Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Paradip Port Trust vs M/S. Cimmco Birla Ltd
2022 Latest Caselaw 291 Ori

Citation : 2022 Latest Caselaw 291 Ori
Judgement Date : 11 January, 2022

Orissa High Court
Paradip Port Trust vs M/S. Cimmco Birla Ltd on 11 January, 2022
             IN THE HIGH COURT OF ORISSA AT CUTTACK

                           ARBA No.35 Of 2015
                     (Through video conferencing mode)

        Paradip Port Trust                    ....            Appellant

                               Mr. Ramakanta Mohanty, Sr. Advocate

                                  -versus-

        M/s. Cimmco Birla Ltd.                ....          Respondent

                                          Mr. S. Chaudhury, Advocate


                 CORAM: JUSTICE ARINDAM SINHA
                                  ORDER
Order                            11.01.2022
No.
  15.   1.      Mr. Mohanty, learned senior advocate appears on behalf of

appellant and submits, the appeal is directed against judgment dated

16th September, 2015 passed by the learned District Judge rejecting his

client's challenge to award dated 14th March, 2012. He submits, the

facts stood admitted in the reference but the Tribunal made some

findings on 'force majeure', which are perverse. The Court below did

not appreciate the perversity and hence the appeal. He refers to

paragraphs 18 to 22 in the award. He submits, paragraph-18 was a

contention on 'force majeure' that the Tribunal decided in favour of

his client. The second contention is in paragraph-19. The contention

was that by reason of lock out in Bharat Works Factory of claimant,

// 2 //

from 15th November, 1998 to 31st January, 1999, there was delay. This

was construed as a 'force majeure' situation by the Tribunal. Mr.

Mohanty accepts that paragraph-20 dealing with the super cyclone on

29th October, 1999 was an act of God and therefore covered by 'force

majeure'. He however submits, the amount of latitude shown by the

Tribunal on holding in favour of claimant on this contention was

beyond the evidence. Appellant itself resumed work activities in the

Poet fifteen days after the cyclone but claimant's personnel admittedly

visited two months after it. Next contention of 'force majeure' was

dealt with in paragraph-21 of the award. It was on strike resorted to by

employees of appellant. Paragraph-22 was contention raised by

claimant regarding hooliganism resorted to by passing connected with

previous contractor of appellant. He submits, the Supreme Court by

judgment dated 5th January, 2022 in Civil Appeal nos.169-170 of

2022 (State of UP v. M/s. Mcdowell and Company Ltd.) held that

for invoking 'force majeure', there must be some act of God.

2. On query from Court Mr. Chaudury, learned advocate

appearing on behalf of respondent submits, cancellation clause-23 in

general conditions of contract stands quoted under paragraph-24 in the

award.

// 3 //

3. The Court below in paragraph-11 of impugned judgment

recorded the facts. Paragraph-11 is reproduced below.

"11.On careful scrutiny of the record, impugned Arbitral award in the light of submission of both the Counsel for the petitioner and the O.P., it shows the following are not the disputed facts:

(i) PPT had floated a tender for execution on the work, Designed, Manufacture, supply, Erection and commissioning of one number of stacker cum reclaimer of capacity of 2500 MTPH,35 meters Boom length.

(ii) O.P. (claimant's company) offered contract value of Rs.823 lakhs.

(iii) Arbitration Agreement was executed in between the claimant company and respondent-PPT with certain terms and conditions to commence the work on 26.3.1998 and its completion on 25.5.2000.

(iv) On 28.3.98 the claimant company deposited 10% of the contract value i.e. Rs.82,30,000/- in shape of Bank Guarantee towards performance security.

(v) 99.995% of the contract work was compelted and balance of 0.005% was remained to be executed. On the request of both the parties, the same was extended up to 11.6.2001.

(vi) On dtd. 13.7.2001, the contract was cancelled with immediate effect with forfeiture of performance security.

// 4 //

(vii) Balance of 0.005% of the contract work was completed by the respondent-PPT by other agencies under its supervision."

4. Appellant will be finally heard on 20th January, 2022. Court

will be interested to hear on applicability of the cancellation clause to

the facts. Court also notices that the agreement provides for expansion

of meaning of 'force majeure' by several clauses.

5. List on 20th January, 2022.

(Arindam Sinha) Judge Sks

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter