Citation : 2023 Latest Caselaw 7816 Ori
Judgement Date : 20 July, 2023
IN THE HIGH COURT OF ORISSA AT CUTTACK
W.P.(C) No.8090 of 2019
Bhushan Power and Steel Ltd. .... Petitioner
-versus-
Director of Industries-Cum- .... Opposite Parties
Chairman, Micro and Small
Enterprises Facilitation Council,
Buxi Bazar, Cuttack and another
Learned advocates appeared in this case:
For petitioner : Mr. Sanjit Mohanty, Senior Advocate
For opposite parties : Mr. A. K. Sharma, Advocate (AGA)
(for opposite party no.1)
Mr. S. S. Das, Senior Advocate
(for opposite party no.2)
CORAM: JUSTICE ARINDAM SINHA
---------------------------------------------------------------------------------------
Dates of hearing : 21.03.2023, 03.04.2023 and 28.06.2023 Date of judgment : 20.07.2023
---------------------------------------------------------------------------------------
1. Mr. Mohanty, learned senior advocate appears on behalf of
petitioner and Mr. Das, learned senior advocate, for opposite party
no.2, the two contesting parties in this writ petition. Mr. Sharma,
learned advocate, Additional Government Advocate appears on behalf
// 2 //
of opposite party no.1. Contesting parties earlier appeared and were
heard.
2. Submission made on behalf of petitioner was, impugned is
award dated 20th February, 2019 made by Micro and Small Enterprises
Facilitation Council (opposite party no.1) under sub-section (3) in
section 18 of Micro, Small and Medium Enterprises Development Act,
2006. Opposite party no.2 was operational creditor. There was
proceeding under Insolvency and Bankruptcy Code, 2016. In the
period of moratorium said opposite party moved the Council. He could
not have done so. Moreover, on the Authority having approved the
resolution plan, payment in accordance with the scheme was made by
the successful resolution applicant. Successful resolution applicant is
behind petitioner. In the circumstances, said opposite party had and is
deemed to have had execution, satisfaction and discharge of its claim
against petitioner. This was overlooked in the award. As such, the
illegality and material irregularity appear on face of impugned award
since the facts stood referred therein.
3. Petitioner rendered demonstration that opposite party no.2,
being supplier to petitioner-company, was operational creditor and its
position considered in the resolution plan approved by the National
// 3 //
Company Law Tribunal (NCLT), on its judgment dated 5th September,
2019. Further demonstration was, pursuant to said judgment opposite
party no.2, on his claim taken at Rs.26,79,70,808.27/- the resolution
plan had provided for Rs.22,01,84,363/-. Consequently, Rs.47.70% of
the accepted amount at Rs.10,50,27,941/- was paid to said opposite
party. The payment was made on 24th March, 2022 evidenced by Unit
Transaction Reference (UTR) no. SBIN 422083896125. Said judgment
has become final on there being no challenge mounted against it. The
supplier having had been paid the money in terms of the resolution
plan, there was no relevance of any dispute to be referred under the Act
of 2006. Hence, impugned award is required to be interfered with on
judicial review as opposite party no.2 had participated in the resolution
process and accepted payment thereunder. Reliance was placed on
sections 31, 60(5) and 238 in the Code.
4. Further submission on behalf of petitioner was with regard to
requirement under section 19 in the 2006 Act, on pre-deposit. Reliance
was on judgments of the Supreme Court, firstly in L. Chandra Kumar
v. Union of India, reported in AIR 1997 SC 1125, paragraphs 78 and
79 for declaration of law that judicial superintendence over decisions
of all Courts and Tribunals within respective jurisdictions of the High
// 4 //
Courts is also part of basic structure of the Constitution and can never
be ousted or excluded by operation of statute, enacted by the
Parliament. Further reliance was on Whirlpool Corporation vs.
Registrar of Trade Marks, Mumbai, reported in AIR 1999 SC 22,
paragraphs 14 and 15 for submission that challenge in the writ petition
squarely fell under the third contingency stated in paragraph 15, on the
order or proceeding under the Act of 2006 being wholly without
jurisdiction.
5. On behalf of opposite party no.2 submission was on reliance
of judgment dated 8th October, 2021 of the Supreme Court in Civil
Appeal no.6252 of 2021 (Gujarat State Disaster Management
Authority V. M/s. Aska Equipments Ltd.), paragraphs 9, 10 and 11
for contention that mandate of section 19 in the 2006 Act, regarding
pre-deposit, had to be complied with for seeking setting aside of any
decree, award or other order made, inter alia, by the Council.
6. Further submission on behalf of opposite party no.2 was, on
the one hand there was non-acceptance by the resolution plan or
confusion regarding said opposite party's claim and on the other,
pursuant to expiry of 180 days from date of admission of the
insolvency resolution process, there was no extension order. As such,
// 5 //
the moratorium ceased to exist. For purpose of quantification, opposite
party no.2, at that time moved the Council under the Act of 2006.
There can be no question arisen on the quantification thereafter made
by the Council.
7. Today, Mr. Das draws attention to the reply filed by petitioner
in the company petition before the NCLT. Paragraph 7 therefrom is
reproduced below.
"The Answering Respondent while dealing with the Applicant's claim considered the contract of service (i.e. work order) as well as the invoices submitted, both referred to the principal amount and not to the interest amount as claimed by the Applicant. Further, there is not even any court or tribunal's order awarding any interest in favour of the Applicant to justify its claim."
(emphasis supplied)
Mr. Das submits, this was the confusion created by petitioner, which is
why his client moved the Council. The premise was that principal
claim stood admitted but the interest was disputed. It needed
quantification on adjudication by appropriate authority, as was alleged
to be an omission. He draws attention to impugned award to
demonstrate that accordingly, the Council proceeding on the basis of
admission of the principal claim, had found interest to also be due to
// 6 //
his client. Interest of Rs.17,76,03,939.39 up to 26th July, 2017 is
payable under sections 15 and 16 under the Act of 2006. The Council
upon verifying the records found that claim of his client is genuine.
Hence, there was award. He concedes that direction for payment in
impugned award ought not to have been made. However, the
quantification on having been made, was not taken into account in
considering the claim of his client in the matter of approval of the
resolution plan. In the circumstances, impugned award was duly made
and should not to be interfered with.
8. He relies on judgments of the Supreme Court:-
i) Swiss Ribbons P. Ltd. vs. Union of India, reported in (2019)
213 Company Cases 198 (SC), placitums 10 and 11. He submits,
extracted was the preamble in the Code of 2016. The interpretation, the
moratorium was for protection of assets of the corporate debtor.
Initiation of the proceeding before the Council pursuant to confusion
sought to be created by petitioner regarding omission of quantification
of interest was not an action directed at alienating or encumbering any
asset of petitioner.
// 7 //
ii) P. Mohanraj. Vs. Shah Brothers Ispat (P) Ltd., reported in
(2021) 6 SCC 258, paragraph 29 for same view taken by the same
learned Judge, who authored Swiss Ribbons (supra).
9. In reply Mr. Mohanty relies on judgment of the Supreme
Court in Ghanashyam Mishra and Sons Private Limited v.
Edelweiss Asset Reconstruction Company Limited, reported in
(2021) 9 SCC 657, paragraphs 61 and 62 (Manupatra print). He
submits, interpretation of the Supreme Court was that legislative intent
of making the resolution plan binding on all stakeholders, after it gets
the seal of approval from the Adjudicating Authority upon its
satisfaction it was approved by the Committee of Creditors (CoC),
meets the requirement as referred in sub-section (2) of section 30. After
approval of the plan, no surprise claims should be flung on the
successful resolution applicant. The purported adjudication and
impugned award made in violation of the moratorium puts forth
something that was not contemplated in the resolution plan, approved
by the Adjudicating Authority.
10. With reference to section 12 in the Code of 2016 he submits
that initially mandated period for completion of insolvency resolution
process was 180 days. The time could be extended as provided
// 8 //
thereunder for period not exceeding 90 days and the extension could
only be granted once. However, there was amendment to the section by
Act 26 of 2019, with effect from 16th August, 2019. Two provisos were
inserted by the amendment. He relies on the second proviso. It is
reproduced below.
"Provided also that where the insolvency resolution process of a corporate debtor is pending and has not been completed within the period referred to in the second proviso, such resolution process shall be completed within a period of ninety days from the date of commencement of the Insolvency and Bankruptcy Code (Amendment) Act, 2019."
He submits, time for completing the insolvency resolution process
stood extended by amended proviso, till 90 days after 16th August,
2019. The resolution plan stood approved on 5th of September, 2019,
well before expiry of the extended time by amendment. In the
circumstances, the moratorium operated during pendency of the
insolvency resolution process, as provided in section 14. Proviso under
sub-section (4), in facts of this case, operates for the moratorium to
have ended on 5th September, 2019. As such, institution of the
proceeding on moving the Council was clearly barred by the
moratorium and hence, the Council having entered upon the reference
// 9 //
to go on to pass impugned award, did so without jurisdiction. Mr. Das
submits, impugned award was made much before the coming into
effect of the amendment on 16th August, 2019.
11. Facts of the case emerging from pleadings and argument put
forth by the contesting parties are not in dispute. Those essential for the
adjudication are that there was initiated insolvency resolution process
in respect of petitioner-company. Opposite party no.2 being supplier
participated in the process on coming to know of it. He filed claims,
both on account of principal and interest. In the resolution process,
cognizance was taken only of the claim on principal. During pendency
of the resolution process the supplier invoked provisions in section
60(5) of the Code. The sub-section is reproduced below.
"60(5). Notwithstanding anything to the contrary contained in any other law for the time being in force, the National Company Law Tribunal shall have jurisdiction to entertain or dispose of-
(a) any application or proceeding by or against the corporate debtor or corporate person;
(b) any claim made by or against the corporate debtor or corporate person, including claims by or against any of its subsidiaries situated in India; and
(c) any question of priorities or any question of law or facts, arising out of or in relation to the insolvency resolution or liquidation proceedings of
// 10 //
the corporate debtor or corporate person under this Code. "
(emphasis supplied)
Contesting parties did not bring to notice of Court, order made
disposing of said application. However, submission was made on
behalf of petitioner that approval of the resolution plan by the NCLT
put paid to all objections as might have been raised during pendency of
the insolvency resolution process. The omission need not detain the
adjudication since, declaration of law by the Supreme Court in
Edelweiss (supra) is clear, on binding nature of the resolution plan
upon approval thereof duly made. It is undisputed that opposite party
no.2 was an operational creditor, who participated in the resolution
process culminating in the duly approved resolution plan. Furthermore,
Court accepts contention of petitioner that the moratorium commenced
and ran till 5th September, 2019, when the resolution plan stood
approved. In the circumstances, the Council entered into the reference
during subsistence of the moratorium.
12. Perusal of impugned award reveals record in it that on behalf
of petitioner, subsistence of the moratorium was brought to notice of
the Council. Impugned award thereafter is silent regarding
consideration of the contention. It proceeds straightway to give finding
// 11 //
on admitted principal claim and genuineness of consequent claim of
interest, claimed under sections 15 and 16 in the Act of 2006. The
omission by the Council to deal with this contention points to non-
application of mind at the first instance and an implication that it could
not be dealt with. In the circumstances, the supplier's anxiety in being
unable to recover on his claim for interest cannot stand in the way of
impugned award being set aside on judicial review.
13. The requirement of pre-deposit is mandated by section 19 in
the Act of 2006. It is a statutory requirement. Section 18, in providing
for arbitration on thereby made applicable provisions in Arbitration
and Conciliation Act, 1996, was resorted to by the Council, resulting in
impugned award. Statutory remedy is for challenge of the award under
section 34 in the Act of 1996. By operation of section 19 in the Act of
2006, the requirement for pre-deposit overrides provisions in section
36 of the 1996 Act. Having said so, challenge in successfully moving
the constitutional writ Court stands on a separate footing and is
maintainable in spite of availability of alternative statutory remedy.
Mandate of statute cannot impede exercise of constitutional writ
jurisdiction. The contention of opposite party no.2 on pre-deposit is not
well founded.
// 12 //
14 . For reasons aforesaid impugned award is set aside and
quashed. Mr. Mohanty submits, his client has filed interim application
for quashing the execution case launched by opposite party no.2,
pursuant to impugned award, set aside herein. Petitioner has liberty to
produce this order before the executing Court and accordingly pray.
15. The writ petition is disposed of.
(Arindam Sinha) Judge
Prasant
Signature Not Verified Digitally Signed Signed by: PRASANT KUMAR SAHOO Reason: Authentication Location: OHC Date: 24-Jul-2023 17:26:58
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!