Citation : 2022 Latest Caselaw 2425 Ori
Judgement Date : 5 May, 2022
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBA No.40 of 2014
(Through hybrid mode)
Steel Authority of India Limited .... Appellants
and another
Mr. N.K.Sahu, Advocate
-versus-
M/S. G.C. Kanungo Construction .... Respondent
(P) Ltd., Cuttack.
Mr. M. Kanungo, Senior Advocate.
CORAM: JUSTICE ARINDAM SINHA
ORDER
05.05.2022
Order No.
22. 1. Steel Authority of India Limited (SAIL) has preferred appeal against order dated 17th May, 2014 made by the Court below, rejecting its challenge to award dated 8th August, 2012.
2. Mr. Sahu, learned advocate appears on behalf of appellant and was heard on 29th March, 2022. He had submitted, parties had agreed, inter alia, after his client filed counter/written statement, respondent (claimant) would have opportunity to file rejoinder to the counter and counter claim, if any. The agreed procedure was recorded by the tribunal on order dated 9th May, 2008. In breach of this procedure, respondent was allowed to file additional rejoinder, disclosing disputed documents, allegedly sent to his client under certificate of posting.
3. He drew attention to paragraph 17 in the award to demonstrate
// 2 //
that additional rejoinder was accepted from claimant. From paragraph
20 he pointed out that the documents disclosed in the additional
rejoinder were marked exhibits C-20, 22, 25 to 28, 33 to 39, 41 to 44
and 47 to 51. Claimant had claimed these documents to have been
dispatched under certificate of posting. His client never received those
documents. In the circumstances, reliance on those documents, for
purpose of making the award, was in violation of provisions in
sections 19 and 28 in Arbitration and Conciliation Act, 1996.
4. Claimant had, in compliance with requirement under the
contract, furnished bank guarantee. His client duly invoked the bank
guarantee. The tribunal travelled beyond scope of the contract to rule
on the invocation and consequently award claimant in respect thereof.
5. The tribunal also travelled beyond four corners of the contract
in awarding Rs.25,000/- as transportation cost for every school site,
there being 90 such sites. This could not be done since clause 4 in
Additional Special Conditions (exhibit R-10) specifically included
transportation in scope of the work. He had submitted, by reason of
above, the award was liable to have been set aside in the challenge.
The Court below erred in not appreciating the challenge.
6. He referred to paragraph 24 in the award, which deals with
// 3 //
whether his client was entitled to recover cost of material and interest.
He submitted, there was a cost and interest component, outstanding
from respondent on account of supply of steel. The tribunal committed
illegality in rejecting the counter claim. On query from Court he
submitted, the supply was made on request of respondent and not as an
obligation under the contract.
7. He then drew attention to clause (iii) under paragraph 30 in the
award. He submitted, there was award of Rs.2000/- per school,
aggregating Rs.1,00,000/-, said to be payable due to use of potable
water. Referring to clause 8 in the Letter of Intent dated 24th April,
2000 (Ext. R-10), he demonstrated that, inter alia, water was to be
arranged by the contractor, at its cost.
8. Moving on to clause (iv) under the paragraph he submitted,
extra transportation cost including lifts and leads were awarded at Rs.
31,50,000/-. There was clear mention under clause 4 in Additional
Special Conditions (Ext. R-10) that all leads, lifts, transportation were
included in the scope of work.
9. With reference to clause (x) under the paragraph he submitted,
compensation could not have been awarded. There was arbitrary
award of Rs.1000/- for each completed school, 86 in number. The
// 4 //
contract did not provide for payment of compensation and the
arbitrator could not have awarded. Furthermore, there was award of
Rs.8,95,000/-, also arbitrarily made at the rate of Rs.10,000/- per
school for 60 schools that were taken out of the scope of work,
Rs.15,000/- for 13 schools and Rs.20,000/- for 5 schools. He
submitted, claimant/respondent itself pleaded for reducing scope of the
work. Hence, from total number of schools in original scope of work,
some schools were taken out. Compensation for pilferage or stealing
or whatever could not have been awarded as not provided in the
contract. The arbitrator travelled beyond four corners of the contract.
There should be interference.
10. He relied on several judgments of the Supreme Court.
(i) State of Chhatisgarh vs. Sal Udyog Pvt. Ltd. reported in
(2022) 2 SCC 275, paragraph 26.
ii) MMTC Ltd. vs. M/S.Vedanta Ltd., reported in (2019) 4 SCC
163, paragraphs 10 to 12, wherein earlier judgments of the Court in
Associate Builders vs. BDA, ONGC Ltd. vs. Saw Pipes Ltd. etc.
were referred for well settled law that Court does not sit in appeal over
the arbitral award and may interfere on merits on limited grounds
provided under section 34, Arbitration and Conciliation Act, 1996.
// 5 //
iii) Food Corporation of India vs M/S.Chandu Construction,
reported in (2007) 4 SCC 697, paragraphs 11 to 13. He submitted, this
judgment too was rendered under the Act of 1940, on jurisdictional
error committed by the arbitrator in travelling beyond four corners of
the contract.
iv) Maharashtra vs. Rashid Babu Bhai Mulani, reported in
AIR 2006 SC 825, paragraph 14. The Supreme Court, in the
paragraph said, regarding postal dispatch under certificate of posting
and the ease, with which such certificate can be procured by affixing
ante dated seal with the connivance of any employee of the post office,
was a matter of concern. He reiterated, the tribunal relied on
documents introduced by additional rejoinder. Those were copies of
letters allegedly sent to his client under certificate of posting.
v) Steel Authority of India Ltd. Vs. J.C. Budharaja, reported in
(1999) 8 SCC 122. He submitted, this judgment was rendered in
adjudication under Arbitration Act, 1940 but the principle of law
applies. The Court found that the award was passed in disregard of
express terms of the contract and therefore was arbitrary, capricious
and without jurisdiction, as in the case here.
11. Mr. Kanungo, learned senior advocate appears on behalf of
// 6 //
respondent and submits, the arbitrator decided in terms of the contract.
He draws attention to paragraph 17 in the award to submit with
reference thereto, that on 25th April, 2009 appellant had filed a memo
of admission and denial, which was inclusive of documents annexed to
the additional rejoinder. In paragraph 18, the tribunal said that some of
the documents annexed to the additional rejoinder were admitted by
said memo dated 25th April, 2009 and on some others, his client's
witness was extensively cross-examined. On yet some other
documents, absolutely no question was raised, either during the
examination or in personal hearing. In this background, the tribunal
had dealt with the additional rejoinder as part of pleadings of his client
and the disclosures therein, as was tendered in evidence. On query
from Court he hands up procedural order no.3 dated 9th May, 2008,
wherein was recorded procedure regarding, inter alia, pleadings to be
filed by the parties.
12. On invocation of bank guarantee and adjudication in respect
thereof he submits, two bank guarantees were furnished. One was in
respect of security deposit. It was refunded. The other bank guarantee
was for Rs.53,48,028/-. He draws attention to paragraph 32 in the
award to show that the arbitrator had found that the bank guarantee
// 7 //
had been furnished in respect of the mobilization advance, being 10%
of contract value. The tribunal went on to find that major part of the
mobilization advance was recovered from running bills leaving
balance of Rs.17,08,339/-. The bank guarantee, having had been
furnished as security for recovery of mobilization advance, therefore,
the tribunal found that recovery in excess of Rs.17,08,399/- could not
be sustained and awarded Rs.36,39,629/- on that account.
13. Moving on to appellant's contention regarding award of
Rs.25,000/- each for 90 sites as made beyond four corners of the
contract. He draws attention to clauses (iv), (v) and (vi) in paragraph
30 of the award. He points out that the tribunal referred to, inter alia,
letter dated 27th November, 2000 of SAIL (Ext. C-11). For the context
he relies on a paragraph in the letter, extracted and reproduced below.
"You will be pleased to know that an additional amount of Rs.15,000/- per School is being considered for payment to you for construction in locations identified under 'Difficult approach'."
14. He submits, it is true that Additional Special Conditions clause-
4 said, inter alia, all leads, lifts transportation are included in the scope
of work but there was this enhancement granted by appellant itself, in
consideration of difficult approach to identified construction locations.
// 8 //
The tribunal enhanced this additional amount to Rs.35,000/- for the 90
schools constructed by his client. He submits, there should not be
scrutiny by a magnifying glass regarding the reason or reasonableness.
He relies on judgment dated 18th January, 2022 in Civil Appeal
no.1533 of 2017 (Atlanta Limited Vs. Union of India), paragraphs
10, 12 and 21 in Manupatra print. Paragraph 21 is quoted below.
"21. In the instant case, having gone through the Award, we find that the learned Sole Arbitrator was lucid in his reasoning for taking a particular view on the interpretation of the terms and conditions of the contract between the parties. It was for this very reason that the learned Single Judge had forbore from interfering with the arbitral Award and dismissed the petition filed by the respondent-Union of India under Sections 30 and 33 of the 1940 Act. By going into the minute details of the evidence led before the learned Sole Arbitrator with a magnifying glass and the findings returned thereon, the Appellate Court has clearly transgressed the limitations placed on it. In any case, we are of the opinion that the reasons offered for taking such a view, are neither justified nor called for interfering with the arbitral Award. "
15. He reiterates his submissions recorded in last preceding
paragraph as also made with regard to award of aggregate
Rs.1,00,000/- for potable water and compensation of Rs.10,000/- for
each completed school at aggregate Rs.8,60,000/-. He submits further,
part of appellants counter claim was awarded and by paragraph 24 in
the award the tribunal was justified in rejecting the other counter claim
// 9 //
regarding cost and interest component on account of supply of steel.
16. On the judgments relied upon by appellant Mr. Kanungo
submits, he has no quarrel with the propositions of law declared
therein. He reiterates reliance on Atlanta Limited (supra) and
submits, even though, it is a judgment in respect of challenge to an
award made under the 1940 Act, the principles declared are applicable.
17. Mr. Sahu in reply reiterates reliance on the judgments already
cited by him and in particular on State of Chhattisgarh (supra),
paragraph 26, from where following passage is extracted and
reproduced below.
"... We are, therefore, of the view that failure on the part of the learned Sole Arbitrator to decide in accordance with the terms of the contract governing the parties, would certainly attract the "patent illegality ground", as the said oversight amounts to gross contravention of Section 28(3) of the 1996 Act, that enjoins the Arbitral Tribunal to take into account the terms of the contract while making an Award. The said 'patent illegality' is not only apparent on the face of the Award, it goes to the very root of the matter and deserves interference."
18. Appellant's first point is regarding agreed procedure,
particularly in respect of pleadings. Perusal of procedural order dated
9th May, 2008 reveals that the tribunal said, after discussion with both
parties it is has been decided in the following manner, as stated
// 10 //
thereafter in the clauses 1 to 10. There being no disclosure of
otherwise written agreement regarding procedure, this procedural
order must taken to be decision of the tribunal, taken upon hearing the
parties. The tribunal having decided the procedure, accepted the
additional rejoinder. The award mentions that appellant had filed
memo of admission and denial, admitted some documents, denied
others, presumably on which there was cross examination made of
claimant's witness and still other documents, about which nothing was
said. In the circumstances, keeping in mind pleadings are for purpose
of giving notice of case to the other side, it is clear that appeallant had
sufficient notice of pleadings by the additional rejoinder as well as
opportunity to deal with disclosures made therein. In the situation, it is
not necessary to express a view on communication dispatched under
certificate of posting. Mr. Kanungo had handed up copy of letter dated
26th May, 2003, marked Ext.C-1 in the reference, sent by appellant to
his client under certificate of posting.
19. So far as, appellant's contention regarding bank guarantee is
concerned, it will appear from above record of submissions that it
cannot be said there is patent illegality appearing in the award. The
tribunal found that the guarantee was furnished for mobilization
// 11 //
advance and encashment of it was in excess of the unrecovered
amount.
20. The tribunal awarded Rs.25,000/- as transportation cost for
every school site, there being 90 school sites. Clause 4 in the
Additional Special Conditions stood in the way. However, appellant
itself appreciated difficult approach to identified locations and by Ext.
C-11 informed that claimant would be paid Rs.15,000/- on those sites.
The arbitrator went on to increase the cost from Rs.15,000/- to
Rs.35,000/-. This the arbitrator deed in respect of all sites. It does not
appear from Ext.C-11, as to which were the identified sites or they
were how many in number. This difficulty respondent has been able to
overcome by reliance on Atlanta Limited (supra), wherein the
Supreme Court said as quoted above.
21. So far as the claims on account of potable water and
compensation are concerned, these claims are clearly outside the
contract and there was no concession or relaxation made by appellant
with regard thereto. Award on account of potable water and
compensation are severable and hereby set aside. Appellant's counter
claim for cost and interest component, outstanding from respondent on
account of supply of steel was a counter claim, rejected. Court has
// 12 //
ascertained that the supply was made on request of respondent and not
as an obligation under the contract. That the arbitrator cannot travel
beyond four corners of the contract has been appellant's contention.
22. Impugned judgment is modified to extent that claims awarded
on account of potable water at aggregate Rs.1,00,000/- and
compensation at Rs.10,000/- per school for 86 completed schools, are
hereby set aside.
23. The appeal is partly allowed and disposed of.
(Arindam Sinha) Judge Prasant
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!