Citation : 2023 Latest Caselaw 5189 Ori
Judgement Date : 5 May, 2023
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBA No.21 of 2007
(From the Judgment dated 26.07.2007 passed by the learned
District Judge, Dhenkanal in Arbitration Petition No.249 of
2005 arising out of arbitration award dated 27.07.2005 passed in
Arbitration Case No.1 of 2003
Babaji Nayak .... Appellant
-versus-
RITES Limited represented through .... Respondent
its Deputy General Manager(C), RITES
Advocates appeared in the case:
For Appellant : Mr. B.N. Mohanty, Adv.
-versus-
For Respondent : Mr. B.S. Tripathy, Adv.
CORAM:
DR. JUSTICE S.K. PANIGRAHI
DATE OF HEARING:-18.01.2023
DATE OF JUDGMENT:-05.05.2023
Dr. S.K. Panigrahi, J.
1. This Appeal under Section 37 of the Arbitration and Conciliation
Act, 1996 (hereinafter referred to as "the Act" for brevity) has been
filed seeking setting aside of the Judgment dated 26.07.2007
pg. 1 passed by the learned District Judge, Dhenkanal in Arbitration
Petition No.249 of 2005 arising out of arbitration award dated
27.07.2005 passed in Arbitration Case No.1 of 2003 by the learned
Sole Arbitrator Shri Govinda Das, Sr. Advocate.
I. FACTUAL MATRIX OF THE CASE:
2. In response to the Tender Call Notice dated 15.11.2000 issued by
the present Respondent, the Appellant submitted his tender on
12.12.2000 for execution of the balance work pertaining to Section
KB-I and II for Kalinga Railway Siding at Talcher, Angul District.
3. Having been declared successful, work order dated 25/30.1.2001
was issued in favour of the Appellant. The work order indicated
the time limit for completion of the contract to be three months.
After receiving the work order, the Appellant approached the
present Respondent at the site office for handing over of the site.
Subsequently, a portion of the site was handed over to the
Appellant on 02.02.2001 and the completion period of the work
was to be countenanced from that date.
4. Upon commencement of execution of the work, the tenants of Plot
Nos.1414, 1415 and 1416 of Khata No.184 of Mouza-Danara raised
a hue and cry on account of non-receipt of compensation as well
as employment pursuant to the land acquisition by Mahanadi
Coal Fields Ltd. These tenants allegedly created grave obstruction
and did not allow the present Appellant to proceed with execution
of the work. The same appears to have been intimated by the
pg. 2 Appellant to the Respondent through multiple letters, with the
first being written on 01.03.2001 and last on 20.11.2001.
5. It appears that despite the fact that the adverse situation was
brought to the knowledge of the present Respondent, it insisted
on completion of the work without rendering any assistance to
solve the issue of obstructions created by the tenants. Meanwhile,
the present Appellant also allegedly attempted to resolve the
issues of the tenants but the same was to no avail. In these
circumstances, the present Appellant requested the Respondent to
close the contract with refund of the security deposit and settle his
claims towards deployment of machines and man power at the
site for the extended period. It is pertinent to note here that there
was unilateral extension of time for completion of the work by the
Respondent despite no such request having been made by the
present Appellant.
6. However, in response to the request for closure of the contract, the
Respondent served an ultimatum on the Appellant to complete
the work in line with the extension granted i.e. by 13.11.2001 or
suitable action would be taken under Clause-62 of the General
Conditions of Contract. Vide letter dated 13.11.2001, the
Respondent gave the Appellant 48 hours additionally to complete
the work, failing which the contract would stand rescinded and
the earnest money deposited by the Appellant would be forfeited.
It was also brought to the notice of the Appellant that upon his
pg. 3 failure to complete the work, a subsequent agency would be
brought in to complete the work.
7. The contract ultimately stood rescinded by the Respondent on
20.11.2001. The present Appellant vide letter dated 27.12.2001
claimed a compensation of Rs.90,57,084/- towards the financial
loss sustained by the Appellant and requested that the matter may
be referred to Arbitration as per Clause 63 of the General
Conditions of Contract.
8. Upon failure of the Respondent to appoint an Arbitrator within
the 30 days, the Appellant approached this Court under Section
11(6) of the Act, wherein after hearing the parties, Sri Govinda
Das, Sr. Advocate was appointed as the sole Arbitrator to
adjudicate the dispute and difference between the parties.
9. After hearing the parties, the learned Sole Arbitrator vide his
award dated 27.07.2005 was pleased to partly allow the claims
made by the Appellant and rejected all the counter claims of the
Respondent. The learned Arbitrator partly allowed Claim No.2
(hiring charges of machineries) at Rs.7,500/- for 288 days for a total
of Rs.21,00,000/-; Claim No.4 (the wages of the employees
employed by the Appellant) for Rs.85,000/-; Claim No.10 (loss of
profit) at Rs.2,18,000/-, Claim No.1 (refund of security
deposit/EMD) at Rs.50,000/- and Claim No.12 (cost of litigation) at
Rs.15,000/- for a total amount of Rs.24,68,000/- with interest @ 9%
pg. 4 per annum from the date of commencement of the arbitration
proceeding to the date of payment of the amount.
10. Being aggrieved, the present Respondent approached the learned
District Judge, Dhenkanal under Section 34 of the Act vide ARBP
No.249 of 2005 seeking setting aside of the arbitral award dated
27.07.2005. After hearing both parties, the learned District Judge
vide order dated 26.07.2007, while upholding the award, partially
modified the same and reduced the amount awarded under Claim
No.2 (hiring charges of machineries) from Rs.21,00,000/- to
Rs.6,75,000/- and also set aside the Claim No. 2 (cost of litigation)
completely. The awarded amount was, therefore, revised by the
learned District Judge from Rs.24,68,000/- to Rs.10,28,000/-.
11.Being aggrieved, the present Appellant filed the present appeal
under Section 37 of the Act seeking setting aside of the judgment
dated 26.07.2007 passed by the learned District Judge, Dhenkanal
in Arbitration Petition No.249 of 2005 arising out of arbitration
award dated 27.07.2005 passed in Arbitration Case No.1 of 2003 by
the learned Sole Arbitrator.
12.As the matter stood thus, while the present Appeal was pending,
the present Respondent paid an amount of Rs.13,43,016/- to the
Appellant. The present Respondent then contended that the said
amount was paid in "full and final settlement" of the award as
modified by the learned District Judge vide order dated 26.07.2007
in Arbitration Petition No.249 of 2005 and, therefore, the present
pg. 5 Appeal ought to be dismissed. Despite protest by the counsel for
the Appellant, the said contention was accepted by this Court and
the present Appeal stood dismissed by order dated 13.09.2019 in
ARBA No.21 of 2007. However, the present Appellant approached
the Supreme Court vide SLP(C) No.27625 of 2019 and sought the
setting aside of order of this Court dated 13.09.2019 passed in the
present Appeal. The Supreme Court was pleased to allow the
Special Leave Petition and vide order dated 23.08.2022 in SLP(C)
No.27625 of 2019 directing that the present Appeal be restored
and adjudicated upon independently on its own merits.
13.Now that the facts leading up to the instant Appeal has been laid
down, this Court makes endeavour to summarise the contentions
of the Parties and the broad grounds on which they have
approached this Court seeking the exercise of this Court's limited
jurisdiction available under Section 37 of the Act.
II. APPELLANT'S SUBMISSIONS:
14. The counsel for the Appellant assails the impugned order dated
26.07.2007 of the learned District Judge mainly on the ground that
the learned District Judge, ignored the exclusive list of limited
grounds as contemplated under Section 34 of the Act and made an
endeavor to enlarge the scope of the same in order to interfere
with the award passed by the Arbitrator.
15.Furthermore, it was vehemently contended that while modifying
and reducing the amount awarded by the Arbitrator under Claim
pg. 6 No.2 (hiring charges of machines), the learned District Judge has
re-appreciated the evidence in order to examine the correctness of
the conclusion of the Arbitrator. By substituting his own views
and evaluation with that of the Arbitrator, the learned District
Judge has contravened the settled position of law which does not
permit any such substitution. Upon arriving at the conclusion that
the arbitral award is not in conflict with public policy or any
substantive law, the learned District Judge went beyond the scope
of Section 34 of the Act in substituting the reasoning of the
Arbitrator as well as partially modifying the award, both of which,
as submitted, is impermissible in law.
16.As regards to the cross objections filed by the present Respondent,
it was submitted by the counsel for the Appellant that the same is
impermissible and not maintainable in law. Furthermore, the
conduct of the Respondents in disbursing the amount as modified
by the learned District Judge indicates their acceptance and
admission of their liability.
III. RESPONDENT'S SUBMISSIONS:
17. Per contra, the learned Counsel for the Respondent submitted that
the present appeal ought to be dismissed as the Appellant has
received the entire modified awarded amount including the
interest on 03.11.2007 without any objection and demur.
18. Furthermore, in the entire discussion on Claim No.2, it was
submitted that there was no finding or reason assigned by the
pg. 7 Arbitrator that the contractor is entitled to compensation at the
rate of Rs.7500/- per day for 280 days (though the contract period
was for 90 days). The Arbitrator failed to appreciate that a
contractor who was entrusted with the work for a total contract
value of Rs.21,72,400/- would never pay hiring charges of
Rs.22,500/- per day as in that eventuality the contractor would
have a paltry sum to meet the expenses of labour payment, cost of
material and cost of establishment. The award of hiring charges of
Rs.7500/- per day was, therefore, violative of the Act.
19.It was also submitted that the Award was illegal as the Arbitrator
had deliberately ignored the material documents filed by the
Respondent. The award is not based on the evidence on record
and the Arbitrator distorted the tenor of the contract by giving
inconsistent and contradictory conclusions. As such, it was
vehemently submitted that the Award of the Arbitrator is not in
conformity with the public policy of India.
20. With reference to the cross objections, the counsel for the
Respondent submitted that the learned District Judge having held
that the Arbitrator has committed serious illegalities, should have
set aside the entire awarded amount instead of partially
modifying the same. Furthermore, the Respondent alleged that no
part of the award could be sustained as the appointment of the
Arbitrator was without jurisdiction and this aspect was not
properly considered by the Arbitrator while disposing of the
pg. 8 petition under Section 16 of the Act. It was also submitted that the
learned District Judge did not take note of the entire matter in its
proper perspective and as such the judgement of the court to the
extent it upheld the award is liable to be set aside.
IV. ISSUES FOR CONSIDERATION:
21.Having heard the learned Counsel for the parties and perused the
materials available on record, this Court here has identified the
following issues to be determined:
A. What is the scope of this Court's power under Section 37 of the Act and whether the arbitral award is in contravention of the public policy of State under Section 34(2)(b)(ii) of the Act?
B. Whether the Court while considering the objections under Section 34 of the Act may sit as a Court of appeal and re-appreciate or reassess the case of the parties and whether the Court is permitted to partially modify the award?
C. Whether the Appellant is barred from raising any dispute after accepting any payment of the nature of alleged "full and final payment"?
D. Whether the Arbitrator erred in law by granting interest on the awarded amount in the absence of a provision in the contract between the parties?
E. Whether a cross objection is maintainable in an appeal under Section 37 of the Act?
V. ISSUE A: WHAT IS THE SCOPE OF THIS COURT'S POWER UNDER SECTION 37 OF THE ACT AND WHETHER THE ARBITRAL AWARD IS IN CONTRAVENTION OF THE PUBLIC POLICY OF STATE UNDER SECTION 34(2)(B)(II) OF THE ACT?
pg. 9
22. In the present matter, this Court concerned with Section 37(1)(c)
which states that an appeal lies under Section 37 from an order
setting aside or refusing to set aside an arbitral award under
Section 34. This Court has had the occasion to recently deal with
this question in its judgment dated 09.01.2023 in ARBA No.39 of
2018 titled as United India Insurance Company Ltd., Bhubaneswar
v. Suryo Udyog Ltd.
23. The Supreme Court has confined the supervisory role of the
Courts when it comes to testing the validity of an Arbitration
Award. The Supreme Court in Mcdermott International
Inc. v. Burn Standard Co. Ltd.1 held that the Court may intervene
only in cases involving fraud, bias, violation of the principles of
natural justice, etc. but not to correct errors of the Arbitrator. The
interference of the Court must be kept at a minimum level.
24.Under Section 37, the extent of judicial scrutiny and scope of
interference is further narrower. The Supreme Court in UHL
Power Co. Ltd. v. State of H.P.2, recently held as follows:
"16. As it is, the jurisdiction conferred on courts under Section 34 of the Arbitration Act is fairly narrow, when it comes to the scope of an appeal under Section 37 of the Arbitration Act, the jurisdiction of an appellate court in examining an order, setting aside or refusing to set aside an award, is all the more circumscribed. In MMTC
(2006) 11 SCC 181
(2022) 4 SCC 116
pg. 10 Ltd. v. Vedanta Ltd. [MMTC Ltd. v. Vedanta Ltd., (2019) 4 SCC 163 : (2019) 2 SCC (Civ) 293] , the reasons for vesting such a limited jurisdiction on the High Court in exercise of powers under Section 34 of the Arbitration Act have been explained in the following words : (SCC pp. 166-67, para 11) "11. As far as Section 34 is concerned, the position is well-settled by now that the Court does not sit in appeal over the arbitral award and may interfere on merits on the limited ground provided under Section 34(2)(b)(ii) i.e. if the award is against the public policy of India. As per the legal position clarified through decisions of this Court prior to the amendments to the 1996 Act in 2015, a violation of Indian public policy, in turn, includes a violation of the fundamental policy of Indian law, a violation of the interest of India, conflict with justice or morality, and the existence of patent illegality in the arbitral award. Additionally, the concept of the "fundamental policy of Indian law" would cover compliance with statutes and judicial precedents, adopting a judicial approach, compliance with the principles of natural justice, and Wednesbury [Associated Provincial Picture Houses Ltd. v. Wednesbury Corpn., (1948) 1 KB 223 (CA)] reasonableness. Furthermore, "patent illegality" itself has been held to mean contravention of the substantive law of India, contravention of the 1996 Act, and contravention of the terms of the contract."
pg. 11 A similar view, as stated above, has also been taken by the
Supreme Court in K. Sugumar v. Hindustan Petroleum Corpn.
Ltd.3.
25.It is in the parameters as laid down by the Apex Court vis-a-vis
the scope of judicial intervention that the present appeal
impugning the order dated 26.07.2007 passed by the learned
District Judge, Dhenkanal in Arbitration Petition No.249 of 2005
arising out of arbitration award dated 27.07.2005 passed in
Arbitration Case No.1 of 2003 by the learned Sole Arbitrator shall
be dealt with.
26.In Oil & Natural Gas Corporation Ltd. v. Western Geco
International Limited4, the Apex Court has observed that the
award could be set aside if it is against the public policy of India,
that is to say, if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality; or
(d) if it is patently illegal.
27.After being subsequently discussed in Associate Builders v. Delhi
Development Authority5 the position of law was clarified and laid
(2020) 12 SCC 539
(2014) 9 SCC 263
(2015) 3 SCC 49
pg. 12 down recently by the Supreme Court in Ssangyong Engg. &
Construction Co. Ltd. v. NHAI6 wherein it was held that:
"36. Thus, it is clear that public policy of India is now constricted to mean firstly, that a domestic award is contrary to the fundamental policy of Indian law, as understood in paras 18 and 27 of Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , or secondly, that such award is against basic notions of justice or morality as understood in paras 36 to 39 of Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] ."
28. It is the Respondent's earnest contention that the arbitral award
goes against the fundamental public policy of India as the
appointment of the Arbitrator is contrary to the mandate of the
contract. The same issue was agitated by the Respondent in the
appeal preferred by them under Section 34 of the Act. The learned
District Judge has correctly given this issue primacy as the same
affects the root of the matter.
29.In this regard, this Court notes that it was the Appellant who vide
letter dated 27.12.2001 raised a demand to refer the dispute to an
Arbitrator. Upon receiving no reply, the Appellant approached
this Court under Section 11(6) of the Act seeking appointment of
an Arbitrator. This Court vide order dated 05.09.2002, was pleased
to appoint Sri Govinda Das, Sr. Advocate to adjudicate the dispute
(2019) 15 SCC 131
pg. 13 and difference between the parties. Section 11 of the Act clearly
stipulates that if the parties fail to agree on an Arbitrator within 30
days of the date of receipt of the request made, then the Chief
Justice or any person or institution designated by him may be
approached to secure the appointment of an Arbitrator. When the
present Respondent failed to act, as is required by the statute, the
Appellant approached this Court. The present Respondent's
grievance arises from the fact that Clause 64.6 of the General
Conditions of Contract which states that the Arbitrator is to be an
Engineer from the Respondent's company. However, this Court is
of the view that the said contention will not survive because the
intent of Section 11 of the Act clearly implies that the Chief Justice
or his designate will make the "choice" of the person to be
appointed as an Arbitrator. Being thus so, the Chief Justice or his
designate cannot be said to be bound by the agreement entered
into between the parties, as if the same was the intention of the
legislature, then it would have been expressly provided in the Act.
The Supreme Court has held in this regard in Datar Switchgears
Ltd. v. Tata Finance Ltd.7 that if the opposite party, upon receipt
of a request for appointment of an arbitrator, does not do so
within 30 days, then the opposite party's right shall cease in this
regard. This reasoning, which was also adopted by the learned
District Judge, suffers no infirmity.
(2000) 8 SCC 151
pg. 14
30.Therefore, bearing in mind the limited scope for this Court's
interference, the arbitral award cannot be said to be perverse,
absurd or against the fundamental public policy of India on this
ground.
VI. ISSUE B: WHETHER THE COURT WHILE CONSIDERING THE OBJECTIONS UNDER SECTION 34 OF THE ACT MAY SIT AS A COURT OF APPEAL AND RE-APPRECIATE OR REASSESS THE CASE OF THE PARTIES AND WHETHER THE COURT IS PERMITTED TO PARTIALLY MODIFY THE AWARD?
31. The law is no longer res integra that where the Arbitrator has
assessed the material and evidence placed before them in detail,
the Court while considering the objections under Section 34 of the
said Act does not sit as a Court of appeal and is not expected to re-
appreciate the entire evidence and reassess the case of the parties.
It is not open to the Court to interfere with the award merely
because in the opinion of the Court, another view is possible. The
duty of the Court, in these circumstances, is to see whether the
view taken by the Arbitrator is a plausible view on the facts,
pleadings and evidence before the Arbitrator. Even if on the
assessment of material, this Court while considering the objections
under Section 34 is of the view that there are two views possible
and the Arbitral Tribunal has taken one of the possible views
which could have been taken on the material before it, the court
would be reluctant to interfere. The Court is not to substitute its
pg. 15 view with the view of the Arbitrator if the view taken by the
Arbitrator is supported by his own reasoning. The same has been
previously reiterated by this Court in State of Orissa v.
Bhagyadhar Dash8.
32.It is seen that the Arbitrator has elaborately considered the various
documents, submissions and evidence led by the parties. The
contract being extended - whether unilaterally or not, would
create a duty to perform on the Appellant. The Appellant has
shown that he was willing and desirous to complete the contract
but because of the lack of assistance from the Respondent, he
could not do so. In this regard, this Court does not deem it
unreasonable that the Appellant would have had deployed
machinery for the entire duration of the contract. As such, the
Arbitrator has applied his mind and granted reasonable hiring
charges per day instead of directly allowing the hiring charges
claimed by the Appellant. The Supreme Court in P.R. Shah Shares
& Stock Broker (P) Ltd. v. B.H.H. Securities (P) Ltd.9 has held that
a Court does not sit in appeal over the award of an Arbitrator by
re-assessing or re-appreciating the evidence. An award can be
challenged only on the grounds mentioned in Section 34(2) of the
Act and in absence of any such ground, it is not possible to re-
examine the facts to find out whether a different decision can be
2016 SCC OnLine Ori 1039
(2012) 1 SCC 594
pg. 16 arrived at. This view was reiterated by the Apex Court in Swan
Gold Mining Ltd. v. Hindustan Copper Ltd.10, K.V. Mohd. Zakir v.
Regional Sports Center11 and State of U.P. v. Ram Nath
Constructions12 and the High Court of Delhi in M/S Pragya
Electronics Pvt. Ltd. v. M/s Cosmo Ferrites Ltd.13.
33.The learned District Judge has entered into the merits of the claim
and has decided the appeal under Section 34 of the Act as if the
District Court was deciding the dispute between the parties
afresh. The learned District Judge has embarked on a journey to
substitute his own reasoning with that of the learned Arbitrator by
modifying the amount payable under Claim No.2. The learned
District Judge has exercised jurisdiction not vested in it under
Section 34 of the Act.
34.Furthermore, it has been held time and again by the Supreme
Court in McDermott International Inc. v. Burn Standard Co.
Ltd.14, Kinnari Mullick v. Ghanshyam Das Damani15 and Dakshin
Haryana Bijli Vitran Nigam Ltd. v. Navigant Technologies (P)
Ltd.16. that under Section 34, the award can only be confirmed or
set aside, but not modified. The Supreme Court recently in NHAI
(2015) 5 SCC 739 11 AIR 2009 (SCW) 6217
(1996) 1 SCC 18
2021 SCC OnLine Del 3428
(2006) 11 SCC 181
(2018) 11 SCC 328
(2021) 7 SCC 657 pg. 17 v. M. Hakeem17, held that Section 34 being an appellate provision,
only provides for setting aside awards on very limited grounds.
Section 34 of the Act, does not include within its scope, the power
to modify an award.
35.In light of the settled position of law, this Court is unable to
sustain the reappreciation of the evidence or the modification of
the arbitral award by the learned District Judge.
VII. ISSUE C: WHETHER THE APPELLANT IS BARRED FROM RAISING ANY DISPUTE AFTER ACCEPTING ANY PAYMENT OF THE NATURE OF ALLEGED "FULL AND FINAL PAYMENT"?
36. For this Issue, this Court considers it apposite to first reproduce a
portion of the Supreme Court's order dated 23.08.2022 passed in
SLP(C) No.27625 of 2019, by virtue of which the present Appeal
was restored. The Apex Court observed therein:
"It reveals from the order impugned dated 13.09.2019 that the High Court has not looked into the appeal preferred at the instance of the petitioner on merits and dismissed on the premise that the petitioner had accepted a sum of Rs.13,43,016/- in terms of the award passed by the District Judge dated 26.07.2007 and since it was accepted by the petitioner without any protest, they have no right to continue with the proceedings initiated under Section 37 of the Act.
(2021) 9 SCC 1
pg. 18 It is also brought to our notice that the respondent has also filed cross objections and that too have been disposed of under the order impugned dated 13.09.2019.
With the assistance of the learned Counsel for the parties, we have looked into the money receipt dated 03.11.2007 which is on record (page 162), it nowhere indicates that it was accepted by the petitioner towards full and final settlement in terms of the award rather it is a money receipt signed by the petitioner and there is no other document filed by either party which may disclose that money has been accepted by the petitioner either under protest or for full and final settlement in terms of the award passed by the District Judge dated 26.07.2007.
After we have heard the learned Counsel for the parties, in our considered view, the judgment passed by the High Court impugned dated 13.09.2019 is not sustainable in law and deserves to be set aside."
37.As has been previously discussed by this Court in United India
Insurance Company Ltd., Bhubaneswar v. Suryo Udyog Ltd.
(supra), accepting a payment in the nature of a so-called "full and
final payment" in itself is not a bar for the Court in adjudicating
upon a dispute arising out of the quantum of such payment. It has
been held by the Supreme Court in National Insurance Company
Ltd. v. Boghara Polyfab Pvt. Ltd.18 that even in the case of
issuance of full and final discharge/settlement voucher/no-dues
certificate the arbitrator or Court can go into the question whether
(2009) 1 SCC 267 pg. 19 the liability has been satisfied or not. This decision has followed
the view taken by the Supreme Court in Chairman and Managing
Director, NTPC Ltd. v. Reshmi Constructions,
Builders and Contract19, which has also been reiterated by the
Apex Court in R.L. Kalathia & Co. v. State of Gujarat20 and
Ambica Construction v. Union of India21.
38.In the present case, however, as has been noted by the Supreme
Court itself, the money receipt dated 03.11.2007 nowhere indicates
that it was accepted by the Appellant towards full and final
settlement in terms of the award. Rather, it is merely a money
receipt signed by the Appellant without any such endorsement to
this effect. Therefore, the present Appeal can by no stretch of
imagination be liable to be dismissed on account of the present
Appellant receiving a sum of money in furtherance of the
impugned judgment and order.
VIII. ISSUE D: WHETHER THE ARBITRATOR ERRED IN LAW BY GRANTING INTEREST ON THE AWARDED AMOUNT IN THE ABSENCE OF A PROVISION IN THE CONTRACT BETWEEN THE PARTIES?
39. It is the contention of the Respondent that the learned Arbitrator
has also committed a patent illegality by granting interest at the
rate of 9% per annum when allegedly there is an express bar in the
General Conditions of Contract which governs the parties. A bare
(2004) 2 SCC 663
(2011) 2 SCC 400
(2006) 13 SCC 475
pg. 20 perusal of Clause 64.11. of the General Conditions of Contract
which refers to money claims, shows that it does not encompass
within its scope of applicability to arbitral awards which arise out
of a claim pertaining to determination, termination or non-
fulfillment of the contract. The Appellant's claim cannot be
equated to a money claim as the same arose because the Appellant
was unable to complete the contract despite his willingness and
readiness to do so. Therefore, the award of a moderate rate of
interest by the Arbitrator cannot be termed to be patently illegal.
40. Furthermore, as the conditions of the contract between the parties
is silent as to award of interest made for a claim of such an nature,
this Court may refer to the Supreme Court in Bhagwati Oxygen
Ltd. v. Hindustan Copper Ltd.22 wherein it was held that if there is
no provision in the arbitration agreement for a rate of interest,
then it is in the discretion of the Arbitral Tribunal to determine the
rate of interest to be granted based on the facts and circumstances
of the matter in hand. The learned Arbitrators further have the
power and jurisdiction to grant interest in all three stages of an
arbitration i.e. pre-reference period, pendente lite and post award
period. The learned Arbitrators are only bound by the terms of
the agreement entered into between the parties, but in cases where
the agreement is silent about the question of interest, the learned
AIR 2005 SC 2071 pg. 21 Arbitrators are required to use the test of reasonableness and
exercise their discretion in awarding interest.
IX. ISSUE E: WHETHER A CROSS OBJECTION IS MAINTAINABLE IN AN APPEAL UNDER SECTION 37 OF THE A&C ACT?
41. At the outset, it may be noted that this Court is of the opinion that
keeping the settled position of law in mind and the discussion
above, the arbitral award is not liable to be set aside on merits and
the learned District Judge's partial modification of the same is not
tenable in law.
42.However, this Court also considers it appropriate to briefly touch
upon the question of maintainability of cross objections in an
appeal under Section 37 of the Act.
43. While dealing with the previous Arbitration Act of 1940, the
Supreme Court in Municipal Corporation of Delhi and others v.
International Security and Intelligence Agency Limited23 had
inter-alia dealt with the issue of competence and maintainability of
cross objections in an appeal preferred under the Arbitration Act,
1940.
44.In this regard, the Supreme Court noted that Section 41(a) of the
Arbitration Act, 1940 provides that "the provisions of the Code of
Civil Procedure, 1908 (V of 1908), shall apply to all proceedings before
the Court, to all appeals, under Arbitration and Conciliation Act". A
(2004) 3 SCC 250
pg. 22 bare reading of Section 41(a) of the Arbitration Act, 1940 would
suggest that in all the appeals filed under Section 39 of the
Arbitration Act, 1940, the provisions of Order 41, Rule 22 of the
C.P.C. would be applicable. The Supreme Court also observed
that the right to take a cross objection is the exercise of substantive
right of appeal conferred by a statute, and the grounds of
challenge against the judgment, decree or order impugned remain
the same whether it is an appeal or a cross objection. The
difference lies in the form and manner of exercising the right.
Hence, the Supreme Court held that a cross objection can be
preferred under Section 39 of the Arbitration Act, 1940.
45. However, unlike the Arbitration Act of 1940, there is no such
provision in the present Act to prescribe that the provisions of the
C.P.C. should apply to all the proceedings before the court and to
all appeals under the Act.
46.The issue of applicability of C.P.C. in the context of
maintainability of cross objection under Section 37 of the
Arbitration and Conciliation Act, which was specifically dealt
with by the Supreme Court in the case of Mahanagar Telephone
Nigam Limited v. Applied Electronics Limited24.
47.The Apex Court while dealing with the applicability of the
provisions of C.P.C. with respect to proceedings taken under the
provisions of the Act, observed that while enacting the Act, the
(2017) 2 SCC 37 pg. 23 legislature has intentionally not carried forward any provision
pertaining to the applicability of C.P.C. While differing from the
ratio laid down in the case of Municipal Corporation of Delhi and
others v. International Security and Intelligence Agency
Limited (supra), the Supreme Court observed that the said
decision was rendered in the backdrop of the Arbitration Act,
1940, and hence, it is distinguishable. The Apex Court held that
the Arbitration and Conciliation Act, 1996 being a complete code
in itself, the applicability of C.P.C. is not to be conceived.
Accordingly, the Supreme Court held that the application of the
provisions of Order 41, Rule 22 of C.P.C., cannot be construed to
maintain a cross objection in an appeal filed under Section 37 of
the Arbitration and Conciliation Act.
48.The Supreme Court while rendering the above view, considered
its earlier decision in ITI Limited v. Siemens Public
Communications Network Limited25 wherein it has inter alia been
held that there is no express prohibition against the applicability
of C.P.C. in a proceeding arising out of the Arbitration and
Conciliation Act, hence, there cannot be any inference that C.P.C.
is not applicable in the matters related to the Arbitration and
Conciliation Act when the express exclusion of C.P.C. is not
provided for. The Supreme Court observed that the decision in ITI
Limited vs. Siemens Public Communications Network Limited
(2002) 5 SCC 510
pg. 24 (supra), though a binding precedent, appears to be incorrect, as
the scheme of the Arbitration and Conciliation Act clearly
provides otherwise and the legislative intent of the Arbitration
and Conciliation Act also postulates the same.
49.In view of such conflict with its pervious decision, the Supreme
Court observed that the views expressed in ITI Limited vs.
Siemens Public Communications Network Limited (supra)
deserves to be reconsidered by a larger Bench and the Supreme
Court continues to be in seisin of the said issue.
50.Until the date and judgment of this order, the outcome of the
reference to the larger Bench remains pending. Till then, it is
pertinent to mention, that the decision of the Supreme Court
in Mahanagar Telephone Nigam Limited s. Applied Electronics
Limited (supra) holds the field, which held that the filing of cross
objection under Section 37 of the Arbitration and Conciliation Act
is not maintainable; and that analogy cannot be drawn from the
provision of Order 41, Rule 22 of the C.P.C., as the same is not
applicable on the proceedings arising under the Arbitration and
Conciliation Act, 1996. Therefore, while even on merits the cross
objections are deemed to not hold much water, the said cross
objections as per the present position of law is also not
maintainable.
51.This Court also briefly notes that the conduct of the Respondent of
accepting and admitting their liability as per the award to the
pg. 25 extent of Rs.28,79,350/- as alleged to be evident from the deduction
of TDS is not extensively dealt with here. The counsel for the
Respondent has clarified that the said TDS certificates were
erroneous, immediately rectified with amendment of return and
the same was duly communicated to the Appellant. This Court
proposes to leave it at that.
X. CONCLUSION:
52. Therefore, in light of the discussion, keeping the settled principles
of law in mind and for the reasons given above, this Court is of the
considered view that the learned Arbitrator acted well within his
jurisdiction in awarding the appropriate relief.
53.The award of Rs.24,68,000/- including interest @ 9% per annum in
favour of the Appellant vide arbitral award dated 27.07.2005 is
upheld and reinstated in its entirety. The Respondent is directed
to make good the payment without any further delay after making
the adjustment in accordance with the amount already paid.
54.Consequently, it is observed that the present ARBA No.21 of 2007
is allowed and the arbitral award is upheld. The cross objections
are dismissed. No order as to costs.
( Dr. S.K. Panigrahi ) Judge Orissa High Court, Cuttack, Dated the 5th May,, 2023/B. Jhankar
BHABAGR Digitally signed by BHABAGRAHI AHI JHANKAR Date: 2023.05.10 JHANKAR 17:24:50 +05'30' pg. 26
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!