                 IN THE HIGH COURT OF ORISSA AT CUTTACK

                              W.P.(C) NO.29914 OF 2022

            Arun Kumar Bhuyan                       ....               Petitioner

                                                       Ms.D.Mahapatra, Adv.

                                         -versus-


            State of Odisha & ors.                  ....        Opposite Party(s)

                                                          Mr.S.P.Panda, AGA
                                                         Mr.D.Mohapatra, Adv.

                       CORAM:
                       JUSTICE BISWANATH RATH
                                        ORDER

7.12.2022 Order No.

05. 1. Heard learned counsel for the Parties.

2. The Writ Petition involves the following prayer :-

"Under the facts and circumstances as narrated above, this Hon'ble Court may graciously be pleased to issue rule Nisi to the opposite parties and if the opposite parties will fail to show cause or shown insufficient cause, make the said Rule absolute by directing the opposite parties to grant approval of the plan in respect of the Plot in question in favour of the petitioner and to make sale deed in favour of the petitioner and quash the letter dated 23.12.2020 under Annexure-7..."

3. Taking this Court to the impugned rejection order at

Annexure-7, learned counsel for the Petitioner submits, there has

been rejection of the plan approval applied at the instance of the

Petitioner by the Development Authority on the premises of plot

// 2 //

being allotted under discretionary quota and is under investigation.

While rejecting the claim of the Petitioner, it has also been indicated

therein that till finalisation of the proceeding, the proposal cannot be

considered.

4. For the opinion of this Court, this is not a complete rejection

of the plan approval of the Petitioner and the Petitioner has still the

scope of consideration.

5. Be that as it may, filing counter affidavit on behalf of the

Development Authority, Mr.D.Mohapatra, learned counsel

appearing for it, brings to the notice of this Court that there is

already a proceeding pending, vide Annexure-A/1 series involving

the notice to show cause for cancellation of the plot standing against

the Petitioner. Through the pleading in the counter through

Paragraph-7, it is claimed, for pendency of the proceeding, it is

necessary to first dispose of the proceeding and dependent on the

outcome in the said proceeding (Annexure-6), a decision is still

available to be taken on the request of the Petitioner, as informed,

vide Annexure-7.

6. There is no dispute at the Bar that there has been a decision

of this Court in the matter of single discretionary quota allotment,

which also applies to the case at hand but for the opinion of this

// 3 //

Court, for pendency of the proceeding against the Petitioner and the

impugned order was passed on 23.12.2020 giving a development

through the decision of this Court to the issue involved therein

recently, vide W.P.(C) No.5274/2022 disposed of on 19.7.2022, this

Court finds, the proceeding involving the Petitioner, vide Annexure-

A/1 series must be disposed of within a time frame at least within

period of one and half months. Decision process may also involve

consideration of the judgment of this Court in W.P.(C)

No.5274/2022.

7. In disposal of the Writ Petition, the Secretary, Cuttack

Development Authority is directed to revive the proceeding, vide

Annexure-A/1 series and complete the entire exercise keeping in

view the judgment of this Court dated 19.7.2022 passed in W.P.(C)

No.5274/2022 at least within a period of one and half months from

the date of communication of this order by the Petitioner. Dependent

on the outcome, there should be also decision on the request of the

Petitioner on the plan approval involving the Plot involved herein. It

is made clear, in the event the proceeding goes in favour of the

Petitioner, decision on the plan approval aspect involving the

Petitioner may also be concluded within a period of one month

thereafter.

// 4 //

8. With this observation, the Writ Petition stands disposed of.

(Biswanath Rath) Judge M.K.Rout

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter