundamental policy of Indian law; or

(b) the interest of India; or

(c) justice or morality; or

(d) if it is patently illegal.

31.After the Apex Court's judgment and findings in Oil & Natural

Gas Corporation Ltd. v. Western Geco International Limited5

were subsequently discussed in Associate Builders v. Delhi

(2014) 9 SCC 263 Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 16 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 Development Authority6 the position of law was clarified and laid

down recently by the Supreme Court in Ssangyong Engg. &

Construction Co. Ltd. v. NHAI7, wherein the Court was pleased

to broadly stipulate the aforementioned four constituents of what

makes an award against the "public policy of India".

32.It is also generally recognised that when the Arbitration Tribunal

has thoroughly evaluated the materials and evidence presented

to them, the court, when considering objections under Section 34

of the A&C Act, does not act as a court of appeal and is not

required to "re-examine" all of the evidence or the parties' case on

merits. An award made by an Arbitration Tribunal cannot be

revoked on the ground that another viewpoint is conceivable in

the court's eyes. In these cases, the court's responsibility is to

determine whether the Arbitration Tribunal's point of view on

the relevant facts, pleadings, and evidence is a reasonable one.

The court should be reluctant to intervene even if, after

(2015) 3 SCC 49

(2019) 15 SCC 131

Signature Not Verified pg. 17 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 considering the objections under Section 34, it were determined

that there were two possible assessments of the material and that

the Arbitral Tribunal had taken one route instead of the other. If

the Arbitration Tribunal's viewpoint is reasonable, the court is not

permitted to substitute its own opinion for that of the Learned

Arbitrator. The same has been previously reiterated by this Court

in State of Orissa v. Bhagyadhar Dash8 and more recently in

judgment dated 09.01.2023 in ARBA No.39 of 2018 titled as

United India Insurance Company Ltd., Bhubaneswar v. Suryo

Udyog Ltd.

33. This Court had the opportunity to peruse Arbitral Award and

the Learned District Judge's judgment and order. It is pertinent to

first note the meticulousness showcased by the Learned Sole

Arbitrator in assessing each claim. Every disputed claim that was

taken up was divided into the Claimant's (present Respondent)

case, the Respondents (present Appellants) case, any document or

2016 SCC OnLine Ori 1039

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 18 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 witness testimony on record which pertains to the same and then

the finding. Similarly, for each counter claim as well, the Learned

Sole Arbitrator has shown a similar conscientiousness. The

present Appellants claim that apart from the claims award in

favour of the present Respondent, they are gravely aggrieved by

the disallowance of their Counter Claim, especially Counter

Claim No.1.

34.Counter Claim No.1 as presented before the Learned Sole

Arbitrator pertains to "compensation towards loss of farmers"

wherein the present Appellants claims Rs.8,56,03,424/-. It was the

present Appellants' case that on account of the delay in

completion of the project, the farmers sustained a loss. A farmer

of the area was also produced as a witness but the Learned Sole

Arbitrator took note that the said witness did not state the extent

of the loss he sustained due to delay in completion of the project,

nor did he give any concrete particulars about the inconvenience

and monetary loss that was caused to him as a result of delay in

completion of the project. The present Appellants also did not

Signature Not Verified pg. 19 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 produce a single document which would indicate any farmer in

the area having sought compensation on account of delay in

completion of the project. It was the Learned Sole Arbitrator's

view that if no proof or material has been brought on record to

showcase that the farmers have in fact raised any claim for

compensation, there is no basis for the State to recover this

unsubstantiated/ unquantifiable compensation from the present

Respondent company.

35.This Court doesn't find this view of the Learned Sole Arbitrator

to be unreasonable. The Learned Sole Arbitrator in his award, has

appreciated all relevant pieces of evidence, examined witness

statements, and simultaneously evaluated the tenacity of the

claims of the parties in light of the terms of contract, to arrive at a

reasoned conclusion.

36.It is seen that in general, the Learned Sole Arbitrator has

elaborately considered the various documents, submissions and

evidence led by the parties in respect of each claim, particularly

this one. The Learned Sole Arbitrator has extensively gone into

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 20 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 the evidence and evaluated the entire material before him to

publish a detailed speaking award.

37.The Supreme Court in P.R. Shah Shares & Stock Broker (P)

Ltd. v. B.H.H. Securities (P) Ltd.9 has held that a Court does not

sit in appeal over the award of an Arbitrator by re-assessing or re-

appreciating the evidence. An award can be challenged only on

the grounds mentioned in Section 34(2) of the Act and in absence

of any such ground, it is not possible to re-examine the facts to

find out whether a different decision could have been arrived at.

This view was reiterated by the High Court of Delhi in M/S

Pragya Electronics Pvt. Ltd. v. M/s Cosmo Ferrites Ltd.10and the

Apex Court in Swan Gold Mining Ltd. v. Hindustan Copper

Ltd.11. In light of the aforesaid facts, and the present Appellant's

inability to substantiate its case, this Court does not doubt that

there is no patent illegality in the present case much less, any

(2012) 1 SCC 594

2021 SCC OnLine Del 3428

(2015) 5 SCC 739 Signature Not Verified pg. 21 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 apparent violation of any terms of public policy in the present

case.

ISSUE B: WHETHER THE DISTRICT COURT ERRED IN REDUCING THE RATE OF INTEREST AWARDED TO THE PRESENT RESPONDENT I.E. PRE REFERENCE AND FUTURE INTEREST FROM 12% AND 18% RESPECTIVELY TO 9% SIMPLE INTEREST WHILE CHOOSING TO UPHOLD THE AWARD OTHERWISE?

38. This Court is to preface this issue by stating that as per the

present position of law, in terms of Section 34 of the A&C Act, an

arbitral award can only be confirmed or set aside in its entirety,

but not modified. Reliance is placed on the Supreme Court's

recent judgment and order in NHAI v. M. Hakeem(supra),

wherein the Supreme Court held that:

"48. Quite obviously if one were to include the power to modify an award in Section 34, one would be crossing the Lakshman Rekha and doing what, according to the justice of a case, ought to be done. In interpreting a statutory provision, a Judge must put himself in the shoes of Parliament and then ask whether Parliament intended this result. Parliament very clearly intended that no power of modification of an award exists in Section 34 of the Arbitration Act, 1996. It is only for Parliament to amend the aforesaid provision in the light of the experience of the courts in the working of the Arbitration Act, 1996, and bring it in line with other legislations the world over."

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 22 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13

39. It now becomes pertinent to assess the law relating to award of

interest especially in cases where the agreement between the

parties is silent as to the nature, manner and rate of such interest.

40. The legal provision in connection with this issue is contained in

Section 31(7)(a) and Section 31(7)(b) of the A&C Act. The relevant

portion is reproduced hereinbelow:

"31. Form and contents of arbitral award.-- xxx (7) (a) Unless otherwise agreed by the parties, where and in so far as an arbitral award is for the payment of money, the arbitral tribunal may include in the sum for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made.

1[(b) A sum directed to be paid by an arbitral award shall, unless the award otherwise directs, carry interest at the rate of two per cent. higher than the current rate of interest prevalent on the date of award, from the date of award to the date of payment.

Explanation.--The expression "current rate of interest" shall have the same meaning as assigned to it under clause (b) of section 2 of the Interest Act, 1978 (14 of 1978).]"

41.The Supreme Court in Bhagwati Oxygen Ltd. v. Hindustan

Copper Ltd.12 wherein it has been held that if there is no provision

AIR 2005 SC 2071 Signature Not Verified pg. 23 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 in the arbitration agreement for a rate of interest, then it is in the

discretion of the Learned Arbitrators only to determine the rate

of interest to be granted based on the facts and the circumstances

of the matter in hand. The Learned Arbitrators further have the

power and jurisdiction to grant interest in all three stages of an

arbitration i.e. pre reference period, pendente lite and post award

period. The Learned Arbitrators in this regard are only bound by

the terms of the agreement entered into between the parties, but

in cases such as this matter at hand, when the agreement is silent

about the question of interest, the Learned Arbitrators are

required to use the test of reasonableness and exercise their

discretion in awarding interest.

42. Conclusively laying down the principles to govern such matters,

the Supreme Court in Irrigation Deptt., Govt. of Orissa v. G.C.

Roy13, has held that:

"43. The question still remains whether arbitrator has the power to award interest pendente lite, and if so on what principle. We must reiterate that we are dealing with the situation where the agreement does not provide

(1992) 1 SCC 508 Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 24 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 for grant of such interest nor does it prohibit such grant. In other words, we are dealing with a case where the agreement is silent as to award of interest. On a conspectus of aforementioned decisions, the following principles emerge:

(i) A person deprived of the use of money to which he is legitimately entitled has a right to be compensated for the deprivation, call it by any name. It may be called interest, compensation or damages. This basic consideration is as valid for the period the dispute is pending before the arbitrator as it is for the period prior to the arbitrator entering upon the reference. This is the principle of Section 34, Civil Procedure Code and there is no reason or principle to hold otherwise in the case of arbitrator.

(ii) An arbitrator is an alternative form (sic forum) for resolution of disputes arising between the parties. If so, he must have the power to decide all the disputes or differences arising between the parties. If the arbitrator has no power to award interest pendente lite, the party claiming it would have to approach the court for that purpose, even though he may have obtained satisfaction in respect of other claims from the arbitrator. This would lead to multiplicity of proceedings.

(iii) An arbitrator is the creature of an agreement. It is open to the parties to confer upon him such powers and prescribe such procedure for him to follow, as they think fit, so long as they are not opposed to law. (The proviso to Section 41 and Section 3 of Arbitration Act illustrate this point). All the same, the agreement must be in conformity with law. The arbitrator must also act and make his award in accordance with the general law of the land and the agreement.

(iv) Over the years, the English and Indian courts have acted on the assumption that where the agreement does not prohibit and a party to the reference makes a claim for interest, the arbitrator must have the power to award interest pendente lite. Thawardas [Seth

Signature Not Verified pg. 25 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 ThawardasPherumal v. Union of India, (1955) 2 SCR 48 : AIR 1955 SC 468] has not been followed in the later decisions of this Court. It has been explained and distinguished on the basis that in that case there was no claim for interest but only a claim for unliquidated damages. It has been said repeatedly that observations in the said judgment were not intended to lay down any such absolute or universal rule as they appear to, on first impression. Until Jena case [(1988) 1 SCC 418 : (1988) 1 SCR 253] almost all the courts in the country had upheld the power of the arbitrator to award interest pendente lite. Continuity and certainty is a highly desirable feature of law.

(v) Interest pendente lite is not a matter of substantive law, like interest for the period anterior to reference (pre- reference period). For doing complete justice between the parties, such power has always been inferred."

43.On this point, this Court considers it apposite to going back to

reading Dispute/Claim No. 15 framed by the Arbitral Tribunal in

its award pertaining to the rate of interest to be granted in the

matter, wherein the Arbitral Tribunal has prescribed its reasoning

for awarding interest to the Claimant i.e. present Respondent.

The relevant portion of the discussion is reproduced herein:

"... Having found that the Claimant is entitled to the above amount there is no reason for me to deny the claim of interest both pre reference and future. Clause 43.1 of the agreement provides for payment of 12% interest per annum for delayed payment. Therefore, the Adjudicator granted future interest at 12%. Since I hold that the Claimant is entitled to both pre-reference and future

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 26 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 interest, the Claimant is entitled to pre-reference interest at the rate of 12% per annum from 10.2.2004 when the contract was terminated. However, the Claimant having claimed pre-reference interest from 1.7.2004, I allow interest at the rate of 12% per annum from 1.7.2004 till the date of award which comes to Rs. 81,05,820/- and I also allow future interest at the rate of 18% per annum from the date of award till payment, in the event, the Respondents fail to satisfy the award within three months from the date of award..."

44.Similarly, the Learned Sole Arbitrator has been fair and in the

interest of equity, deemed the present Appellants to also be

entitled to pre reference interest on the awarded amount in their

favour at the rate of 12% per annum, i.e. from the date of

termination of contract dated 2.11.2002 till the date of the award

and from the date of the award till payment. However, as the

present Appellants have claimed pre-reference interest only from

28.02.2017, therefore, pre-reference interest was awarded at the

rate of 12% from 28.02.2017 till the date of the award.

Additionally, future interest was awarded at the rate of 18% from

the date of the award till the date of payment.

45.Having regard to the aforesaid position of law and the facts of the

matter in hand, this Court comes to the conclusion that the

Signature Not Verified pg. 27 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 Learned District Judge should not have interfered with the rate

of interest awarded by the Learned Arbitral Tribunal, a

modification which in itself is impermissible in law given the

Supreme Court's judgment and order recently in NHAI v. M.

Hakeem (supra).It was therefore, not appropriate to reduce the

rate of interest awarded to the present respondent i.e. pre

reference and future interest from 12% and 18% respectively to

9% simple interest while choosing to uphold the award otherwise

while pertinently choosing to not simultaneously reduce the rates

of interest awarded to the present Appellants.

V. CONCLUSION:

46.Therefore, in light of the above discussion, keeping the settled

principles of law in mind and for the reasons given above, this

Court is of the considered view that the learned Sole Arbitrator

acted well within his jurisdiction in awarding the appropriate

relief.

47. The award Rs.1,77,50,015.87/- excluding pre reference interest at

the rate of 12% from 1.7.2004 till 23.04.2018 and future interest at

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 28 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 the rate of 18% per annum from 23.04.2018 till the date of

payment in favour of the present Respondent and Rs.1,94,439/-

excluding pre reference interest at the rate of 12% per annum

from 28.2.2017 till 23.4.2018 and future interest at the rate of 18%

per annum from 23.04.2018 till the date of payment in favour of

the present Appellants vide arbitral award dated 23.04.2018 is

reinstated in its entirety and upheld The parties are directed to

make good their respective share of the payments without any

further delay.

48.Consequently, it is observed that the present appeal i.e. ARBA

No.6 of 2021 bears no merit and is hereby dismissed. However, it

is clarified that interest is to be calculated as per the rates

originally awarded by the Learned Sole Arbitrator in his award

dated 23.04.2018. The Arbitral Award is hereby upheld. ARBA

No.6 of 2021 is disposed on the abovementioned terms. No order

as to costs.

49. In view of the dismissal of the present ARBA, the interim order

dated 01.09.2021 passed by this Court in I.A. No.12 of 2021 arising

Signature Not Verified pg. 29 Digitally Signed Signed by: BHABAGRAHI JHANKAR Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13 out of ARBA No.6 of 2021 stands vacated. Accordingly, the

Executing Court is at liberty to proceed with the Execution Case

No.1 of 2019.

50. With such observations, W.P.(C) No.429 of 2022 is also disposed

of.

(Dr. S.K. Panigrahi) Judge

Orissa High Court, Cuttack, Dated the 19th May,, 2023/B. Jhankar

Signature Not Verified Digitally Signed Signed by: BHABAGRAHI JHANKAR pg. 30 Designation: SECRETARY Reason: Authentication Location: Orissa High Court, Cuttack Date: 25-May-2023 12:19:13

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter