Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sarojkanta Mallick vs Bhubaneswar Development ...
2023 Latest Caselaw 4737 Ori

Citation : 2023 Latest Caselaw 4737 Ori
Judgement Date : 1 May, 2023

Orissa High Court
Sarojkanta Mallick vs Bhubaneswar Development ... on 1 May, 2023
         IN THE HIGH COURT OF ORISSA AT CUTTACK

                         W.P.(C). No.9850 of 2012

         In the matter of an application under Article 226 & 227 of the
         Constitution of India.
                                    -----------
         Sarojkanta Mallick                ...                Petitioner

                                         Versus

         Bhubaneswar Development Authority,
         represented through its Vice-Chairman
         & Ors.            .                   ...   Opposite Parties

             For Petitioner         ...     M/s. U.C.Mishra, A.Mishra,
                                         J.K.Mahapatra & P.K.Tripathy

             For Opposite Parties        M/s.D.Mahapatra,M.Mahapatra,
                                         G.R.Mahapatra & A.Dash.



                               JUDGMENT

PRESENT:

THE HONOURABLE JUSTICE BISWANATH RATH

Date of Hearing: 19.04.2023 Date of Judgment: 01.05.2023

Biswanath Rath, J. This writ petition involves a challenge to the

impugned order dated 17.05.2022 passed by the Allotment

Officer-1, Bhubaneswar Development Authority (for short <the

B.D.A.=) under Annexure-17 with further request to any other

// 2 //

allotment/possession of Plot No.108 of Prachi Enclave Plotted

Development Scheme in Chandrasekharpur, Bhubaneswar.

2. The writ petition was entertained on 28.05.2012 with an

interim order directing operation of the impugned order at

Annexure-17 shall be stayed till next date, which order appears

to be continuing as of now.

3. Factual background involving the case is that petitioner

while working as a Junior Assistant, came across of Kalinga

Nagar Plotted Development Scheme floated by the B.D.A. in

1991. A copy of brochure being obtained, petitioner had applied

for a plot and in the consideration process petitioner was also

allotted with Plot No.K-9-A/143 under Kalinga Nagar Plotted

Development Scheme from out of discretionary quota following

Clause-8(a)of the brochure vide Annexure-1. After allotment of

the plot in favour of the petitioner, on arrangement of a

purchaser petitioner applied for transfer of the said plot to one

Farhat Nizami and the transfer on consent of the Development

Authority was effected though a pre-possession transfer vide

office order dated 27.12.1999. The copy of the brochure and the

copy of the transfer order dated 27.12.1999 find place at

Annexures-1 and 2 respectively. It is while the matter stood

// 3 //

thus, petitioner on the premises of having no

residential/commercial plot in Bhubaneswar area came to own

Plot No.262 under District Centre Commercial Plotted

Development Scheme at Chandrasekharpur of the B.D.A. again

by way of pre possession and change of allotment from a

previous allottee vide Office Order dated 29.06.2000. Petitioner

has a clear disclosure that he is in possession of a commercial

plot being allotted by the B.D.A. from 15.09.2001 It is on the

petitioner having no residential plot in Bhubaneswar and under

the premises there is no bar in applying for a residential plot

even if in possession of a commercial plot under any of the

scheme of the Development Authority, on 29.09.2000,

petitioner applied for allotment of a residential plot under

Prachi Enclave Plotted Development Scheme at

Chandrasekharpur. The brochure hereinabove finds place at

Annexure-4 to the writ petition. It is pleaded that the brochure

had a clear clause vide paragraph-9 (A) 5 at Annexure-4

containing 2% i.e. at least 3 plots under the scheme were

reserved for the staff of B.D.A. It is for the working of the

Prachi Enclave Plotted Development Scheme lottery procedure

was adopted considering a number of applicants available even

// 4 //

under discretionary quota and the petitioner could have been

selected in the lottery process for allotment of a plot under the

scheme under the B.D.A. Staff Reservation Quota and in the

process, petitioner was served with letter of allotment vide

Letter No.336/AL/BDA, Bhubaneswar dated 09.Jan, 2001

intimating him the selection for the allotment of a plot under the

scheme indicated hereinabove. While the matter stood thus,

unanimous allegation came to be filed against the petitioner and

the matter got into investigation by the Superintendent of Police,

Vigilance, Bhubaneswar. Information being sought from the

Development Authority, the Development Authority appears to

have been supplied necessary information and relevant

documents to Vigilance for their doing the needful. There is

however pleading in paragraph-10 of the writ petition that the

Development Authority informed the Vigilance Authority

intimating that there was no bar for allotment of Commercial

plot as well as residential plot in favour of petitioner within the

Municipal area of Bhubaneswar. Through paragraph-11 of the

writ petition, it is pleaded that Vigilance Authority deemed to

have closed the proceeding. After the Vigilance proceeding

got closed, lottery process was effected and in the lottery

// 5 //

process Plot No.108 of Prchi Enclave Plotted Development

Scheme fell to the petitioner. In the meantime, depending on

the closure of Vigilance Proceeding, petitioner as well as 2 other

employees of Bhubaneswar Development Authority namely,

Mr.Ambika Prasad Mohanty and Smt.Prativa Baskey were in

entitlement of plots under staff quota. Consequently, final

allotment orders being issued, all such persons had taken

possession of the residential plot under the scheme involved.

Finding there is difficulty, petitioner brought a writ petition vide

W.P.(C).No.853 of 2008 for Development Authority not issuing

the allotment order involving Prachi Enclave Plotted

Development Scheme, Chandrasekharpur, Bhubaneswar. This

Court disposed of the matter on 07.02.2008 authorizing the

petitioner to furnish fresh representation within ten days before

the Allotment Officer of the Development Authority and the

Development Authority-opposite party no.3 therein was directed

to dispose of such representation within a month thereafter.

Following the development in the aforesaid writ petition, the

petitioner filed a representation vide Annexure-11 series. Basing

on a charge-sheet against the petitioner dated 05.12.2008,

proceeding since drawn against the petitioner, petitioner filed

// 6 //

written statement of defence involving such proceeding on

27.08.2011. There has been appointment of Inquiry Officer and

Marshalling Officer for taking up the inquiry into the charges

against the petitioner. It is brought to the notice of the Court

through the pleading at paragraph-23 of the brief that

challenging the initiation of Disciplinary Proceeding, the

petitioner brought W.P.(C).No.28898 of 2011 and this Court

entertaining the said writ petition on 03.11.2011 while issuing

notice directed the petitioner to co-operate the Inquiry Authority

in allowing continuance of the proceeding. However, there was

direction not to pass final order without leave of the Court.

In the above scenario, petitioner has been served with

cancellation of allotment order in favour of the petitioner in the

Prachi Enclave Plotted Development Scheme, Chandrasekharpur

vide Annexure-17 with clear intimation of forfeiture of

Rs.1,00,000/- for petitioner applying under falsehood. In course

of argument, Mr.Mishra, learned counsel also took this Court to

the plea taken by the petitioner in the rejoinder affidavit and also

the document appended therein.

4. In the process of hearing, Mr.Mishra, learned counsel

appearing for the petitioner took this Court to all such

// 7 //

documents referred to hereinabove further also to the order-sheet

of the Development Authority vide Annexure-10 series and

taking this Court to the observations therein, further the opinion

of the counsel thereto finds place at page- 64 of the brief

attempted to convince the Court that there is no observation

against the petitioner supporting the decision vide Annexure-17.

5. Mr.Mishra, learned counsel appearing for the petitioner

for the whole background indicated hereinabove took this

Court to the development involved herein involving initial

allotment of a plot by the B.D.A. under Kalinga Nagar Plotted

Development Scheme vide Annexure-1 and in the transfer of

plot vide Plot No.K-9-A/143 to one Farhat Nizami, claiming to

be transfer of such land at pre-possession stage further on the

subsequent allotment of Plot No.262 to be a commercial plot

under District Centre Commercial Plotted development Scheme

at Chandrasekharpur by B.D.A contended that there was rightful

allotment completely in terms of the conditions in the scheme.

Then taking this Court to the cancellation of allotment involved

herein, a residential plot under staff quota in Prachi Enclave

Plotted Development Scheme videAnnexure-4 and taking again

this Court to the brochure condition, Mr.Mishra, learned

// 8 //

counsel attempted to submit that for there is no restriction in the

entitlement of a plot by an employee even in the entitlement of a

commercial plot from the same Development Authority,

claimed there was lawful application and there has been illegal

rejection of the allotment vide Annexure-17. Taking this Court

to the brochure condition at Annexure-1, Annexure-25 at page-

13 of the rejoinder affidavit and the brochure at Annexure-4,

reading through the same Mr.Mishra, learned counsel attempted

to satisfy the Court that there was no restriction at all either in

the scope for applying by the petitioner under Annexure-4 or

taking a decision involving the allotment of land involving the

land in Annexure-4. Mr.Mishra, learned counsel thus contended

that there has been illegal and arbitrary exercise of power by the

Development Authority in taking out a vested right by passing

the illegal impugned order at Annexure-17 and claimed such

order ought to be interfered and set aside. It is based on such

request, Mr.Mishra, learned counsel for the petitioner took this

Court to the decision of this Court in W.P.(C).No.5274 of 2022

and thus requests this Court upon setting aside of the order at

Annexure-17 there should be direction to the Development

// 9 //

Authority in the minimum handing over of the plot involved to

the petitioner and allowing regularization.

6. Mr.Mahapatra, learned counsel appearing for the

Development Authority taking this Court to the preliminary

counter averments even though did not dispute that there exists

pre-allotment in favour of the petitioner under the guise of same

Development Authority, first one being a transfer of the land in

pre-allotment stage undisputedly in the involvement of the

petitioner and second one being a commercial allotment of plot

in favour of the petitioner and third one under the discretionary

quota of the Development Authority in terms of conditions in

Annexure-4, however, taking this Court to the counter pleading

contended that for the condition in the brochure vide Annexure-

4 having a discretionary quota in the allotment of residential

plot in favour of the employees to the extent 2% of the actual

availability but such a relaxation should not be considered to

enter into multiple allotment keeping in view the petitioner was

already in allotment of two plots though one of it involved in a

transfer at pre-possession stage. Apart from the plea taken in

the counter affidavit, Mr.Mahapatra, learned counsel for the

Development Authority also took this Court to the judgment of

// 10 //

this court in O.J.C.No.5485 of 1993 and taking this Court to the

decision of Division Bench through paragraph-27 therein

contended that the Division Bench of this Court relying on a

decision of the Hon9ble Supreme Court in 1995 Supp.(3) SCC

382 has already put a cap in the use of discretionary quota

which is binding on the parties. In the above circumstance,

Mr.Mahapatra, learned counsel attempted to satisfy that the

impugned order at Annexure-17 requires no interference.

7. Considering the rival contentions of the parties, this Court

finds there is no factual dispute to the following:

In the first stage, petitioner was an applicant for the

Kalinga Nagar Plotted Development Scheme vide Annexure-1,

page-24 of the brief. Undisputedly, petitioner remained one of

the allottee in the said scheme. It is in the allotment stage,

petitioner approached the Development Authority showing

intention by 3rd party to take possession of such land and able

to obtain transfer of possession of such land in favour of 3rd

party though pre-delivery of possession in favour of such party.

It is needless to mention here that this allotment in favour of

the petitioner remain under discretionary quota. In the second

stage, petitioner was an applicant for a commercial plot under

// 11 //

the District Central Commercial Plotted Development Scheme at

Chandrasekharpur again by Bhubaneswar Development

Authority vide brochure at Annexure-25. In the consideration

process, it appears petitioner is in entitlement of a commercial

plot bearing Plot No.262 in District Center Commercial Plotted

Scheme at Chandrasekharpur. Undisputedly, petitioner being an

employee of the Development Authority is already in possession

of Plot No.262 in the aforesaid Development Scheme at the

instance of the B.D.A. In the third stage, petitioner applied for

a residential plot under discretionary quota/staff quota in the

Prachi Enclave Plotted Development Scheme vide brochure at

Annexure-4 and also remained successful in the allotment of

Plot No.108 in Prachi Enclave Plotted Development Scheme.

There also remained an undisputed fact that considering the

second allotment, there involved Vigilance Inquiry but such

inquiry has been dropped finding there was no cap in the

entitlement of the petitioner in the brochure involved therein.

Undisputedly, there has been also writ petition brought to this

Court vide W.P.(C).No.853 of 2008 as well as W.P.(C).No.

9850 of 2012. There is no disclosure by either side as to the

ultimate decision in the second writ petition.

// 12 //

8. This Court records the submission of Mr.Mahapatra,

learned counsel that in a proceeding on acquisition of property

disproportionate to the income of the petitioner, the petitioner

has already been convicted by criminal Court and as an

outcome, he has already been dismissed from service.

9. This Court from Annexure-4 finds in the Prachi Enclave

Plotted Development Scheme floated by B.D.A., the

Development Authority put a clear condition vide paragraph-9

(A) 5 reserving 2% of the plots available i.e. at least in the

minimum 3 plots under the scheme reserved for staffs of B.D.A..

This Court since finds petitioner is an employee under the

B.D.A. and is unable to appreciate the scope for allotment of

commercial plot in favour of the employee of the very same

Authority. This Court thus is of the view that there should not

be any such allotment in favour of any employee even there

should not have been any allotment in favor of even near and

dear relation of such employee. This Court finds strange in

bringing such brochure and hopes and expects all Development

Authorities in the State hereafter shall remain careful in having

no such relaxation for their employees at least.

// 13 //

10. Undisputedly the petitioner was an allottee in respect of

Plot No.K-9-A/143 under Kalinga Nagar Plotted Development

Scheme under discretionary quota applying Clause-8(a) of the

brochure at Annexure-1. There is however development to the

extent after the allotment but before delivery of possession on

an application of the petitioner for a 3rd party transfer, the

transfer was effected vide Office Order dated 27.12.1999. In

course of hearing, learned counsel for the Development

Authority brought to the notice of the Court that once there is

allotment in favour of the petitioner applying discretionary quota

and on the request of the petitioner, there involved a transfer of

such land and take out the petitioner from the cap of party in the

entitlement of a plot under discretionary quota. This Court here

takes into account the rival contentions of the parties and finds

the petitioner is already a definite beneficiary involving

discretionary quota on account of allotment under discretionary

quota and for the sale/transfer involved therein, petitioner must

have gained financially. This Court takes into account the

general picture prevailing in the State and records there are

lackhs of people even applying not getting even a single plot

and since the petitioner is already in benefit of a allotment, it is

// 14 //

only on his application, the allotment was transferred in favour

of 3rd party, there should not have been applying of

discretionary quota particularly involving the petitioner. This

Court finds considering petitioner to be entitlement in another

plot will be jeopardizing the interest of persons , who are yet to

get a single plot. This Court here also takes into account a

Division Bench decision of this Court vide judgment dated

09.04.2002 passed in O.J.C.No.5485 of 1993 in the case of

Jadunath Panda Vs. Bhubaneswar Development Authority &

Ors. In paragraph-27 therein, the Division Bench of this Court

held as follows:

<27. Thus, to sum up, it is to be held that reservation of plots/houses for categories like Green Card Holders, Scheduled Caste, Scheduled Tribe and the like and for staff of Development Authorities, is not permissible in law. However, reservation of some plots/houses for defence personnel and retiring/retired Government servants and reservation of some plots/houses for allotment under the discretionary quota has to be strictly in accordance with the principles and guidelines framed for the purpose in the light of the judgments of the Apex Court in V.Purushottam Rao9s case (supra) and Centre For Public Interest Litigation v. Union of India and others, 1995 supp.(3) S.C.C. 382. In the case at hand, even though we have found that reservation in respect of certain categories are impermissible in law, in view of long lapse of time, since the allotments have been made and possession delivered, it will not be just and proper at this stage to interfere with the said allotments.=

11. Coming to the petitioner9s claim on the basis of

observation in the order-sheet of the Corporation at Annexure-

10 series and the information of the employees placed therein at

page 64 of the brief, this Court finds there is no issue in

// 15 //

supplying all materials vide Anenxure-10 but it is unable to

appreciate in supplying of opinion of the counsel to the parties

under exercise of Right to Information Act. Considering such

document should not have been supplied to 3rd party, as opinion

of counsel remain as a privilege document.

12. It is keeping in view the view rendered by this Court

recorded hereinabove and the decision of the Division Bench,

this Court finds there is no hesitation on the part of this Court in

declining to interfere in the cancellation of allotment vide

Annexure-17 impugned herein. However, considering the

petitioner was a bonafide applicant and the Development

Authority remaining not careful in putting restriction denying

application from the earlier allottees through any development

scheme of the Development Authority, the application of the

petitioner should be construed to be a bonafide application and

there should not be forfeiture of the amount, if any, deposited

by the petitioner. This Court here also records the clear

statement and pleading in the writ petition that the petitioner is

also in the entitlement of a commercial plot in the same

township again under a development scheme of the B.D.A.

project. Thus, this Court while declining to interfere in the

// 16 //

impugned order at Annexure-17, however finding petitioner was

a bonafide applicant though legally not entitled to any further

allotment, deposit, if any made by the petitioner, is still lying in

the end of the Development Authority, the same should be

refunded to the petitioner along with interest at least @ 6% all

through. Entitlement should be calculated within a period of

three weeks of the receipt of copy of the order and refund should

also be achieved within one week of such assessment.

13. Before parting with the case, this Court likes to put an

observation for future caring in the allotment of land by

Development Authority involved herein to at least put a 8cap9/

<restriction= on applicant by the party already in receipt of land

from the Development Authority under any of its Development

Scheme operated in city or under any other development

scheme in the city and even in any other development scheme

of any other district at least to make it available to all bonafide

citizen instead of allotting multiple land in favour of particular

individuals, who are already in entitlement of a land by such

agencies may in any of the district.

14. The writ petition stands dismissed but however with the

// 17 //

further direction hereinabove. There is however no order as to

cost.

15. Copy of this judgment be sent to the Advocate General

Office, Secretary, Housing & Urban Development Department

to remain careful in the issuing of the future brochures of any

Development Authority in the State of Odisha at least taking

care of the observation in the matter of restriction indicated in

paragraph-13 hereinabove.

(Biswanath Rath) Judge

Orissa High Court, Cuttack.

                    Dated the 1st day of May ,2023/SKS




              Digitally signed by
SUSIL KUMAR SUSIL KUMAR SWAIN
SWAIN       Date: 2023.05.01
            16:26:50 +05'30'





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter