Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Oil And Natural Gas Corporation ... vs M/S.Shiv-Vani Oil And Gas Exploration
2025 Latest Caselaw 6887 Mad

Citation : 2025 Latest Caselaw 6887 Mad
Judgement Date : 10 September, 2025

Madras High Court

M/S.Oil And Natural Gas Corporation ... vs M/S.Shiv-Vani Oil And Gas Exploration on 10 September, 2025

Author: N.Anand Venkatesh
Bench: N.Anand Venkatesh
                                                                                      O.P.No.1007 of 2015



                              IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                               DATED: 10.09.2025

                                                        CORAM

                          THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH

                                                  O.P.No.1007 of 2015

                     M/s.Oil and Natural Gas Corporation Limited,
                     Having its registered Office at
                     Jeevan Bharti, Tower II, 124 Cannaught
                     Circus,
                     New Delhi and site office at Godavari Bhavan,
                     1st Floor, B Wing, Base Complex,
                     Rajahmundry-533 106.
                                                                                            Petitioner
                                                       Vs.
                     1.M/s.Shiv-Vani Oil and Gas Exploration
                     Service Limited,
                       (Amalgamated with SVUL Projects Limited)
                       Having its Registered Office,
                       at Tower-1, 5th Floor, NBCC Plaza,
                       Sector-5, Pushp Vihar, Saket,
                       New Delhi-110 017.

                     2.Hon'ble Mr.Justice N.V.Balasubramanian(Retd).,
                       Sole Arbitrator,
                       No.40, Sankarapuram,
                       Alemelumangapuram,
                       Mylapore, Chennai-600 004.

                     3.The Official Liquidator,
                       High Court, Delhi.
                                                                                         Respondents

                     [*R3 is impleaded vide order dated 25.09.2019 in A.No.7199 of 2019
                     and condone the delay in carrying out the amendement as per order
                     dated 23.01.2020 in A.No.113 of 2020].


                     1/18



https://www.mhc.tn.gov.in/judis             ( Uploaded on: 12/09/2025 12:07:21 pm )
                                                                                              O.P.No.1007 of 2015



                     Prayer: Original Petition filed under Section 34(2)(A)(IV) & (V) and
                     (B)(2) r/w. Section 16(6) of the Arbitration and Conciliation Act, 1996,
                     to set aside the arbitration award dated 27.08.2015 passed by the second
                     respondent which had arisen out of the dispute between the petitioner
                     and the first respondent in Contract dated 11.08.2000 and direct the first
                     respondent to pay the costs of the petition.

                                  For Petitioner           :   Mr.A.Abdul Hameed
                                                               Senior Counsel

                                  For Respondents         :    No appearance
                                                               for R1 and R2
                                                               Mr.S.Gopalakrishnan for R3


                                                               ORDER

This Original Petition has been filed under Section 34 of the

Arbitration and Conciliation Act, 1996, against the award dated

27.08.2015 passed by the Sole Arbitrator arising out of a dispute between

the petitioner and the first respondent in a contract dated 11.08.2000.

2. Heard Mr.A.Abdul Hameed, learned Senior Counsel appearing

for the petitioner and Mr.S.Gopalakrishnan, learned counsel appearing

for the third respondent.

3. On 11.08.2000, a contract was entered into between the

petitioner and the first respondent for Charter Hire of 1 No.200 Ton

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

Work Over Rig, together with all equipments/accessories for Work Over

Operation in the KG Basin of the petitioner in the State of

Andhra Pradesh. This contract was awarded in favour of the first

respondent pursuant to the tender floated by the petitioner. It is stated

that the first respondent failed to perform the obligations under the

contract and as a result, the liquidated damages were levied and

ultimately, the contract was terminated vide notice dated 04.09.2001 with

effect from 30.09.2001.

4. The first respondent was permitted to continue the work over

operation, subject to certain conditions contained therein and ultimately,

the contract came to an end on 11.10.2002.

5. The first respondent issued the trigger notice dated 28.01.2006

under Section 21 of the Arbitration and Conciliation Act, 1996 [for

brevity 'the Act'] for referring the disputes to the Arbitrator. Thereafter,

the Sole Arbitrator was appointed and the arbitration proceedings

commenced on 09.11.2010.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

6. The first respondent filed the claim statement on 10.12.2010 and

the petitioner filed reply and counter claim on 10.03.2011, and a

rejoinder was also filed by the first respondent on 29.04.2011. The chief

and cross-examination was over on both sides on 10.04.2013 and the first

respondent commenced their arguments on 15.06.2013 and completed on

25.08.2013.

7. The first respondent filed a memo dated 06.09.2013 for receipt

of three additional documents. Objections were filed by the petitioner on

26.09.2013. However, the Arbitrator passed an order on 29.09.2013

taking those documents on file and marked them as Ex.C37 to Ex.C39.

Thereafter, arguments were addressed on both sides and the impugned

award dated 27.08.2015 came to be passed by the Sole Arbitrator. The

same has been put to challenge in the present petition.

8. The main ground that was urged by the learned Senior Counsel

appearing on behalf of the petitioner is that the claim made by the first

respondent was hopelessly barred by limitation. The learned Senior

Counsel further submitted that the Arbitrator, without there being any

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

evidence, and after giving a finding to that effect, proceeded to award a

sum of Rs.15,00,000/- in favour of the first respondent towards

Claim No.5, which pertained to reimbursement towards costs for

drill strings and other accessories which remained in the well.

9. Per contra, the learned counsel appearing on behalf of the third

respondent submitted that the first respondent is presently under the

administration of the Official Liquidator, who is the third respondent.

The learned counsel submitted that there is no patent illegality in the

reasoning given by the learned Arbitrator warranting interference of this

Court. Hence, he sought for dismissal of this petition.

10. It is not in dispute that the notice of termination of contract was

given on 04.09.2001, with effect from 30.09.2001. It is also not in

dispute that the contract came to an end on 11.10.2002. The trigger

notice before initiation of arbitration proceedings was issued by the first

respondent only on 28.01.2006. After the appointment of the Arbitrator,

the claim statement was filed by the first respondent. One of the main

objections that was raised in the reply filed by the petitioner is that the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

claim made by the first respondent is barred by limitation and hence, the

entire claim is liable to be rejected. For this reply, the first respondent has

filed a rejoinder and has merely stated that the claim made by the first

respondent is within the period of limitation.

11. At this juncture, it will be relevant to take note of the written

arguments filed on the side of the first respondent and the portion which

dealt with the issue of limitation. For appreciation, the same is extracted

hereunder:-

“XV. Whether the claim made by the claimant is within the period of limitation?

A.As per Ex.P22 issued by the respondent, the contract came to an end on 11.10.2002. The claimant raised the claims by various letters between 11.10.2002 and 10.10.2005 i.e. within a period of 3 years. The letters are dated 05.09.2000, 05.10.2000, 27.06.2001, 22.01.2002, 28.01.2002, 06.03.2001, 27.02.2002, 27.05.2002, 30.03.2002, 01.04.2003, 26.08.2004, 12.01.2005, 21.02.2005, 28.04.2005 and 01.07.2005 which are marked as Ex.P.10, Ex.P.11, Ex.P.12, Ex.P.13, Ex.P.19, Ex.P.21, Ex.P.23, Ex.P.24, Ex.P.26, Ex.P.28, Ex.P.29, Ex.P.30, Ex.P.31, Ex.P.32 and Ex.P.33 respectively.”

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

12. The above stand taken by the first respondent makes it clear

that the contract came to an end on 11.10.2002 and thereafter, the first

respondent was continuously sending communications to the petitioner

upto the year 2005, and there was nothing to show that the petitioner

responded to any of those communications. Thereby, the first respondent

has virtually attempted to extend the period of limitation by means of

sending repeated representations/communications to the petitioner.

13. Even in the written arguments filed on the side of the

petitioner, a specific stand was taken to the effect that the contract came

to an end in the year 2002 and the claim has not been made within the

period of limitation of 3 years thereafter, and therefore, the claim made

by the first respondent is barred by limitation.

14. After the written submissions were filed, arguments on the side

of the first respondent was also completed, which is evident from the

proceedings recorded by the learned Arbitrator which is found at Page

Nos.241 to 243 in the paper book. At this point of time, a memo dated

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

06.09.2013 came to be filed on the side of the first respondent. For

proper appreciation, the memo is scanned and extracted hereunder:-

15. The three documents that were relied upon by the first

respondent is available at Page Nos.251 to 256 in the paper book. For

this memo, the petitioner filed objections. The petitioner took a stand that

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

the documents relied upon are attempted to be brought in belatedly,

without assigning any reasons, and that there is no proof regarding the

issuance of receipt of documents mentioned at Serial Nos.2 and 3 of the

memo and that the document in Serial No.1 is inadmissible in evidence.

16. The learned Arbitrator, through proceedings dated 29.09.2013,

considered the memo and objections and decided to take those

documents on file and marked those documents as Ex.C37 to Ex.C39,

subject to the objections raised by the petitioner. Thus, even though the

Arbitrator did not deal with the objections in the proceedings dated

29.09.2013, the Arbitrator was expected to deal with the objections

atleast while passing the award.

17. It is relevant to take note of one vital fact which missed the

attention of the learned Arbitrator. The learned Arbitrator failed to see

that these three documents were not supported by any pleadings. The

appropriate manner in which these three documents ought to have been

brought on file is by permitting the claimant to file additional statement

and explain the purport of those documents and the stand that is sought

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

to be taken by relying upon those documents. Instead, the Arbitrator

thought it fit to straight away admit those documents without pleadings.

Apart from that, these documents ought to have been marked through the

witness who should have explained the above three documents and the

scope of the bank entries that were relied upon by the first respondent. If

this procedure had been followed, the petitioner would have had an

opportunity to file a reply for the additional statement, and also would

have cross-examined the witness pertaining to the three additional

documents that were sought to be brought in by the first respondent

towards the fag end of the proceedings. The denial of this opportunity to

the petitioner would clearly tantamount to violation of the principles of

natural justice. The reason for rendering such a finding will get more

clearer in the later portion of this order.

18. The learned Arbitrator while dealing with the issue of

limitation has rendered the following finding:-

“81. I am of the view that though the contract came to an end on 11.10.2002, the last payment against the said work was made by the respondent to the claimant Company on 28.03.2003 and the claimant has issued a notice dated

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

28.01.2006 in Ex.C38 for appointment of Arbitrator and the Chennai office has forwarded the same to the Rajahmundry office the letter of the claimant requesting for appointment of Arbitrator on 31.01.2006 (Ex.C39). But the Learned Counsel for the respondent has denied the same and stated that the payment made on 28.03.2003 (Ex.C37) cannot be relied upon. However, there is no evidence from the respondent to establish that no payment was made on 28.03.2003 nor there is any evidence from the respondent to show when the respondent has made the last payment and in absence of final bill, the last date of payment made by the respondent can be considered as the starting point of limitation. The respondent also had not produced any evidence to show that they have denied the claims made by the claimant prior to 28.3.03 to the several letters sent by the claimant for commencement of period of limitation. I am therefore of the view that mere denial by the Learned Counsel for the respondent that no payment was made by respondent on 28.3.03 is not acceptable in the absence of any proof of the non-payment on 28.3.2003. The respondent could have produced the copies of account books showing when the last payment was made to the claimant under the agreement or when the respondent had denied the claims of the claimant made in several letters referred to prior to 11.10.2002, when the contract came to an end.”

19. The learned Arbitrator has given a finding as if the petitioner

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

has made the last payment against the work done by the first respondent

on 28.03.2003, by relying upon the entry that was made in the statement

of account which was marked as Ex.C37. If such a finding has to be

rendered, the learned Arbitrator ought to have explained as to whether

such a payment actually was received from the petitioner, and even if it is

assumed that it is received from the petitioner, whether it pertained to the

contract that is under dispute. The bank entry is completely silent about

these facts. However, the Arbitrator thereafter proceeds to put the burden

of proof on the petitioner and has held that the petitioner has failed to

show that no such payment was made by them on 28.03.2003 and the

petitioner has failed to show that such last payment was made in the

absence of the final bill. On this premise, the Arbitrator has calculated

the limitation from 28.03.2003 and has concluded that the trigger notice

was issued on 28.01.2006 and hence, the claim made by the first

respondent is within the time.

20. This is further elaborated by the Arbitrator at paragraph No.82

of the award.

21. In the considered view of this Court, the above finding of the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

learned Arbitrator suffers from patent illegality. It is not necessary for

this Court to burden this order with all the citations and it will suffice to

take note of the latest judgment of the Hon'ble Apex Court in the case of

OPG Power Generation Private Limited vs. Enexio Power Cooling

Solutions India Private Limited and another reported in

2025 (2) SCC 417. The Hon'ble Apex Court has held that the ground of

patent illegality is available for setting aside a domestic award, if the

decision of the Arbitrator is found to be perverse or so irrational that no

reasonable person would have arrived at it. Such patent illegality can also

arise in a case where a finding is based on no evidence at all or where an

award ignores a vital evidence while arriving at a decision. Even an

award without reasons would suffer from patent illegality. Such patent

illegality will also arise in a case where the Arbitrator decides a matter

not within his jurisdiction or there is a violation of the principles of

natural justice.

22. In the case in hand, the impugned award suffers from patent

illegality since it is vitiated due to violation of principles of natural

justice and also due to the fact that the findings were rendered on the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

issue of limitation based on no evidence.

23. As was observed supra, the basis for admitting three

documents as Ex.C37 to Ex.C39 was not supported by pleadings and it

was not marked through a witness. As a result, the petitioner lost an

opportunity to file a reply for additional statement, which should have

been filed by the first respondent, and the petitioner also lost an

opportunity to cross-examine the witness, if those documents had been

marked through a witness.

24. The learned Arbitrator expected the petitioner to prove that the

petitioner did not make any payment to the first respondent on

28.03.2003 and no final bill was raised for such payment. Even though

the Indian Evidence Act does not apply to the arbitration proceedings,

certainly the principles of evidence will apply during such proceedings.

If the first respondent was relying upon certain documents in order to

save the claim from being knocked out on the ground of limitation, it is

the first respondent who should have discharged the burden and the

burden never shifts to the petitioner till the first respondent discharges

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

the burden. Therefore, the learned Arbitrator went wrong in strongly

relying upon the bank entry dated 28.03.2003 and thereby, gave a finding

that the claim is within the limitation. In other words, a claim which

otherwise was hopelessly barred by limitation, all of a sudden, sees the

light at the end of the tunnel because of a one bank entry dated

28.03.2003. In such an event, the entire burden was on the first

respondent to explain those bank entries to sustain the claim. By no

stretch, the burden could have been shifted on the petitioner.

25. The last issue pertains to the counter claim made by the

petitioner. If the very claim made by the first respondent is barred by

limitation, it goes without saying that the counter claim also cannot be

considered on the very same ground. In any case, the learned Arbitrator

has given sufficient reasons for rejecting the counter claim made by the

petitioner.

26. The upshot of the above discussion leads to the only

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

conclusion that the award dated 27.08.2015 passed by the learned

Arbitrator suffers from patent illegality and it can be brought within the

scope of Section 34(2)(a)(iv) of the Act.

27. Accordingly, the award dated 27.08.2015 passed by the Sole

Arbitrator is hereby set aside and this Original Petition stands allowed.

There shall be no order as to costs.

10-09-2025

ssb

Index:Yes

Speaking order

NCC:Yes

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

To

1.M/s.Shiv-Vani Oil and Gas Exploration Service Limited, (Amalgamated with SVUL Projects Limited) Having its Registered Office, at Tower-1, 5th Floor, NBCC Plaza, Sector-5, Pushp Vihar, Saket, New Delhi-110 017.

2. The Sole Arbitrator, No.40, Sankarapuram, Alemelumangapuram, Mylapore, Chennai-600 004.

3.The Official Liquidator, High Court, Delhi.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

N.ANAND VENKATESH, J

ssb

10.09.2025

https://www.mhc.tn.gov.in/judis ( Uploaded on: 12/09/2025 12:07:21 pm )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter