Citation : 2022 Latest Caselaw 2981 Ori
Judgement Date : 5 July, 2022
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBA No.18 of 2014
(Through hybrid mode)
NALCO .... Appellant
Mr. Manoj Kumar Mishra, Senior Advocate
Mr. T. Mishra, Advocate
-versus-
Amardeep Constructions .... Respondent
Mr. G.N. Mishra, Advocate
CORAM: JUSTICE ARINDAM SINHA
ORDER
05.07.2022 Order No.
6. 1. Mr. Manoj Kumar Mishra, learned senior advocate had
moved the appeal on 28th June, 2022. He had submitted, the
award is removed from the evidence. The arbitrator misdirected
himself in looking at the dispute to be a difference in the
measurement of excavated silt. In fact, claim made by
respondent was for additional work. There was no scope for
additional work in the contract. No direction was made to do
the additional work.
2. He referred to cross-examination of claimant witness
Amar Budhwar. He demonstrated from the deposition that the
evidence was, second RA bill covered work executed in
// 2 //
addition to work mentioned in the agreement. There is
admission that no order was issued by NALCO for doing any
additional work. According to the witness the additional work
was ordered by NALCO Engineer. He submits, no such order
was made.
3. Today Mr. G.N. Mishra, learned advocate appears on
behalf of respondent and submits, as found by the arbitrator,
controversy between the parties revolved on the simple
question whether the silt excavated from Sabari lake was
11,225.524 cu. mts. as claimed by his client or 6,500 cu. mts. as
contended by appellant. He draws attention to deposition of
said witness, both in chief and cross-examination, to point out
that it was not a claim for additional work but the variation
from quantity provided in the contract. He draws attention to
impugned judgment dated 27th January, 2014 for reliance on the
contract quantity clause introduced and extracted in it. He relies
upon following passage, reproduced below.
"The quantity variation has been mentioned in Clause 9.0 which runs as follows:
"The quantity mentioned in the schedule is approximate in nature and may vary widely. The contractor shall have to execute the work accordingly as per the direction of Engineer-in-
// 3 //
Charge. You shall not be entitled to any compensation whatsoever for a variation in the quantum of job.""
He submits, there should not be interference in appeal on the
Court below having found that the award cannot be said to
suffer from any ground under section 34 in Arbitration and
Conciliation Act, 1996, for it to be set aside.
4. Upon perusal of materials on record in the appeal, it is
clear that appellant's scope of work as per the contract was to
excavate 6,500 cu. mts. of silt from the lake. It appears to be
without dispute that the procedure provided for measurement of
silt excavated, was not adhered to. Several notings were made
and the engineer of appellant was also said to have maintained
record of measurements in his personal diary, not produced. The
arbitrator had before him parties having laid evidence. The
Tribunal found, scoring out of the figure arrived at on
measurements recorded, to be substituted by 6,500 cu. mts., did
not tally with rest of the notings made in the record of
measurements, maintained, as aforesaid, not as per procedure
provided in the contract. In analyzing the evidence, the Tribunal
found that the controversy arose because the contractor had
initialed the scoring out. The arbitrator appears to have been
// 4 //
impressed with evidence of the contractor that he had initialed
on being told that first R.A. bill was to be confined to the
contract quantity and for the balance, another bill had to be
raised. Hence, relying on evidence adduced, the Tribunal came
to the finding that the controversy was only about calculation of
quantity of excavated silt.
5. Appellant has relied on cross-examination of claimant
witness to emphasis there is admission that the second R.A. bill
did not constitute any claim for extra work. The contract
providing for excavation of a specified quantity, anything above
that was extra work. There was no direction by his client to do
such extra work and nothing could be disclosed before the
Tribunal to show otherwise. This contention cannot be accepted
because clause 9, quoted above, while providing for wide
variation in the quantity excavated, only barred the contractor
from claiming compensation for doing more work. Thus he
could claim for the actual quantity difference but not as an
extra, to include compensation.
6. Considering that the measurements recorded were not as
per procedure provided in the contract, the controversy between
parties necessarily enlarged scope of inquiry by the Tribunal. It
// 5 //
allowed both parties to lay evidence, documentary and oral. On
going through the evidence the Tribunal found as aforesaid. The
finding cannot be said to be such as a reasonable and prudent
person would not come to or that the view taken is not possible.
In the circumstances, this Court does not find that any of the
grounds in section 34 has been demonstrated as present in the
award.
7. Impugned judgment is confirmed. The appeal is
dismissed.
(Arindam Sinha) Judge
Sks
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!