Citation : 2022 Latest Caselaw 381 Ori
Judgement Date : 19 January, 2022
ORISSA HIGH COURT: CUTTACK
W.P(C) NO. 24589 of 2014
In the matter of an application under Articles 226 and
227 of the Constitution of India.
---------------
AFR Raghunath Sahu ..... Petitioner
-Versus-
State of Odisha & others ..... Opp. Parties
For Petitioner : M/s. (Mrs.) Pami Rath,
J. Mohanty & J.P. Behera,
Advocates
For Opp. Parties : Mr. T. Pattnaik,
Addl. Standing Counsel
P R E S E N T:
THE HONOURABLE DR. JUSTICE B.R.SARANGI
THE HONOURABLE MR. JUSTICE S.K. PANIGRAHI
Date of Hearing: 10.01.2022:: Date of Judgment: 19.01.2022
DR. B.R. SARANGI, J. The petitioner, who is a registered
contractor in 'A' class category of the State P.W.D.
Department, has filed this writ petition seeking to
quash the letter dated 03.12.2013 under Annexure-17
issued by the Joint Secretary to Government of Odisha, // 2 //
Fisheries & ARD Department in compliance of the
order dated 19.02.2008 passed by this Court in W.P.(C)
No.15922 of 2007, stating that no further escalation is
considerable at Government level for payment against
the work "Construction of Landing Quay and allied
structures at Talasari Fish Landing Centre in Balasore
District", because of existing situation and the
conditions in the work supported with the undertaking
dated 15.10.2002 after payment of legitimate claims for
Rs.11,85,207/- through Bank Draft No.792415 dated
26.11.2010 by the Executive Engineer, Fishery
Engineering Division, Bhubaneswar as per Fisheries
and ARD Department Sanction Order No.11834/FARD
dated 04.11.2010, and further to direct the opposite
parties to disburse the differential escalation amount of
Rs.4,20,940/- with interest @ Rs.18% per annum from
the date the escalation bill was submitted, i.e.,
27.08.2002.
2. The factual matrix of the case, in brief, is
that the petitioner, being the lowest tenderer in respect
of the work "Construction of Landing Quay and allied // 3 //
structures at Talasari Fish Landing Centre in Balasore
District", was selected in the tender process floated by
opposite party no.4. The work was entrusted to him by
execution of an agreement i.e. Divisional Agreement
No.22F2 of 1999-2000. As per stipulation made in
the agreement, the date of commencement and the
date of completion of the work were 01.12.1999 and
30.05.2001 respectively. Although bids were opened
on 06.04.1998, but there was delay on the part of the
opposite parties in finalization of the tender and
according approval due to pendency of some litigation.
Due to delay in acceptance of the tender, the rate
quoted by the petitioner became unworkable. The
agreement is nothing but verbatim copy of the tender
conditions and thus the original date of
commencement and completion reflected in the tender
papers have also been copied even though the
agreement actually was executed on 25.03.2000 and
the work actually commenced on 01.12.1999 and the
work was completed on 31.03.2003 during extended
period delay being not attributable to the petitioner.
// 4 //
2.1. As per contractual provision, i.e. Clause-
32(a)(b)(c) is strictly for payment of price escalation
during execution of the work in case of
increase/decrease in average wholesale price index (all
commodities) for material inputs and Consumer Price
Index for industrial workers towards labour inputs of
the work and price of POL (diesel oil being the
representative item for price adjustment) pursuant to
the prescribed formulae provided that the work is
carried out within the stipulated time or extension
thereof for the reasons that are not attributable to the
petitioner.
2.2. In view of the above provisions of contract
and in pursuance of the other conditions of the
contract, the petitioner is entitled to escalation cost. In
spite of difficult site condition and unavoidable
situations, the petitioner executed the work and
completed the same during the period extended validly
by the opposite party-Department. The cause of delay
in completion of the work is solely attributable to the
opposite parties and after considering the hindrances // 5 //
caused to the work, the opposite parties have not only
granted extension of time, but also paid running
account bills during extended period. Opposite party
no.3 effected payment through running account bill,
but neglected miserably in his contractual obligation to
pay the differential cost of escalation charges as per
Clause-32 of the agreement in spite of escalation bill of
Rs.16,06,147/- submitted on 27.08.2002.
2.3. The petitioner approached the authority time
and again by submitting representations/letters
addressed to the opposite parties for releasing price
escalation bill amount, as mentioned above, but the
same were not attended to. On account of unusual
delay caused in making payment of the escalation bill
amount, the petitioner was forced to approach this
Court by filing W.P.(C) No.15922 of 2007 seeking
direction for release of undisputed escalation amount
of Rs.16,06,147/- together with interest @ 18% per
annum from 27.08.2002 i.e. the date of submission of
the escalation bill and cost. This Court, vide order
dated 19.02.2008, disposed of the said writ petition // 6 //
with a direction that in case, the petitioner submits a
representation to the opposite parties with regard to
payment of escalation amount, the same shall be
considered and disposed of by giving a reasoned order
within two months from the date of production of such
representation. In compliance thereof, the petitioner
submitted his representation to opposite party no.3
with copies of the order to opposite parties no.1 and 2
on 18.03.2008. Subsequently, he sent reminders to the
said opposite parties on 10.09.2008. Though opposite
parties no.2 & 3 in their letters dated 13.08.2008 and
05.08.2008 respectively admitted the claim of the
petitioner for payment of escalation amount after due
check up to the bills presented by him, there was
inordinate delay caused by opposite party no.1 in
according approval. However, after a good deal of
correspondence and clarification, opposite party no.1
communicated to the petitioner that an amount of
Rs.11,85,207/- (which is less than the bill presented)
towards escalation charges for payment was sanctioned
in his favour vide letter dated 12.11.2010, without // 7 //
disclosing the reasons for not sanctioning the entire
escalation bill amount of Rs.16,06,147/-. As the
petitioner was undergoing much financial hardship due
to substantial amount remaining blocked in the hands
of the department and as situation then warranted to
make payment to his creditors and to be saved from
payment of unnecessary interest, the petitioner
accepted the sanctioned amount of Rs.11,85,207/- on
protest on 24.11.2010 vide acknowledgement on the
reverse of running account bill-C prepared by opposite
party no.3 for Rs.16,06,147/-, but limited it to
Rs.11,85,207 in view of Government sanctioned order.
As a consequence thereof, the petitioner is deprived of
getting payment of balance amount of Rs.4,20,940/-
towards his price escalation cost under the agreement,
which is due to one sided and illegal course of action
by the opposite parties dishonouring the agreemental
provision made in Clause-32 (a)(b)(c). Hence this
application.
3. Mrs. Pami Rath, learned counsel for the
petitioner emphatically urged before this Court that the // 8 //
opposite parties are liable to pay the admitted
escalation dues as per Clause-32 (a)(b)(c) of the
agreement and the letter dated 05.08.2008 issued by
opposite party no.3, it has been clearly held that price
escalation to the petitioner is payable as per the
formula fixed by the Works Department. Non-payment
of a part thereof amounting to Rs.4,20,940/-, the
opposite parties have violated the agreemental
provision of Clause-32 (a)(b)(c). It is further contended
that in order to receive the balance price escalation
amount, the petitioner again made representation and
finally he served a notice under Section 80 CPC for
taking steps towards clearance of his blockage balance
payment of Rs.4,20,940 under original agreement
period. It is further contended that though opposite
parties no.2 and 3 found that the dues of the petitioner
are genuine, pursuant to letter dated 22.08.2012
issued by opposite party no.4-Director of Fisheries,
Cuttack under Annexure-18, and the letter
23.05.2012, issued by opposite party no.3-Executive
Engineer, Fishery Engineering Division, Bhubaneswar // 9 //
and as evident from the fact, opposite party no.3 paid a
part of the escalation amount, but opposite party no.1
in a most whimsical and unjustified manner illegally
refused to pay the entire escalation charges by virtue of
the undertaking of the petitioner dated 15.10.2002. It
is further contended that vide letter dated 03.12.2013,
opposite party no.1 rejected the claim of the petitioner
for disbursement of the rest of the amount claimed in
the bill dated 27.08.2002 assigning the reason for non-
release of the left over amount that the petitioner had
submitted a no claim certificate when extension of time
was granted, while the departmental instruction dated
28.06.1996 states that such certificate cannot be made
a ground to reject the claim for escalation cost.
Thereby, the action taken by the authority is arbitrary,
unreasonable and contrary to the provisions of law and
as a consequence thereof, the petitioner is entitled to
get Rs.4,20,940/-, which was deducted from the
escalation cost along with interest @ 18% per annum.
To substantiate her contentions, she has relied upon
the judgment of the apex Court in ABL International // 10 //
Ltd. V. Export Credit Guarantee Corporation of
India Ltd., (2004) 3 SCC 553.
4. Per contra, Mr. T. Pattnaik, learned
Additional Standing Counsel for the State contended
that the date of commencement and stipulated date of
completion were 01.12.1999 and 30.05.2001
respectively, i.e. 18 months from the date of
commencement. The work was not completed by the
petitioner within the stipulated period of 18 months,
therefore, the petitioner applied extension of time up to
31.03.2003 and submitted an undertaking that he will
not claim any compensation on any account from the
Department for delay in completion of the work and
considering the same, opposite party no.1 granted
extension of time till 31.03.2003 vide letter no.3888
dated 10.03.2005. Thereby, escalation bill raised by the
petitioner amounting to Rs.16,06,147/- was submitted
to opposite party no.1, i.e. Government in Fisheries
and A.R.D. Department for approval and concurrence
of Finance Department for due approval and payment.
Opposite party no.1 after examining the claim of the // 11 //
petitioner by way of short audit after due concurrence
of Financial Advisor (FA)-cum-Joint Secretary of the
Department and in consultation with Finance
Department, accorded approval/sanction to an amount
of Rs.11,85,207/- for payment to the petitioner vide
letter dated 22.11.2010. Accordingly, the payment of
Rs.11,85,207/- was made on 26.11.2010 vide bank
draft. Thereby, the petitioner is not entitled to get the
balance amount of Rs.4,20,940/-, as claimed in the
writ petition. Therefore, he contended that the writ
petition is liable to be dismissed as it does not warrant
interference of this Court.
5. This Court heard Mrs. Pami Rath, learned
counsel for the petitioner and Mr. T. Pattnaik, learned
Additional Standing Counsel for the State opposite
parties by video conferencing mode. Pleadings have
been exchanged between the parties and with the
consent of learned counsel for the parties, the writ
petition is being disposed of finally at the stage of
admission.
// 12 //
6. At the outset, this Court made a query with
regard to maintainability of the writ petition in a
contractual matter, more particularly for payment of
the dues as claimed in the writ petition. In this regard,
learned counsel for the petitioner relied upon
paragraph-27 of ABL International Ltd. (supra),
wherein it is stated as follows:
"27.From the above discussion of ours, the following legal principles emerge as to the maintainability of a writ petition:
(a) In an appropriate case, a writ petition as against a State or an instrumentality of a State arising out of a contractual obligation is maintainable.
(b) Merely because some disputed questions of fact arise for consideration, same cannot be a ground to refuse to entertain a writ petition in all cases as a matter of rule.
(c) A writ petition involving a consequential relief of monetary claim is also maintainable."
7. In view of paragraph-27(c), as quoted above,
it has been clarified that the writ petition involving a
consequential relief of monetary claim is also
maintainable. But, while entertaining an objection with
regard to the maintainability of a writ petition under
Article 226 of the Constitution of India, it should be
borne in mind the fact that power to issue prerogative
writs under Article 226 of the Constitution is plenary in // 13 //
nature and is not limited by any other provisions of the
Constitution. The High Court, having regard to the
facts of the case, has a discretion to entertain or not to
entertain a writ petition. The Court has imposed upon
itself certain restrictions in the exercise of this power.
8. The plenary right of the High Court to issue
a prerogative writ will not normally be exercised by the
Court to the exclusion of other available remedies
unless such action of the State or its instrumentality is
arbitrary and unreasonable so as to violate the
constitution mandate of Article 14 or for other valid
and legitimate reasons, for which the Court thinks it
necessary to exercise the said jurisdiction.
9. Taking into account the above principle, now
in the fact of the present case it is to find out whether
the petitioner is entitled to get the relief or not as
sought in the writ petition filed by him. Furthermore,
there is no dispute that the opposite parties are the
"State" under Article 12 of the Constitution of India.
Therefore, on the factual matrix delineated above, // 14 //
whether the opposite parties are liable to pay the
petitioner's blockage balance amount of escalation cost
of Rs.4,20,940/- as per the original agreement.
10. Escalation cost is payable, in view of Clause-
32 (a)(b)(c) of the agreement, which reads as follows:
Clause 32-(a) "if during the progress of the work the price of any material incorporated in the work (not being materials supplied from the Engineer-in-charge's store in accordance with Clause .......... there of) increases or decreases as a result of increase or decrease in the average wholesale Price Index (all commodities), and the Contractor there upon necessarily and properly pays in respect of that material (incorporated in the work) such/increased or decreased price, then he shall be entitled to reimbursement or liable to refund, quarterly, as the case may be, such an amount, as shall be equivalent to the plus or minus difference of 70% in between the Average Wholesale price Index (all commodities) which is operative for the quarter under consideration and that operated for the quarter in which the tender was opened, as per the formula indicated below, provided that the work has been carried out within the stipulated time or extension thereof as are not attributable to him.
Formula to calculate the increase or decrease in the price materials:-
Vm- 0.75x Pm X R(i-i0) 100 10
Vm- Increase or decrease in the cost of work during the quarter under consideration due to changes in the rates for material.
R- The value of work done in rupees during the quarter under consideration.
// 15 //
i0- The average wholesale Price Index (all commodities) for the quarter in which the tender was opened (as published in R.B.I. Bulletin).
i- The average wholesale Price Index (all commodities) for the quarter under consideration.
Pm- Percentage of material Component (Specified in Schedule of analysis) of the item.
(b) Similarly, if during the progress of work, the wage of labour increase or decrease as a result of increase or decrease in the Average Consumer's Price Index for industrial workers (wholesale Price), and the Contractor thereupon necessarily and properly pays in respect of labour engaged on execution of the work such increased or decreased wages, then he shall be entitled to reimbursement or liable to refund, quarterly as the case may be, such an amount as shall be equivalent to the plus or minus difference in between the Average Consumer's Price Industrial workers (wholesale price) which is operating for the quarter under consideration and that operated for the quarter in which the tender was opened as per the formula indicated below provided that the work has been carried out within the stipulated time or extensions thereof as are not attributable to him.
Formula to calculate the increase or decrease in the cost of labour :-
VI- 0.75 x PI x R (i- i0)
100 10
VI- Increase or decrease in the cost of work during
the quarter under consideration due to changes in the rates of labour .
R- The value of work done in rupees during the quarter under consideration.
i0- The average Consumer's Price Index for industrial workers (wholesale price) for the quarter in which the tender was opened (as published in R.B.I Bulletin).
// 16 //
i- The average Consumer's Price Index for industrial workers (wholesale price) for the quarter under consideration.
P1- Percentage of labour Component (Specified in schedule and analysis) of the item.
(c) Similarly if during the progress of work, the price of Petrol, Oil and lubricants (Diesel oil being the representative item for price adjustment) increases or decreases as a result of the price fixed therefor by the Government of India and the Contractor thereupon necessarily and properly pays such increased or decreased price towards Petrol, Oil and Lubricants used on execution of the work, then he shall be entitled to re-imbursement or liable to refund quarterly, as the case may be such an amount, as shall be equivalent to the plus or minus difference in between the price of P.O.L. which is operating for the quarter under consideration and that operated for the quarter in which the tender was opened as per the formula indicated below."
11. As has been already stated, the work was
entrusted to the petitioner by execution of an
agreement i.e. Divisional Agreement No.22F2 of 1999-
2000 by opening bids on 06.04.1998 and as per the
terms of the agreement, the date of commencement
and the date of completion of work were 01.12.1999
and 30.05.2001 respectively. But, the agreement was
executed on 25.03.2000 and the work was actually
commenced on 01.12.1999 and it was completed on
31.03.2003 during the extended period, delay being not
attributable to the petitioner. Therefore, the petitioner // 17 //
submitted escalation bill of Rs.16,06,147/- on
27.08.2002 as per Clause-32 of the agreement.
Opposite parties no.2 and 3, vide letters dated
13.08.2008 and 05.08.2008 respectively, admitted the
claim of the petitioner for payment of escalation cost.
As against claim of Rs.16,06,147/-, opposite party no.1
vide letter dated 22.11.2010, in compliance of the
order dated 19.02.2008 passed by this Court in W.P.(C)
No.15922 of 2007, approved an amount of
Rs.11,85,207/- in order to make payment of the said
amount in favour of the petitioner towards escalation
charges as admissible for the work "Construction of
Landing Quay and allied structures at Talasari Fish
Landing Centre in Balasore District" and the petitioner
received such payment on protest as has been
indicated in the running account bill 'C' which reads as
follows:
"Received the payment Rs.11,25,947/- with protest to my claim Amount Rs.16,06,147/- against my escalation bill."
12. The petitioner made grievance on
13.01.2011 for payment of balance amount of
// 18 //
Rs.4,20,940/-, but the said amount was not paid on
the plea of "no claim certificate" dated 15.10.2002
submitted by the petitioner. The no claim certificate,
which was given by the petitioner, reads as follows:
"Certified that I will not claim any compensation on any account from the department for the delay incompletion of the work construction of Construction of Landing Quay and allied structure of Talsari Fish Landing Centre in Balasore Dist under Agreement No: 22F2/1999-2000."
On perusal of the same, it appears that no claim
certificate was in respect of only 'compensation', but
not with regard to 'escalation cost' as embodied in the
agreement itself.
13. In State of Gujarat v. Shantilal Mangal
Das, AIR 1969 SC 634, the apex Court held that
"compensation" means anything given to make things
equivalent, a thing given to or to make amends for loss,
recompense, remuneration or pay. It need not therefore
necessarily be in terms of money.
Similar view has also been taken by the apex
Court in KSRTC v. Mahadeva Shetty, (2003) 7 SCC
197 and Sandvik Asia Ltd. v. CIT, (2006) 2 SCC 508.
// 19 //
14. In Entertainment Network (India) Ltd. v.
Super Cassette Industries Ltd., (2008) 13 SCC 30,
the apex Court held that a 'compensation' maybe held
to be payable on a periodical basis, as part from the
compensation, other terms and conditions can also be
imposed.
15. In Jeejeebhoy v. Asst. Collector, Thana,
AIR 1965 SC 1069, the apex Court held that the
expression 'compensation' means 'just equivalent of
what the owner has been deprived of'.
16. In Kiranbala Dandapat v. Secy. Grid
Corporation of Orissa Ltd., AIR 1998 Ori. 159, this
Court has also considered 'compensation' as follows:
"Compensation means anything given to make things equivalent, a thing given or to make amends for loss, recompense, remuneration or pay; it need not, therefore, necessarily be in terms of money, because law may specify principles on which and manner in which compensation is to be determined as given. Compensation is an act which a Court orders to be done, or money which a Court orders to be paid, by a person whose acts or omissions have caused loss or injury to another in order that thereby the person damified may receive equal value for his loss or be made whole in respect of his injury; something given or obtained as equivalent given for property taken or for an injury done to another, a recompense in value; a recompense given for a thing received recompense for whole injury suffered, remuneration or satisfaction for injury or // 20 //
damage or every description. The expression 'compensation' is not ordinarily used as an equivalent to 'damage' although compensation may often have to be measured by the same rule as damages in an action for a breach."
17. Therefore, the no claim certificate so given
by the petitioner can be construed that he will not
claim any 'compensation'. But, fact remains the
petitioner claims escalation cost as per provisions of
Clause-32 (a) (b) (c) of the agreement.
18. In Food Corporation of India v. A.M.
Ahmed & Co., (2006) 13 SCC 779, the apex Court held
that 'escalation' is normal and routine incident arising
out of gap of time in this inflammatory age in
performing any contract of any type.
19. In Suryamani Nayak v. Orissa State
Housing Board, AIR 2005 Ori. 26, this Court held that
the expression 'escalation' used in an agreement
ordinarily means an agreement allowing for adjustment
up and down according to change in circumstances as
in cost of material in work contract or in cost of living
in wage agreement. It would not bring within its sweep // 21 //
higher rate of wage which a contractor is otherwise
liable to pay.
20. Therefore, taking into consideration the
meaning attached to the word 'escalation', as per terms
and conditions of the agreement, the petitioner is
entitled to get escalation cost but not the
compensation, for which the blockage of the escalation
benefit has been made. Needless to say, an
'undertaking' is nothing but a standard form, which
every contractor has to sign and submit to the effect
that he shall not claim for compensation for delay in
work and extend the period of work. This is submitted
whenever extension of time is granted for completion of
work or else extension will not be granted. This
document is signed, without adjudicating the merits of
the claim of the petitioner, and is done under duress or
else the contract would be liable to be terminated with
penalty, even though the petitioner may not be
responsible for delay in execution of work.
// 22 // 21. The Government of Odisha in Works Department, vide letter dated 28.06.1996 under
Annexure-12, introduced the provision of escalation
clause in P.W.D. Contract form for payment of
escalation charges to the contractor during the
extended period, relying upon the extract of the
proceedings of the Codes Revision Committee Meeting
held on 25.11.1995 at 11.30 A.M. in the Office
Chamber of Engineer-in-Chief-cum-Secretary to
Government, Works Department in Item -1, which is
extracted hereunder:-
"Item -1: Payment of escalation charges to Contractors.
Xxx xxx xxx
(ii) While granting extension of time to the Contractors "no claim certificate" is obtained from them in the prescribed form of the Department. The significance of such certificate is that the Contractor surrenders his claim for "compensation on any account". But it is seen in many cases that contractors are putting up their claims for escalation in spite of no claim certificate given by them earlier. It is to be decided if such claim of the contractors are consistent with the non claim certificate. At this point, Secretary, Works Department observed that compensation and escalation are not one and the same. The object of payment of compensation is to make good the loss suffered by the contractor on account of negligence, default or fraud committed by the other party and does not cover escalation. Hence "no claim certificate" will not be a bar to te claim of // 23 //
escalation. The members endorsed the above views of the Engineer-in-Chief-cum-Secretary.
Xxx xxx xxx"
In view of the above mentioned provision, even though
the petitioner executed "no claim certificate", but that
will not be a bar for him to claim escalation cost.
22. In the present case, the bill dated
27.08.2002 was raised towards escalation cost to the
tune of Rs.16,06,147/-, but the authority considered
the same, after the order was passed by this Court on
19.02.2008 in W.P.(C) No.15922 of 2007, and
sanctioned a sum of Rs.11,85,207/- towards escalation
cost, by deducting Rs.4,20,940/- without any rhyme or
reason, for which the said amount of Rs.11,85,207/-
was received by the petitioner with protest. Thereby,
the opposite parties have agreed that the petitioner is
entitled to escalation cost during extended period of
work and as such, extension of work was not due to
fault of the petitioner. As a matter of fact, the
escalation cost was granted in part to the petitioner,
relying upon no claim undertaking submitted by the
petitioner, which is absolutely a myth. The opposite // 24 //
parties, having accepted the entitlement of escalation
cost by the petitioner as per Clause-32 of the
agreement, have taken into consideration the "value of
work done in rupees during the quarter under
consideration". The said value of the work in rupees of
the relevant quarter has already been decided and
sanctioned by opposite party no.1 vide sanction order
dated 18.08.2003. As per certificate dated 18.08.2003,
the Junior Engineer F4 Engineering, Sub-Division,
Bhadrak and Sub-Divisional Officer, Balasore, F4
Engineering Sub-Division, Bhadrak have certified the
value in rupees of quarter-wise work, which states as
follows:
Serial No. Running Date of Related Value of
Bill measurement quarter work in
by opposite rupees
party
1 1st 18.2.2000 1st quarter Rs.35,74,433
of 2000
2 2nd 12.5.2000 2nd quarter Rs.46,89,274
of 2000
3 3rd and 4th 23.6.2000 & 3rd quarter Rs.18,15,326
11.8.2000 of 2000
4 5th and 6th 1.3.2001 1st quarter Rs.15,00,596
of 2001
// 25 //
The bill dated 27.08.2002 also reflects the same value
even though it has been submitted earlier. As it
appears, instead of taking note of own certified
document dated 18.08.2003, the opposite parties,
while dealing with the escalation bill of the petitioner
dated 22.11.2010, have reduced the value of the work
arbitrarily, so far it relates to the value of 1st quarter of
2000. Instead of reflecting the value as Rs.35,74,433/-,
it has been reflected as Rs.1,21,600/-, which has
resulted in arriving at a different amount as escalation
cost and that is how instead of Rs.16,06,147/- the
escalation cost has been calculated as Rs.11,85,207/-.
23. The reflection of work value for the first
quarter of 2000 as Rs.1,21,600/-, instead of
Rs.35,74,433/-, is erroneous and contrary to its own
recording in certificate dated 18.08.2003. This is also
fortified from the entries made by the opposite parties
in the measurement book, which has been placed on
record as Annexure-15, wherein for 1st quarter of 2000
the amount of Rs.35,74,433/- has been specifically
mentioned at page 137. Though in respect of other // 26 //
quarters the amount has been mentioned correctly,
and the same has been reasonably placed, but
erroneously calculated for payment of escalation cost
as Rs.11,85,207/- in place of Rs.16,06,147/-. As per
the measurement book and certificate dated
18.03.2002, the total value of work upon which
escalation is to be calculated has come to
Rs.1,15,79,625/-, i.e. the said amount is also the
amount payable to the petitioner. The said amount has
also been paid in the form of final bill, which has been
paid much prior to the payment of escalation amount.
Thereby, there is no dispute with regard to the value of
work reflected in the measurement book or in the
certificate dated 18.03.2002. But, due to erroneous
intimation of amount for the 1st quarter of 2000
running account bill in the letter dated 22.11.2010 in
Annexure-14 amounting to Rs.1,21,600/- in place of
Rs.35,74,433/-, the escalation cost reduced from
Rs.16,06,147/- to Rs.11,85,207/-. Therefore, due to
wrong recording of value of work, the blockage amount // 27 //
of Rs.4,20,940/- towards escalation cost is payable to
the petitioner.
24. Even in paragraph-23 of the writ petition,
the petitioner has pleaded as follows:-
"23. That the said amount reflected for the 1st quarter of 2000 as Rs.1,21,600/- instead of Rs.35,74,433/- is not only contrary to its own recording in certificate dated 18.08.2003 but also to the entries made by the opposite party in measurement book. The amount reflected in certificate dt. 18.08.2003 is also supported by the entries in the measurement book which again is a document authored by the opposite party. It is clearly reflected in measurement book that the amount for 1st quarter of 2000 is not Rs.1,21,600/- but Rs.35,74, 433/-."
But, there is no specific denial to such pleading. Rather
in paragraph-11 of the counter affidavit, it is stated as
follows:-
"11. That in reply to the averments made in Paragraphs-21 to 28 of the writ application, it is humbly submitted that the after examining the claim of the petitioner, the O.P. No.1, by conducting short audit and in consultation with the Finance Department has sanctioned the legitimate amount in favour of the petitioner and accordingly the same has been paid to the petitioner. No further claim of the petitioner is pending with the Opp. Parties. Considering the aforesaid facts, the Hon'ble Court may graciously be pleased to dismiss the writ being devoid of any merit."
Since the pleadings made in paragraph-23 of the writ
petition have not been disputed by the opposite parties // 28 //
and the claim has been denied only on the basis of no
claim certificate, the petitioner is entitled to get the
benefit of blockage amount of Rs.4,20,940/- towards
escalation cost as per the bill submitted on
27.08.2002.
25. Considering the facts and law, as discussed
above, this Court is of the considered view that the
opposite parties are liable to pay the blockage amount
of Rs.4,20,940/- towards escalation cost as per the bill
submitted on 27.08.2002 along with interest @ 12%
per annum w.e.f. 22.08.2012 till the actual payment is
made. As such, the payment shall be made within a
period of three months from the date of
communication/production of the judgment, failing
which it will carry further interest @ 18% per annum
w.e.f. from 22.08.2012 till the actual payment is made.
26. In the result, the writ petition is allowed.
However, there shall be no order as to cost.
As the restrictions due to resurgence of
COVID-19 situation are continuing, learned counsel for // 29 //
the parties may utilize a print out of the order available
in the High Court's website, at par with certified copy,
subject to attestation by the concerned advocate, in the
manner prescribed, vide Court's Notice No.4587 dated
25th March, 2020, as modified by Court's notice no.
4798 dated 15th April, 2021, and Court's Office Order
circulated vide Memo Nos.514 and 515 dated 7th
January, 2022.
.....................................
DR. B.R. SARANGI,
JUDGE
S.K.PANIGRAHI,J. I agree.
..................................... S.K. PANIGRAHI, JUDGE
Orissa High Court, Cuttack The 19th January, 2022, Alok
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!