Citation : 2022 Latest Caselaw 5735 Ori
Judgement Date : 19 October, 2022
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBA No.4 Of 2021
(Through hybrid mode)
Jindal India Thermal Power Ltd. .... Appellant
Mr. C. Mukhopadhya, Senior Advocate
Mr. S.P.Mishra, Senior Advocate
Mr. Satyajit Mohanty, Advocate
Mr. Prashant Mehta, Advocate
Mr. Asit Kumar Dash, Advocate
Ms. Divita Vyas, Advocate
-versus-
Quartz Infra and Engineering Pvt. .... Respondent
Ltd.
Mr. Vegesna Subba Raju, in person
CORAM: JUSTICE ARINDAM SINHA
ORDER
19.10.2022 Order No.
21. 1. Mr. Mukhopadhya, learned senior advocate appears on behalf
of appellant and resumes his argument. In fairness he submits, there
was view taken by a learned Single Judge of Bombay High Court in
National Highways Authority of India v. Additional Commissioner
available at 2022 SCC OnLine Bom 1688. He submits, paragraphs 16
to 18, 22 and 23 in the judgment would show that though judgment of
the Supreme Court in NHAI v. M. Hakeem reported in (2021) 9 SCC
1 was considered but the view was rendered on reliance of a Full
Bench judgment of that Court in R.S. Jiwani v. Ircon International
// 2 //
Ltd. reported in (2010) 1 Mah LJ 547. He then relies on judgment of
the Supreme Court in National Highways Authority of India v. P.
Nagaraju available at 2022 SCC OnLine SC 864 paragraphs 29 and
43 to submit, said Court reiterated that there could not be modification
of the award and in the case held, appropriate course to be adopted
was to set aside the award and remit the matter to the Tribunal.
2. Drawing attention to paragraph-943 in the award he
demonstrates the tabulation to be under three heads of total awarded
amount, pendent lite interest and arbitration costs. He submits, in
event Court finds substance in his submissions regarding, inter alia,
termination of contract and erroneous rejection of the application
under section 27, Arbitration and Conciliation Act, 1996, it would
cause reduction in the total awarded amount, with consequent effect
on pendent lite interest as well as arbitration costs, provided for under
sections 31(8) and 31-A. Same would require modification of the
award, impermissible in law.
3. He then draws attention to paragraphs 905, 921 to 925
regarding his client's counter claim no.2 and paragraphs 926 to 930 on
counter claim no.3. On query from Court he submits, wrongful
termination of contract was not given as reason for rejecting either of
the counter claims. In paragraph-930 the Tribunal said it had arrived at
// 3 //
finding of fact that respondent (claimant) had not abandoned the
contract. He submits further, while rejecting counter claim no.2 the
Tribunal also said there is nothing to show that the subsequent contract
with Sinhotia Metal Works Ltd. was identical in nature, whereas in
paragraph-826, said subsequent contract was considered for
adjudication of respondent's claim for loss of profit on termination.
4. He then draws attention to print of electronic mail dated 2nd
February, 2013. He submits, this was construed by the Tribunal to be
the termination. Respondent thereafter attended meeting between
itself, subsequent contractor and his client. He demonstrates from
minutes dated 6th February, 2013, serial nos.1 and 2 that respondent
expressed unwillingness to complete works in other areas as work on
raw water reservoir and ash dyke had been offloaded. There was
agreement under serial no.7 for joint measurement.
5. On query from Court he refers to letter dated 19th February,
2013 of respondent, as its response with reference to his client's said
electronic mail dated 2nd February, 2013. In this regard Court requires
assistance by a list of dates, giving dates of the contracts, their original
periods for completion and the disputed termination with relevant
correspondence, upto notice for commencement of arbitral proceeding.
// 4 //
6. On further query from Court Mr. Mukhopadhya submits, there
was no other termination in respect of contracts for works other than
construction of raw water reservoir and ash dyke. Loss of profit was
awarded on calculation of aggregate value of all contracts.
7. List on 26th October, 2022 marked at 2.00 p.m.
(Arindam Sinha) Judge Sks
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!