Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Meghalaya Cements Ltd. vs . Union Of India & Ors.
2022 Latest Caselaw 625 Meg

Citation : 2022 Latest Caselaw 625 Meg
Judgement Date : 26 October, 2022

High Court of Meghalaya
Meghalaya Cements Ltd. vs . Union Of India & Ors. on 26 October, 2022
     Serial No. 03
     Supplementary
     List

                        HIGH COURT OF MEGHALAYA
                            AT SHILLONG

WP(C) No. 289 of 2018
                                                 Date of Decision: 26.10.2022
Meghalaya Cements Ltd.                Vs.                Union of India & Ors.
Coram:
               Hon'ble Mr. Justice W. Diengdoh, Judge

Appearance:
For the Petitioner/Appellant(s)   :         Dr. A. Saraf, Sr. Adv. with
                                            Mr. S.J. Saikia, Adv.
For the Respondent(s)             :         Dr. N. Mozika, DSG. with

Ms. A. Pradhan, Adv. for R 1.

Mr. M. Singh, Sr. Adv. with Mr. M.Z. Ahmed, Sr. Adv.

GP Capt. K. Singh Bhatti, Adv.

Ms. B. Dutta, Sr. Adv. for R 2-5.

i)       Whether approved for reporting in                      Yes/No
         Law journals etc.:

ii)      Whether approved for publication
         in press:                                              Yes/No


                        JUDGMENT AND ORDER


1. The petitioner company is engaged in the business of

manufacturing cement and for this purpose had entered into an agreement

with the respondent No. 3/North Eastern Coalfields for purchase of coal.

In furtherance of this purpose, the parties have entered into a Coal Supply

Agreement (CSA) (also referred to as Fuel Supply Agreement in this

petition, which term may be used interchangeably) on 18.07.2008 under

the terms and conditions set therein.

2. The petitioner on being asked by the respondent No. 4 to furnish

a bank guarantee for an amount equal to 10% of the notified based price

of the annual coal requirement for issuance of Letter of Assurance (LOA)

has furnished a bank guarantee for an amount of ₹ 1,12,00,000/- (Rupees

one crore twelve lakhs) only in favour of respondent No. 3 vide guarantee

dated 22.05.2008 issued by the State Bank of India, Commercial Branch,

Guwahati. Accordingly, the Letter of Assurance (LOA) was issued on

30.05.2008.

3. Vide letter dated 04.11.2008 the respondent No. 4 informed the

petitioner that the supply of coal for delivery could not be fulfilled as a

result of which import from outside is required. For such an operation, the

service charges has to be borne by the petitioner company, who was

compelled to agree having no other option.

4. Again, vide letter dated 16.10.2009, the respondent No. 5

informed the petitioner company that if it wants its coal to be delivered

against the value paid orders in time, it has to agree to the revised notified

price, for which the petitioner company has to agree to the revised price

and to pay the differential amount.

5. Yet again, on 01.07.2010, the respondent No. 3 has informed the

petitioner about revision of price on introduction of clean Energy Cess

charges for which the petitioner company has to deposit the balance

deferential amount for further despatch, to which the petitioner having no

option has to agree.

6. The respondent No. 5 vide letter dated 13.06.2011 then asked

the petitioner to increase the price of security deposit on the basic price of

the highest value of coal, failing which the entire Bank Guarantee shall be

encashed.

7. Since the prices were increased to almost 55% of the prices

agreed, the petitioner was left with no option, but to surrender the

Agreement on the import of coal, conveyed to the respondents vide letter

dated 27.09.2011.

8. The respondent No. 5 vide letter dated 05.01.2012 has drawn the

attention of the petitioner to the Government Notification dated

30.12.2011 whereby the system of grading of coal was discontinued as a

result of which the price of coal stands revised.

9. The respondent No. 3 vide invoice dated 11.05.2012 has

demanded that the petitioner pay an amount of ₹ 57,09,500/- (Rupees

fifty-seven lakhs, nine thousand and five hundred) only within 90 days as

compensation for short lifting of the coal for the year 2011-12, failing

which the amount will be deducted from the current credit balance lying

with the respondent company.

10. The respondent No. 3 through its General Manager has issued

letter dated 29.05.2012 upon the petitioner which is a notice for

termination of the Fuel Supply Agreement (FSA) dated 18.07.2008 on the

ground that there was a short lifting of coal by the petitioner for the year

2011-12 which was less than 30% of the Annual Contracted Quantity

(ACQ) thus attracting clause No. 15.1.4 of the FSA.

11. In reply to the letter dated 29.05.2012, the petitioner has vide

letter dated 30.05.2012 informed the respondent No. 3 that the short lifting

of the coal was due to the hefty increase in the price of coal by more than

55% of what was agreed upon and has therefore sought for 30 days' time

to reply to the said letter.

12. The respondent No. 3 has also issued a Notice dated 04.09.2012

for extension of the validity of the Bank Guarantee submitted earlier for

the amount of ₹ 1,37,02,800/- (Rupees one crore, thirty- seven lakhs, two

thousand and eight hundred) only.

13. The petitioner being highly aggrieved by the action of the

respondent company in increasing the price of coal by 60% and the levy

of penalty as well as for issuing the notice of termination of the contract,

has approached the Guahati High Court (Shillong Bench) by way of a writ

petition being W.P.(C) No. 243(SH) 2012 and the Court vide order dated

26.11.2013 has allowed the prayer of the petitioner by holding that the

respondents has not suffered any loss and therefore, notice dated

11.05.2012 demanding compensation was set aside.

14. The respondent company however preferred a writ appeal

against the said order dated 26.11.2013 before a Division Bench of this

Court numbered as WA No. 2 of 2014 which was disposed of vide order

dated 29.09.2016 directing the parties to take recourse to the settlement

mechanism provided in the agreement.

15. Pursuant to the direction of the Division Bench of this Court, the

representatives of the petitioner and the respondent company,

respectively, held a number of meetings on the following appeals made by

the petitioner being:

i. Waiver of ₹ 57,09,500.00 (Rupees fifty-seven lakhs, nine

thousand and five hundred ) only claimed as compensation

by the Coal India Limited for short lifting for the period

2011-12;

ii. Waiver of forfeiture of security deposit in the form of Bank

Guarantee for the amount of ₹ 1,37,02,800.00 (Rupees one

crore, thirty-seven lakhs, two thousand and eight hundred);

iii. Cancellation of notice of termination of FSA dated

18.07.2008;

iv. To allow recalculation of the compensation for the year

2011-12 as per the FSA dated 18.07.2008.

16. The respondent company vide letter dated 08.06.2018 has

informed the petitioner of the decision taken on 10.07.2017 as regard the

appeals made by the petitioner and in effect has accepted the appeal for

waiver of compensation of ₹ 57,09,500.00 (Rupees fifty-seven lakhs, nine

thousand and five hundred) but has however rejected the appeal for non-

termination of the FSA and non-forfeiture of the Bank Guarantee of ₹

1,37,02,800/- (Rupees one crore, thirty-seven lakh, two thousand and

eight hundred) only.

17. Not being satisfied with the culmination of the proceedings

between the parties herein as regard the manner in which the appeal of the

petitioner company was disposed of by the respondent company which

has not conceded to most of the demand made, the petitioner has

accordingly approached this Court with this instant writ petition with a

prayer to declare as illegal the clauses 4.5, 9.1,9.2 and 15 of the said Coal

Supply Agreement and also to quash the invoice dated 11.05.2012, Notice

dated 29.05.2012, Minutes of the meeting dated 10.07.2017 and the Final

Order dated 08.06.2018.

18. Heard Dr. A. Saraf, learned Sr. counsel for the petitioner who

has submitted that the issue to be decided herein is whether liquidated

damages can be imposed, if there is no loss to the party under Section 73

of the Indian Contract Act. Though there was short lifting of the coal by

the petitioner because of the increase of price upto 55%, the fact is that the

respondent No. 3 has sold the coal to some other party at a huge profit.

19. That the respondent company has imposed liquidated damages

for short lifting of the coal taking recourse to clause 4.5 of the Agreement

cannot be contemplated as facts would prove that no loss was incurred by

the respondent company. Demand for liquidated damages is not automatic

as proof of loss has to be shown by the respondent company and penalty

cannot be imposed as the stipulation in the said clause speaks of

compensation and not penalty.

20. Submitting that a perusal of clause 4.5 of the agreement would

show that the respondent company can demand compensation in case of

short lifting of coal, however compensation cannot be equated with

penalty. To further clarify this position, the learned Sr. counsel has cited

the case of Rathi Menon v. Union of India: (2001) 3 SCC 714 wherein at

para 24, the term compensation was explained as " ... though the word

"compensation" is not defined in the Act or in Rules it is the giving of an

equivalent....." and also the case of Smt. Sova Ray & Anr v. Gostha

Gopal Dey & Ors (1988) 2 SCC 134 para 7 parts of which reads as " ...

The expression 'penalty' is an elastic term with many different shades of

meaning but it always involves an idea of punishment..."

21. The learned Sr. counsel has submitted that the impugned

demand notice and the notice of termination of the CSA issued by the

respondent company amounts to imposition of penalty which is

impermissible in law as was held in the case of Maya Devi v. Lalta Prasad

(2015) 5 SCC 588 para 19 when it was held that "...The imposition and

recovery of penalty on breach of a contract is legally impermissible under

the Contract Act..."

22. In this regard, the learned Sr. counsel has referred to certain

decisions in which the term liquidated damages has been explained, viz;

the case of Fateh Chand v. Balkishan Dass: (1964) 1 SCR 515, para 8,

9, 15 & 16, Maya Devi v. Lalta Prasad: (2015) 5 SCC 588, para 19, 24,

26, Kailash Nath Associates v. Delhi Development Authority & Anr:

(2014) 4 SCC 136, para 43, 43.1, 43.2, 43.3, 43.4, 43.5, 43.6, 43.7 & 44.

23. The learned Sr. counsel has also referred to the order dated

26.11.2013 passed by the Single Bench of this Court in WP(C) No.

243(SH) of 2012 wherein at para 8 of the same, it was clearly observed

that an admission was made by the learned Sr. counsel for the respondents

that on failure of the petitioner to lift the coal, the same was subsequently

sold and as such, no loss was incurred by the respondent company. It is

submitted that though this order was set aside by the Division Bench of

this Court since the matter was referred for mediation and settlement, the

fact remains that the coal was not lying in the stock of the respondent

company, but was sold at a profit. There is nothing in the pleadings of the

respondent company to show that the coal was not sold and because of the

short lifting by the petitioner, loss was caused to the respondent company.

The only pleading is that because the clause in the agreement provided for

compensation in case of short lifting, the petitioner is therefore liable to

pay the compensation.

24. Mr. M. Singh, learned Sr. counsel for the respondents No. 2-5

has countered the submission and contentions made by the learned Sr.

counsel for the petitioner by stating at the outset, that coal is considered

an essential commodity and is scarce and in the recent past, there has

arisen an anomalous situation where the distribution of coal in the country

was not channelled properly resulting in genuine users not getting it. This

led to a number of litigation in the courts and finally, a Constitutional

Bench of the Supreme Court has directed the Government to bring out a

policy to prevent misuse of coal, such policy to include putting stringent

conditions in the contract. In this regard, the case of M/s Ashoka

Smokeless Coal India Pvt. Ltd v. Union of India & Ors: (2007) 2 SCC

640 para 188, 89 & 190 was cited by the learned Sr. counsel to submit that

when the terms of the contract between the parties herein was prepared,

this aspect of the matter was taken note of.

25. Since the petitioner company has failed to comply with the terms

of the contract, that is, there was no lifting of the coal during the relevant

period, only then the respondent Company, in view of the demand in the

market and the fact that the space was needed, diverted the coal, not with

a profit oriented motive, but for the purpose of circulation of the same.

26. Another contention raised by the learned Sr. counsel for the

respondents No. 2-5 is that under the contract agreement between the

parties, clause 16 speaks of 'Force Majeure' which is a circumstance or

situation which arises in course of the contractual period causing loss to

either parties not attributable to any specific action on their part. However,

the proviso to the said clause stipulates that a Force Majeure act shall not

include economic hardship, equipment failure or breakdown other than

those specifically set forth. In the case of the petitioner, any loss cause out

of short lifting or non-lifting cannot be a condition for exemption or for

demand of compensation.

27. The learned Sr. counsel has also confirmed that in compliance

with the order dated 29.09.2016 of the Division Bench of this Court

directing for settlement and negotiation between the parties, the petitioner

company having set out its request considered as appeal before the

respondent company, after sitting together and having considered the

issues presented, the respondent company has, finally taking everything

into consideration have, vide the letter No M&S/Legal/Meghalaya

Cements/365 dated 08.06.2018 informed the petitioner company of the

final action taken by Coal India Ltd. against the various appeals made by

the petitioner company in the meeting dated 10.07.2017 to the extent that

only the appeal for waiver of compensation of ₹ 57,09,500.00 (Rupees

fifty-seven lakhs, nine thousand and five hundred) only was allowed.

28. Yet another contention raised by the learned Sr. counsel for the

respondents No. 2-5 is on the issue of maintainability of this writ petition.

It is submitted that if on the issue of compensation or loss suffered in terms

of the contractual provisions, whether a writ would lie?

29. Referring to the case of Fateh Chand (supra) relied upon by the

petitioner, the learned Sr. counsel for the respondents No. 2-5 has

submitted that in that case, there was a contractual dispute which arises

from a suit which was dealt with in a complete trial and eventually, the

matter reached the Supreme Court where the Hon'ble Supreme Court has

decided the matter as reflected in the said judgment. However, in this

instant case, there is no trial, but a writ was instead filed. It is therefore

asserted that the ratio of this judgment is not applicable to the case of the

petitioner herein.

30. The issue of 'res judicata' has also been raised by the learned Sr.

counsel for the respondents No. 2-5 who has submitted that the petitioner

in this writ petition has made identical prayer as those made in the earlier

writ petition which has since been disposed of by this Court. Whether

such successive writ applications can be moved in the same court on the

same cause of action? The answer is no, since the provision of res judicata

as incorporated in Section 11 of the Code of Civil Procedure (CPC)

though may not strictly be applicable to successive writ applications,

however the general principle of res judicata is applicable as could be

noticed from a number of decisions of the Apex Court and High Courts,

some of which are cited being the case of M.S.M. Sharma v. Dr. Shree

Khrishna Sinha & Ors: AIR 1960 SC 1186 para 8; Radha Shyam Datta

& Ors v. Patna Municipal Corporation: AIR 1956 Patna 182, para 12;

Shamsul Haque Dastgirali v. The Assistant Custodian of Evacuee

Property: AIR 1958 Madhya Pradesh 82, para 2; Daryao & Ors v. State

of U.P. & Ors: AIR 1961 SC 1457, para 9 & 10.

31. It is also the submission of the learned Sr. counsel for the

respondents No. 2-5 that the dispute between the parties herein raised

some pertinent questions on the factual aspect, as to what would be the

exact loss caused to the petitioner or the respondent company, or if the

allegation that the respondent company has sold off the coal to others at a

huge profit, then what is the amount received is also a question of facts

which can only be determined by a civil court of competent jurisdiction

and as such, the petitioner cannot raise these issues before a writ court.

32. As to whether a writ is maintainable in a contractual matter, the

learned Sr. counsel has cited the case of Kerala State Electricity Board &

Anr v. Kurien Kalathil & Ors: (2000) 6 SCC 293, para 10, 11 & 12

wherein the Hon'ble Supreme Court has held that if a term of contract is

violated, ordinarily the remedy is not a writ petition under Article 226 of

the Constitution of India. The case of Godavari Sugar Mills Limited v.

State of Maharashtra & Ors: (2011) 2 SCC 439, para 8 was also cited in

this regard in which it was held that a petition under Article 226 of the

Constitution of India will not be entertained to enforce a civil liability

arising out of a breach of contract.

33. Another issue raised by the learned Sr. counsel for the

respondents is whether in a non-statutory contractual matter on the ground

that such contract is based on the superior bargaining power of one party

to such contract and whether the concept of arbitrariness,

unreasonableness, unfairness or irrationality can be brought before a writ

court while making a challenge to the same, considering the fact that the

principles of natural justice, fair play and legitimate expectation may not

have any role to play in such a situation. It is submitted that the Hon'ble

Supreme Court while dealing with a case of non-statutory contract has

held that the application of the principles or natural justice has no role to

play in such cases. This refers to the case of M/s Radhakrishna Agarwal

& Ors v. State of Bihar & Ors: (1977) 3 SCC 457, para 23 & 25.

34. The case of Bareilly Development Authority & Anr. v. Ajai Pal

Singh & Ors: (1989) 2 SCC 116 para 21, 22 & 23 as well as the case of

Assistant Excise Commissioner & Ors. v. Issac Peter & Ors: (1994) 4

SCC 104, para 26 was cited to support the case of the respondents as far

as the applicability of the principles of arbitrariness, fair play and

unreasonableness is concerned.

35. It is finally submitted that under the facts and circumstances of

the case of the parties, this petition is devoid of merits and the same has to

be dismissed. Alternatively, this Court, if deemed fit can also direct the

petitioner company to approach the competent civil court for redressal of

its grievances.

36. In reply, the learned Sr. counsel for the petitioner has submitted

that the contention of the respondents that a writ application will not lie in

contractual matters is not the correct law as the Hon'ble Supreme Court in

the case of Unitech Limited and Ors v. Telengana State Industrial

Infrastructure Corporation(TSIIC) & Ors: 2021 SCC Online SC 99 has

clearly held that the exercise of jurisdiction of the Court under Article 226

of the Constitution cannot be ousted only on the basis that the dispute

pertains to the contractual arena. This is for the simple reason that the State

and its instrumentalities are not exempt from the duty to act fairly merely

because in their business dealings they have entered into the realm of

contract (para 41).

37. The argument advanced by the parties have been duly taken note

of by this Court. It may however be pointed out that the respondent No.

1/Union of India represented by the learned DSG has not advanced any

argument being considered only a formal party.

38. The parties having been heard in this matter, the issue of 'res

judicata' may be decided at the outset before one proceed to discuss the

contentious issues involved.

39. The authorities cited by the learned Sr. counsel for the

respondents as regard 'res judicata' would reveal that it has been accepted

that the provisions of res judicata as incorporated in Section 11 of the Code

of Civil Procedure may not strictly apply to successive writs application,

however the general principle of res judicata can be made applicable to

writ applications also. Consequently, once a decision is made on merits

under Article 226, a subsequent writ cannot be moved in the same court

on the same cause of action.

40. The contention of the respondents in this case is that this Court

on an earlier occasion has already dealt with the same facts and prayer of

the petitioner for issuance of directions or order on the challenge to

clauses 4.5, 9.1, 9.2 and 15 of the CSA dated 18.07.2008 as well as the

invoices for compensation dated 11.05.2012 along with the termination

notice dated 29.05.2012, the same having been decided in W.P.(C) No

243(SH) of 2012 vide order dated 26.11.2013 and which decision was

later overturned in W.A. No 2 of 2014 vide order dated 29.09.2016,

therefore the petitioner seeking similar relief against the respondents in

this instant writ petition cannot be allowed, being hit by the principle of

res judicata.

41. Though the contention of the respondents as regard the identical

contents of the prayer in the earlier petition and that this petition is correct,

however the respondent has failed to notice that the developments in the

dispute between the parties herein did not end only on the disposal of the

matter in W.P. (C) No 243(SH) of 2012, but on appeal, the Division Bench

of this Court in W.A. No. 2 of 2014 has directed the parties to take

recourse to the settlement provision made available in the FSA itself and

has annulled the decision made in W.P. (C) No 243(SH) of 2012 only to

allow the parties to approach the matter on a fresh platform.

42. In this regard, the observations of the Division Bench may be

culled out to come to an understanding that having been relegated to the

'Settlement Mechanism' found within the provisions of the CSA, the field

is open to the parties to agitate the matter ab initio. The observations reads

thus:

".... When the parties are being relegated to the agreed settlement, it does appear necessary that the order impugned be annulled and to make it clear that none of the observations made in the impugned order or even in this judgment shall be having any bearing on settlement of dispute by the parties in terms of the mechanism provided in the agreements..."

43. It is also on account of the said direction of the Division Bench

of this Court that the petitioner company has made an appeal before the

respondent company for waiver of the compensation amount of ₹

57,09,500/- (Rupees fifty-seven lakhs, nine thousand and five hundred)

only for the year 2011-12 and refund of Bank Guarantee of ₹ 1,37,02,800/-

(Rupees one crore, thirty-seven lakhs, two thousand and eight hundred)

only besides recalling of the termination notice, that the final order of the

respondent company conveyed through communication dated 08.06.2018

was made wherein only one appeal, that is waiver of compensation of ₹

57,09,500.00 was accepted and the rest rejected. This, in the opinion of

this Court has changed the texture of the litigation and additional cause of

action has arisen which has paved the way for the petitioner to approach

this Court by way of this instant writ petition. The principle of res judicata

is therefore found not applicable to the present case.

44. Much has been said by the parties as to whether a writ is

maintainable in a contractual matter to the extent that relevant authorities

have been cited by both sides, for and against. The case of Kerala State

Electricity Board (supra) and other similar cases have been cited by the

respondents to impress upon this Court that a dispute as regard the terms

of agreement in a contract cannot be the subject matter of a writ

proceedings, but would have to be pursued before a competent civil court.

45. As a counter to this, the petitioner have maintained that the Apex

Court have, time and again, in appropriate cases, held that a writ petition

is maintainable in contractual matter involving the Instrumentalities of the

State. The case of ABL International Ltd. & Anr v. Export Credit

Guarantee Corporation of India Ltd. & Ors: (2004) 3 SCC 553 has been

cited to support this contention wherein at para 27 of the same, it was held

that:

"27. From the above discussion of ours, the following legal principles emerge as to the maintainability of a writ petition:

(a) In an appropriate case, a writ petition as against a State or an instrumentality of a State arising out of a contractual obligation is maintainable.

(b) Merely because some disputed questions of fact arise for consideration, same cannot be a ground to refuse to entertain a writ petition in all cases as a matter of rule.

(c) A writ petition involving a consequential relief of monetary claim is also maintainable."

46. Again, the case of Unitech Limited & Ors (supra) at para 41 was

also referred to which reads as follows:

"41. Therefore, while exercising its jurisdiction under Article 226, the Court is entitled to enquire into whether the action of the State or its instrumentalities is arbitrary or unfair and in consequence, in violation of Article 14. The jurisdiction under Article 226 is a valuable constitutional safeguard against an arbitrary exercise of state power or a misuse of authority. In determining as to whether the jurisdiction should be exercised in a contractual dispute, the Court must, undoubtedly eschew, disputed questions of fact which would depend upon an evidentiary determination requiring a trial. But equally, it is well-settled that the jurisdiction under Article 226 cannot be ousted only on the basis that the dispute pertains to the contractual arena. This is for the simple reason that the State and its instrumentalities are not exempt from the duty to act fairly merely because in their business dealings they have entered into the realm of contract. Similarly, the presence of an arbitration clause does oust the jurisdiction under Article 226 in all cases though, it still needs to be decided from case to case as to whether recourse to a public law remedy can justifiably be invoked. The jurisdiction under Article 226 was rightly invoked by the Single Judge and the Division Bench of the Andhra

Pradesh in this case, when the foundational representation of the contract has failed. TSIIC, a state instrumentality, has not just reneged on its contractual obligation, but hoarded the refund of the principal and interest on the consideration that was paid by Unitech over a decade ago. It does not dispute the entitlement of Unitech to the refund of its principal."

47. Looking into the facts and circumstances of this case, since the

contentious issue revolves around the interpretation of Clause 4.5, which

speaks of compensation, clause 9.1 and 9.2 which refers to the pricing of

the coal in question and finally clause 15 which is the provision for

termination of the Agreement, all other actions resorted to by the

respondent company being subsequent thereto, dispute on facts and

figures not really apparent so as to require a detailed delving into the same

by way of evidence, the controversy between the parties can be resolved

at this forum and as such, this Court is of the view that this writ is

maintainable.

48. Even otherwise, going by the history of the litigation between

the parties, the court was approached by the petitioner in the year 2012

and even almost ten years down the line, no closure of the same have been

made, this lapse of time is also a factor as to why this Court would choose

to end the dispute between the parties without sending the petitioner to a

civil court for institution of a suit. In this connection, para 54 of the ABL

International Ltd. case is referred to when it was held that :

"54. Apart from the above reasons given by us to interfere with the judgment of the Appellate Bench of the High Court, we have one other good reason why we should not drive the appellants

to a suit. The claim of the appellants was rejected by the respondent in the year 1994. The respondent challenged the basis of rejection by way of a writ petition in the year 1996. The objection as to the maintainability of the petition was rejected by the High Court by its judgment dated 15-5-1997. We are now in the end of the year 2003. We at this distance of time and stage of litigation, do not think it proper to relegate the parties to a suit. To direct the appellants to approach a civil court at this stage would be doing injustice to the appellants. In this view of ours, we are supported by a number of decisions of this Court like in Shambhu Prasad Agarwal v. Bhola Ram Agarwal:(2000) 9 SCC 714 wherein this Court though noticed the fact that the appellants had an alternate remedy for issuance of a letter of administration, it refused to dismiss the appeal on the grounds: (SCC p. 715, para 5) Since considerable time has elapsed, the interest of justice demands that the proceeding should come to an end as early as possible and that the appeal should not be dismissed merely on highly technical ground."

49. Moving forward, what is noticed is that one of the main focus of

the petitioner in this case, is the issue of compensation demanded by the

respondent company as is present in Clause 4.5 of the CSA which was

consequent to the failure of the petitioner company to lift the coal or for

short lifting of the coal, for which the said demand for compensation for

the year 2011-2012 was accordingly made. However, it is on record that

the respondents vide their communication dated 08.06.2018 has informed

the petitioner company that the waiver of demand for compensation of ₹

57,09,500/- (Rupees fifty-seven lakhs, nine thousand and five hundred)

only was allowed. Therefore, the argument of the petition on the issue of

compensation has now become unnecessary.

50. In fact, the only stand of the respondent company is that the

petitioner by short lifting of the coal, has violated the terms of the CSA

and as a result has cause loss of use of space and goodwill to the

respondent company which warrants that the Bank Guarantee be revoked

and the notice of termination be put to action. However, once the demand

for compensation has waived, which is clearly an admission on the part of

the respondents that no loss was caused as a result of short lifting of the

said coal by the petitioner company and also that the said coal was

subsequently sold to other parties, then, there is no question of forfeiture

of the security deposit and consequently, invocation of the Bank

Guarantee cannot be resorted to by the respondents.

51. The relevant provision of law upon which the concept of 'bank

guarantee' is founded is Sections 126 and 127 of the Indian Contract Act,

1872. A bank guarantee can be said to be an assurance given by a bank on

behalf of a customer which undertakes to pay or discharge the liability of

a debtor in case of any default. A bank guarantee essentially stems out of

a contractual obligation to reassure a third-party creditor that his financial

interest will not be affected in case of loss or in the event of default. By

issuing bank guarantee, a bank ordinarily undertakes to pay the amount

specified in the guarantee on demand made by a beneficiary in accordance

with the terms and conditions agreed to by the parties. A conditional

guarantee is one which presupposes a claim under the guarantee on proof

of breach of the terms of the contract or any loss occurring as a result of

such breach. The object of a bank guarantee is to ensure due performance

of the contract or it can also be towards security deposit for a contract.

52. Generally, courts would exercise restraint on prayer to injunct a

bank guarantee being invoked or to encash the same except on two

grounds namely; fraud and secondly, irretrievable injury, where a creditor

is restrained from exercising his right of encashment. If the bank guarantee

has come about as a result of fraud on the part of the creditor, the whole

transaction is vitiated. The other exception to the encashment of a bank

guarantee is irretrievable harm or injustice to one of the parties.

53. The prayer of the petitioner company in this case to restrain the

respondent company to encash the bank guarantee can only be on the

ground of irretrievable injury or injustice. In the case of Dwarikesh Sugar

Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd. & Anr: AIR

1997 SC 2477, the Hon'ble Supreme Court speaking on bank guarantee

has observed at para 20 as:

"20. Numerous decisions of this Court rendered over a span of nearly two decades have laid down and reiterated the principles which the Courts must apply which considering the question whether to grant an injunction which has the effect of restraining the encashment of a bank guarantee. We do not think it necessary to burden this judgment by referring to all of them. Some of the more recent pronouncements on this point where the earlier decisions have been considered and reiterated are Svenska Handelsbanken v. M/s. Indian Charge Chrome, (1994) 1 SCC 502: (1993 AIR SCW 4002), Larsen & Toubro Ltd. v. Maharashtra State Electricity Board, (1995) 6 SCC 68: (1975 AIR SCW 4134), Hindustan

Steel Workers Construction Ltd. v. G.S. Atwal & Co.

(Engineers) Pvt. Ltd. (1995) 6 SCC 76: (1995 AIR SCW 3821) and U.P. State Sugar Corporation v. Sumac International Ltd. (1997) 1 SCC 568: (1997 AIR SCW 694). The general principle which has been laid down by this court has been summarised in the case of U.P. State Sugar Corporation's case as follows: (at p. 697 of AIR SCW):

"The law relating to invocation of such bank guarantees in by now well settled. When in the course of commercial dealings an unconditional bank guarantee is given or accepted, the beneficial is entitled to realize such a bank guarantee in terms thereof irrespective of any pending disputes. The bank giving such a guarantee is bound to honour, it as per its terms irrespective of any dispute raised by its customer. The very purpose of giving such a bank guarantee would otherwise be defeated. The Courts should, therefore, be slow in granting an injunction to restrain the realization of such a bank guarantee. The courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very foundation of such a bank guarantee. Hence if there is such a fraud of which the beneficiary seeks to take the advantage, he can be restrained from doing so. The second exception relates to cases where allowing the encashment of an unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned. Since in most cases payment of money under such a bank guarantee would adversely affect the bank and its customer at whose instance the guarantee is given, the harm or injustice contemplated under this head must be of such an exceptional and irretrievable nature as would override the terms of the guarantee and the adverse effect of such an injunction on commercial dealings in the country."

Dealing with the question of fraud it has been held that fraud has to be an established fraud. The following observations of Sir John Donaldson, M.R. in Bolivinter Oil S.A. v. Chase Manhattan Bank, (1984) 1 All ER 351, are apposite:

"The wholly exceptional case where an injunction may be granted is where it is proved that the bank knows that any demand for payment already made or which may thereafter be made will clearly be fraudulent. But the evidence must be clear both as to the fact of fraud and as to the bank's knowledge .It would certainly not normally be sufficient that this rests on the uncorroborated statement of the customer,

for irreparable damage can be done to a bank's credit in the relatively brief time which must elapse between the granting of such an injunction and an application by the bank to have it charged."

(emphasis supplied)

54. On the facts of this case, as noted above, the fact that Clause 4.5

binds the parties as far as short lifting of the coal is concerned, inasmuch

as, it was incumbent upon the purchaser/petitioner company to maintain

the agreed level of ACQ (Annual Contracted Quantity), short lifting of the

same to be visited by a demand of compensation, this being part of the

Agreement, the same cannot be questioned by any of the parties. However,

as observed, the fact that no compensation can be demanded as there was

no loss incurred as a result of the short lifting since the same coal was sold

off to some other party, the petitioner company cannot be faulted for

seeking injunction on invocation of the security deposit/bank guarantee as

in the opinion of this Court, invocation of the bank guarantee would result

in irretrievable loss and injury to the petitioner company. Considering the

time factor as regards the proceedings, this Court having observed that

sending the parties to the civil court would not serve the ends of justice,

pending final settlement between the parties herein, restraining the

respondent company from encashing the bank guarantee is reasonable and

justifiable.

55. What flows from the above proposition is that the respondent

company cannot be allowed to gain from the drawback of short lifting of

the coal by the petitioner company solely on the ground that no loss was

incurred in the process thereof, the notice for termination of the

Agreement is also not found justified by this Court. The same is not

allowed.

56. Consequently, the prayer of the petitioner is found reasonable

and the same is hereby allowed.

57. On an overall analysis, taking into account the import of the

many authorities cited by the parties, some of which have been considered

relevant herein and was accordingly quoted or referred to, others which

are not found relevant and thus not quoted, this Court is of the considered

opinion that it is not open to the respondent company to impose penalty

on the petitioner company and to invoke the said bank guarantee as well

as to issue the said notice for termination of the Agreement.

58. Consequently, the prayer of the petitioner is found reasonable

and the same is hereby allowed.

59. The respondent No. 3 is hereby directed to refund the Bank

Guarantee, if already invoked and to refrain from putting into effect the

notice for termination of the CSA dated 29.05.2012.

60. Since the dispute between the parties could not be resolved

through the settlement process as directed by the Division Bench of this

Court and since the petitioner as a result of the breakdown of the same has

now approached this Court with this instant petition, the matter having

been finally decided judicially herein, it stands to reason that the final

order of the respondent company dated 08.06.2018 is hereby set aside and

quashed to the extent indicated above.

61. Petition disposed of. No costs.

Judge

Meghalaya 26.10.2022 "D. Nary, PS"

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter