Citation : 2021 Latest Caselaw 12542 Ori
Judgement Date : 6 December, 2021
IN THE HIGH COURT OF ORISSA AT CUTTACK
ARBA No.11 Of 2011
(Through hybrid mode)
M/s. Engineers India Ltd. .... Appellant
Mr. S.P. Mishra, Senior Advocate
-versus-
Shyam Sunder Agarwal and .... Opposite parties
another
Mr. Y.Dash, Senior Advocate
CORAM: JUSTICE ARINDAM SINHA
ORDER
Order 06.12.2021 No. 14. 1. Mr. Mishra, learned senior advocate appears on behalf of
appellant and submits, challenge of his client to set aside award passed
under Arbitration Act, 1940 is on ground (a) in section 30. In other
words, the arbitrator has misconducted himself and the proceedings by
awarding on claims beyond scope of the contract. The arbitrator could
not have moved beyond four corners of the contract. He submits, the
contract had special conditions. He relies on clause-7 in the special
conditions, reproduced below:
"7. The contractor agrees that he has visited the site and acquainted himself fully with the site conditions and that no claims other than those stipulated herein,
// 2 //
shall be entertained by the Company on the plea of ignorance of difficulties or hardships involved in providing the services."
2. Mr. Dash, learned senior advocate appears on behalf of
respondent-claimant he submits, admittedly the award is non-speaking
one. Details of claims are given at page-25 of the application for setting
aside the award. He submits, 19 claims were made for agreegate
Rs.1,14,74,180/- and interest at Rs.41,30,704/- taking the total to
Rs.1,56,04,884/-. Of this claim, the arbitrator awarded Rs.52,00,000/-.
Hence, less than 1/3rd of the total claim was awarded. He relies on
order dated 5th August, 2015 of the Supreme Court in Civil Appeal
no(s). 3209 of 2007 ( Indian Rare Earths Ltd. v. Unique Builders
Ltd.) to submit, there should be no interference. The award should be
made judgment of Court and decree drawn up accordingly.
3. In Indian Rare Earths (supra), contention of appellant seeking
to challenge the award finds record in the order, extracted and
reproduced below:
"Mr. Vinoo Bhagat, learned cousnel appearing for the appellant, assailed the said Award and the impugned order passed by the High Court on various grounds inter alia the jurisdiction of the Arbitrator in passing a non-speaking Award when arbitrability of the disputes was questioned. Mr. Bhagat, learned counsel, also
// 3 //
submits that in absence of any specific provision, the claim against the escalation of prices ought not to have been awarded. In this connection, Mr. Bhagat relied upon various decisions of this Court in the case of T.N. Electricity Board vs. Bridge Tunnel Constructions & Ors. - (1997) 4 SCC 121; V.G. George vs. Indian Rare Earths Ltd. & Anr. - (1999) 3 SCC 762; and Associated Engineering Co. vs. Government of Andhra Pradesh & Anr. - (1991) 4 SCC 93."
The Court dealt with the challenge in the manner reproduced below:
"As noticeed above, although the respondent claimed a sum of Rs.97,54,143.78/- but the Arbitrator only awarded a sum of Rs.19,55,368/- (Rupees nineteen lakh fifty five thousand three hundred and sixty eight only) with pendente lite interest at the rate of 15% per annum from the date of institution of the suit till the date of the Award. Admittedly, the Award is a non- speaking award. Hence, it is not permissible for the Court to probe into the mental process of the learned Arbitrator especially when the Arbitrator rejected major portion of the claim made by the respondent.
In the background of all these facts, we do not find any reason to interfere either with the Award passed by the learned Arbitrator or with the impugned order passed by the High Court. Hence, this appeal is dismissed."
// 4 //
4. Adjournment is granted for appellant to be heard in contest of
record in today's order.
5. List on 17th December, 2021 as prayed for.
(Arindam Sinha) Judge Sks
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!