United Construction vs The Chief General Manager
2021 Latest Caselaw 10535 Ori

Citation : 2021 Latest Caselaw 10535 Ori
Judgement Date : 1 October, 2021

Orissa High Court
United Construction vs The Chief General Manager on 1 October, 2021
                  IN THE HIGH COURT OF ORISSA AT CUTTACK
                                     ARBP No.69 of 2018
               United Construction                 ....              Petitioner
                                                  Mr. S.S. Rao, Sr. Advocate
                                          -versus-
               The Chief General Manager,
               Office of the Principal Chief
               Engineer, Rail Sadan,               ....           Opp. Parties
               Bhubaneswar and others
                                                 Mr. A.K. Mishra, Advocate


                        CORAM:
                        THE CHIEF JUSTICE


                                      ORDER

Order No. 01.10.2021 Dr. S. Muralidhar, ACJ

21. 1. This petition under Section 11(6) of the Arbitration and Conciliation Act, 1996 ('Act') seeks appointment of an Arbitrator to adjudicate the disputes between the Petitioner and the Opposite Parties East Coast Railways (ECR) arising from the award of work in favour of the Petitioner on 19th April, 2010 for replacement of the existing steel channel sleepers with new galvanized fastenings.

2. The case of the Petitioner is that under Clause-64 of the General Conditions of Contract (GCC), governing the award of the above work, as amended on 11th November, 2016, the disputes involving claims of total value not exceeding One Crore were to be referred to the sole Arbitrator who shall be a Gazetted Officer of the Railway not below the rank of J.A.

cadre nominated by the General Manager, who shall be appointed within 60 days from the date of demand. In other cases, the disputes were to be referred to a panel of three Gazetted Railway Officers not below the J.A. cadre or two Railway Gazetted Officers not below the J.A. cadre and a retired Railway Officer not below the rank of an SAG Officer.

3. The Petitioner states that in view of the amendment made to the Act in 2015, an option was given to the parties to waive of the applicability of Section 12 (5) of the Act. According to the Petitioner he prayed for extension of time for completion of the work but this request was not accepted. Therefore, by a letter dated 12th November 2012 he requested the ECR to close the work and release the funds.

4. The Petitioner by letter dated 25th June, 2018 is stated to have raised a demand and sought the appointment of an Arbitrator. In paragraph 6 of the petition it is stated by the Petitioner that by a letter dated 6th July, 2018 he was advised by the General Manager, Arbitration, of the ECR to sign a letter exempting the applicability of the Section 12 (5) of the Act. The Petitioner declined and wrote back on 21st July, 2018 asking the General Manager to suggest a panel of Arbitrators. It is stated that on 4th September, 2018 the Chief General Manager (CGM) wrote to the Petitioner disputing the correctness of the demand and declined the request.

5. On 14th September, 2018 the Petitioner's request for the appointment of Arbitrator was rejected. The ECR stated in the said letter that the claim of the Petitioner was baseless and would not be required to be referred to arbitration. It is in the above circumstances, the present petition was filed on 21st December, 2018.

6. The ECR has filed a reply to the petition on 24th July, 2019. It is stated therein that the work was completed within the extended date, i.e., 31st March, 2013. The final bills (one each for Asst. Divisional Engineer/Bhubaneswar and Dhenkanal) had been passed and the contractor submitted 'No Claim Certificate' (NCC) on both the final bills. Thereafter, the final bills were passed and the security deposit was released on the Petitioner submitting the NCC.

7. In its reply the ECR has pointed out how five years after the release of the money, the Petitioner applied by a letter dated 25th June, 2018 for the appointment of an Arbitrator. The claim was time-barred and was accordingly rejected.

8. At the hearing of the present petition on 5th July, 2021 the Court noticed that the NCC had been signed by the Petitioner on 16th November, 2013 whereas the fresh notice by the Petitioner to the ECR making a claim was sent on 25th June, 2018. The Petitioner was asked to explain the gap of over four years between these dates. Mr. Rao, learned Senior counsel

appearing for the Petitioner then sought time for instructions regarding the delay.

9. The Court heard the submissions of Mr.S.S. Rao, learned Senior counsel appearing for the Petitioner and Mr. A.K. Mishra, learned counsel appearing for the ECR.

10. Mr. Rao referred to the decision dated 10th March, 2021 of the Supreme Court of India in Civil Appeal Nos.843-844 of 2021 (Bharat Sanchar Nigam Ltd. v. M/s. Nortel Networks India Pvt. Ltd.) and submitted that the issue whether the claims for time barred should be best left to the Arbitrator. He however frankly stated that he had no material to explain the delay between the date of Petitioner signing the NCC and the date of making the claim. However, he submitted that this also should also be left to be decided by the Arbitrator.

11. The Court has examined the above decision. The law has been summarized by the Supreme Court in paragraph 40 of the judgment as under:

"40. Conclusion Accordingly, we hold that:

(i) The period of limitation for filing an application under Section 11 would be governed by Article 137 of the First Schedule of the Limitation Act, 1963. The period of limitation will begin to run from the date when there is failure to appoint the arbitrator;

It has been suggested that the Parliament may consider amending Section 11 of the 1996 Act to provide a period of limitation for filing an

application under this provision, which is in consonance with the object of expeditious disposal of arbitration proceedings;

(ii) In rare and exceptional cases, where the claims are ex facie time-barred, and it is manifest that there is no subsisting dispute, the Court may refuse to make the reference."

12. The question is here about the delay between the date, the NCC was signed and the date on which the Petitioner made a fresh claim. Since this gap is well over four years, it was incumbent by the Petitioner to satisfactorily explain to the Court, even prima-facie, that the claim is not barred by limitation. There is no such material available with the Petitioner. Therefore, even if the dispute were to be referred to arbitration, the result would be no different.

13. In the considered view of the Court the claims of the Petitioner appear ex facie time barred and therefore cannot be referred to arbitration. In that view of the matter, the Court declines to accept the prayer of the Petitioner for the reference of the dispute to arbitration. The arbitration petition is accordingly dismissed but in the circumstances no order as to costs.

(Dr. S. Muralidhar) Chief Justice

KC Bisoi

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter