Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Steel Authority Of India Limited vs M/S. G. C. Kanungo Construction
2022 Latest Caselaw 2287 Ori

Citation : 2022 Latest Caselaw 2287 Ori
Judgement Date : 19 April, 2022

Orissa High Court
Steel Authority Of India Limited vs M/S. G. C. Kanungo Construction on 19 April, 2022
                 IN THE HIGH COURT OF ORISSA AT CUTTACK

                                 ARBA No.40 Of 2014
                                (Through hybrid mode)


            Steel Authority of India Limited      ....                    Appellants
            and another
                                                          Mr. N.K.Sahu, Advocate

                                           -versus-

            M/S. G. C. Kanungo Construction       ....                   Respondent
            (P) Ltd., CTC.
                                                Mr. M.Kanungo, Senior Advocate

                      CORAM: JUSTICE ARINDAM SINHA

                                     ORDER

19.04.2022 Order No.

20. 1. Mr. Sahu, learned advocate appearing on behalf of appellants

resumes his submissions in continuation of those made and recorded in

order dated 29th March, 2022. He refers to paragraph 24 in the award,

which deals with whether his client was entitled to recover cost of

material and interest. He submits, there was a cost and interest

component, outstanding from respondent on account of supply of

steel. The tribunal committed illegality in rejecting the counter claim.

On query from Court he submits, the supply was made on request of

respondent and not as an obligation under the contract.

2. The then draws attention to clause (iii) under paragraph 30 in

// 2 //

the award. He submits, there was award of Rs.2000/- per school,

aggregating Rs.1,00,000/- said to be payable due to use of potable

water. Referring to clause 8 in the Letter of Intent dated 24th April,

2000 (Ext. R-10), he demonstrates that, inter alia, water was to be

arranged by the contractor at its cost.

3. Moving on to clause (iv) under the paragraph he submits, extra

transportation cost including lifts and leads were awarded at Rs.

31,50,000/-. There was clear mention under clause 4 in additional

special conditions (Ext. R-10) that all leads, lifts, transportation was

included in the scope of work.

4. With reference to clause (x) under the paragraph he submits,

compensation could not have been awarded. There was arbitrary

award of Rs.1000/- for each completed school, i.e., 86 in number. The

contract did not provide for payment of compensation and the

arbitrator could not have awarded. Furthermore, there was award of

Rs.8,95,000/- also arbitrarily made at the rate of Rs.10,000/- per

school for 60 schools taken out of the scope of work, Rs.15,000/- for

13 schools and Rs.20,000/- for 5 schools. He submits,

claimant/respondent itself pleaded for reducing scope of the work.

Hence from total number of schools in original scope of work, some

// 3 //

schools were taken out. Compensation for pilferage or stealing or

whatever could not have been awarded as not provided in the contract.

The arbitrator travelled beyond four corners of the contract and hence

there should be interference.

5. He relies on several judgments of the Supreme Court.

i) MMTC Ltd. vs. M/S.Vedanta Ltd., reported in (2019) 4 SCC

163, paragraphs 10 to 12, wherein earlier judgments of the Court in

Associate Builders vs. BDA, ONGC Ltd. vs. Saw Pipes Ltd. etc.

were referred for well settled law that Court does not sit in appeal over

the arbitral award and may interfere on merits on limited grounds

provided under section 34, Arbitration and Conciliation Act, 1996.

ii) Maharashtra vs. Rashid Babu Bhai Mulani, reported in

AIR 2006 SC 825, paragraph 14. The Supreme Court, in the

paragraph, said regarding postal dispatch under certificate of posting

and the ease, with which such certificate can be procured by affixing

ante dated seal with the connivance of any employee of the post office,

was a matter of concern. He reiterates, the tribunal relied on

documents introduced by additional rejoinder. Those were copies of

letters allegedly sent to his client under certificate of posting.

iii) Steel Authority of India Ltd. Vs. J.C. Budharaja, reported in

// 4 //

(1999) 8 SCC 122. He submits, this judgment was rendered in

adjudication under Arbitration Act, 1940 but the principle of law

applies. The Court found that the award was passed in disregard of

express terms of the contract and therefore was arbitrary, capricious

and without jurisdiction, as in the case here.

iv) Food Corporation Of India vs M/S.Chandu Construction,

reported in (2007) 4 SCC 697, paragraphs 11 to 13. He submits, this

judgment too was rendered under the Act of 1940, on jurisdictional

error committed by the arbitrator in travelling beyond four corners of

the contract.

6. Mr. Sahu concludes his submission. Mr. Kanungo, learned

senior advocate appearing on behalf of respondent will be heard on

adjourned date.

7. List on 26th April, 2022.

(Arindam Sinha) Judge Prasant

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter