Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vishnu Infra Pvt. Ltd vs Engineering Projects India Ltd
2025 Latest Caselaw 7536 Mad

Citation : 2025 Latest Caselaw 7536 Mad
Judgement Date : 6 October, 2025

Madras High Court

Vishnu Infra Pvt. Ltd vs Engineering Projects India Ltd on 6 October, 2025

Author: N.Anand Venkatesh
Bench: N.Anand Venkatesh
                                                                             Original Application No.824 of 2025

                              IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                             DATED: 06.10.2025

                                                      CORAM

                          THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH

                                     Original Application No.824 of 2025

                     Vishnu Infra Pvt. Ltd.,
                     represented by its Director,
                     Mr.MVS Krishnam Raju
                     Having registered office at:
                     H.No.6-3-1095 & 1096, Metro Palm,
                     Grove Apartment, Hyderabad,
                     Telengana - 50034.                                             .... Applicant

                                                          Vs.

                     1.Engineering Projects India Ltd.
                       represented by its Director,
                       Ms.Akanksha Pare Kashiv
                       Having registered office at:
                       Core 3 Scope Complex 7
                       Institutional Area, Lodhi Road,
                       New Delhi - 110 003.
                       Also at:
                       Southern Regional Office,
                       3D, EC Chambers, 92, G.N.Chetty Road,
                       T.Nagar, Chennai - 600 017.

                     2.Union Bank of India
                       Besant Nagar Branch,
                       No.58, AV Church Road,
                       Chennai - 600 090.                                           .... Respondents



                     PRAYER

                     1/14



https://www.mhc.tn.gov.in/judis           ( Uploaded on: 07/10/2025 03:16:07 pm )
                                                                                  Original Application No.824 of 2025

                                  Original Application filed under Order XIV Rule 8 of
                     O.S.Rules read with Section 9(1)(ii)(e) of the Arbitration and
                     Conciliation Act, 1996, praying to grant an order of interim injunction
                     restraining the first respondent, its men, agents and representatives from
                     encashing the Performance Bank Guarantee of Rs.2,89,50,000/- dated
                     31.01.2024 bearing No.52720IGL0002423 issued by the second
                     respondent as well as the Demand Draft for Rs.2,89,50,000/- furnished by
                     the applicant, until a competent Arbitral Tribunal is seized of the matter.
                                  For Applicant         : Mr.Rohan Rajasekaran

                                  For Respondents       : Mrs.Hema Srinivasan [R1]
                                                           *****

                                                           ORDER

This application has been filed under Section 9 of the

Arbitration and Conciliation Act, 1996 (for brevity 'the Act') for an order

of interim injunction restraining the first respondent from encashing the

Performance Bank Guarantee for a sum of Rs.2,89,50,000/- dated

31.01.2024 bearing No.52720IGL0002423 issued by the second

respondent as well as the demand draft for a sum of Rs.2,89,50,000/-

furnished by the applicant until the dispute is resolved by the Arbitral

Tribunal.

2. The facts of the case and the grounds raised by the applicant

was considered by this Court and an interim order was passed on

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

14.08.2025 and for proper appreciation, the same is extracted hereunder:

"This application has been filed under Section 9 of the Arbitration and Conciliation Act, 1996, seeking for an order of interim injunction to restrain the first respondent from encashing the Performance Bank Guarantee for a sum of Rs.2,89,50,000/- dated 31.01.2024 given by the applicant; and also for an order of interim injunction to restrain the first respondent from encashing the Demand Draft (DD) for a sum of Rs.2,89,50,000/- issued by the second respondent bank.

2. The applicant was appointed as a sub-contractor by the first respondent, who was awarded a contract by the Railways. As per the terms and conditions of the sub-contract awarded to the applicant, the applicant had executed a Performance Bank Guarantee for a sum of Rs.2,89,50,000/- dated 31.01.2024 in favour of the first respondent. According to the applicant, despite fulfilling their part of the contract as per the terms and conditions of the contract agreement dated 05.02.2024, the first respondent is now attempting to encash the Performance Bank Guarantee in violation of the terms and conditions of the contract. The applicant has also pleaded in the affidavit filed in support of this application that if the Performance Bank Guarantee is encashed, the applicant will be put to irreparable loss/hardship and they have also pleaded that any attempt made by the first respondent to encash the Performance Bank Guarantee will amount to fraud.

3. Earlier, the very same applicant in respect of the very same contract had approached this Court against the very same respondents and this Court, vide its order dated 30.10.2024 passed in O.A.No.834 of 2024, restrained the first respondent from engaging a third party. Thereafter, the applicant and the first respondent reached an amicable settlement and the same was recorded by the Arbitrator through the compromise arbitral award dated 01.03.2025. However, according to the applicant, despite the applicant's readiness and willingness to complete the contract as per the terms and conditions of the contract agreement dated 05.02.2024, the first respondent is now once again attempting to invoke the Performance Bank Guarantee. As per the terms and conditions of the contract agreement dated 05.02.2024, the time for completion of the contract by the applicant ends on 05.02.2027.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

4. The applicant also claims that apart from the Performance Bank Guarantee, which was given as security for the due performance of the contract by the applicant, the first respondent is also possessing a Demand Draft taken in their favour for the same amount. Therefore, the applicant seeks for an order of interim injunction not alone in respect of the Performance Bank Guarantee but also in respect of the Demand Draft taken for the very same amount. Insofar as the DD is concerned, the question of granting interim injunction at the exparte stage does not arise, as the same has been taken voluntarily by the applicant in favour of the first respondent. However, insofar as the prayer sought for in respect of Performance Bank Guarantee is concerned, this Court is inclined to grant an order of interim injunction as the applicant has made adequate averments in the affidavit filed in support of this application, which are supported by documents.

5. For the foregoing reasons, since the applicant has made out a prima-facie case, and the balance of convenience and irreparable loss/hardship have also been established by the applicant, this Court is issuing the following directions:-

(a) There shall be an order of interim injunction restraining the respondents from encashing the Performance Bank Guarantee dated 31.01.2024 for a sum of Rs.2,89,50,000/-.

(b) Insofar as the other relief in respect of the DD for a sum of Rs.2,89,50,000/- is concerned, the said relief cannot be granted by this Court at the exparte stage.

(c) Notice to the respondents through Court as well as privately returnable by 18.09.2025."

3. Pursuant to the above order, notice was issued to the

respondents and the 1st respondent entered appearance and a counter

affidavit was also filed on behalf of the first respondent along with typed-

set of documents.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

4. When the mater came up for hearing on 25.09.2025, this

Court after hearing both sides and after considering the counter affidavit

filed by the first respondent, passed the following order:

"Counter and typed set of papers have been filed on the side of the 1st respondent. This Court also heard the learned counsel for the applicant and the learned counsel appearing on behalf of the 1st respondent.

2. It is seen that earlier there was a settlement agreement between the applicant and the 1st respondent on 31.05.2024, whereby, the applicant was supposed to give an additional bank guarantee of Rs.2crores, apart from the bank guarantee of Rs.2.89cores which was available. The fresh bank guarantee for a sum of Rs.2crores was supposed to replace the existing bank guarantee of Rs.2.89crores. Insofar as the existing bank guarantee of Rs.2.89crores, a demand draft has to be given by the applicant and accordingly, the applicant has given the demand draft.

3. The specific case of the 1st respondent is that even after the settlement agreement, there has been absolutely no progress on the side of the applicant and repeated letters have been issued in this regard, starting from 11.04.2025 onwards. Since there was no progress, ultimately, the termination notice was issued by the 1st respondent on 13.08.2025.

4. The learned counsel for the 1st respondent submitted that an unconditional bank guarantee has been issued by the applicant and therefore, unless and otherwise the applicant is able to bring this case within the parameters that are available for injuncting the invocation of bank guarantee, the applicant cannot sustain this application. That apart, the grounds that were raised by the applicant, which were recorded in the earlier order by this Court on 14.08.2025, are unsustainable.

5. Learned counsel for the applicant seeks for some

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

time to respond and to place the relevant documents in order to establish before this Court that for those letters that were issued on the side of the 1st respondent, the applicant had in fact responded.

Post this case under the caption “part heard case” on 06.10.2025."

5. The application was taken up for hearing today and this

Court heard the learned counsel for applicant and the learned counsel

appearing on behalf of the first respondent.

6. The present application has been filed before this Court to

injunct the first respondent from invoking the Bank Guarantee. It is now

too well settled that Bank Guarantee is an independent contract between

the bank and the beneficiary, who is the first respondent in this case.

Therefore, irrespective of the dispute between the beneficiary at whose

instance the Bank has given the guarantee, the Bank is obliged to honour

the guarantee. There are only two exceptions available for this rule. The

first exception is where there is a clear fraud, for which the Bank has

notice. The second exception is where there are special equities in favour

of granting interim injunction such as irretrievable injury or injustice that

would be faced by a party, if such an order of injunction is not granted.

Thus, the Court has a very limited jurisdiction to injunct invocation of a

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

Bank Guarantee.

7. Keeping the above in mind, the facts of the present case has

to be dealt with.

8. When the ex parte interim order was granted by this Court on

14.08.2025, three facts loomed large in the mind of the Court. The first

fact is regarding earlier order passed in O.A.No.834 of 2024, which

ultimately resulted in a settlement between the parties. This order

pertained to a completely different contract and it has got nothing to do

with the present dispute between the parties. The present dispute has

arisen after the settlement agreement entered between the first respondent

and the applicant on 31.05.2024. Therefore, this fact will have no bearing

in the present application.

9. The second fact that was considered by this Court is the

agreement dated 05.02.2024 where the applicant is said to have expressed

the readiness and willingness to complete the contract and that the tenure

of the agreement itself ends only on 05.02.2027. There is a factual

mistake insofar the completion of the tenure. The tenure actually comes

to an end on 07.02.2026 and not on 05.02.2027. The issue is as to

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

whether the applicant was really showing the readiness and willingness as

was recorded by this Court in the interim order.

10. The third fact that was considered by this Court is regarding

the Bank Guarantee given as security and the demand draft given by the

applicant for the very same amount of Bank Guarantee, which was also

retained by the first respondent.

11. Insofar as the above fact is concerned, after the settlement

agreement, a fresh Bank Guarantee for a sum of Rs.2 crores was

supposed to replace the existing Bank Guarantee of Rs.2.89 crores.

Insofar as the existing Bank Guarantee of Rs.2.89 crores, the demand

draft was given by the applicant and this demand draft is available with

the first respondent. This clarity was not there when the interim order was

passed by this Court on 14.08.2025.

12. In the order dated 25.09.2025, this Court took into

consideration the various communications made by the first respondent

starting from 11.04.2025 complaining about the lack of progress in the

work undertaken by the applicant. In reply to the same, additional typed-

set of documents has been filed on the side of the applicant today. On

going through the same, it is seen that the applicant has issued various

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

letters during the period 2024-2025. Curiously, for all those

communications received from the first respondent highlighting lack of

progress for the work done and also the inadequate labour strength, there

is only one document available in the additional typed-set of documents

which is a letter dated 20.06.2025, which was purportedly given for the

letter of the first respondent dated 18.06.2025. For none of the other

communications, there was even a response on the side of the applicant.

13. Apart from the above, learned counsel for the applicant

submitted that the labour license itself was obtained by the first

respondent on 21.03.2025 and 25.03.2025 and only if this license is

obtained, the applicant will be able to engage the maximum labour force.

Therefore, the first respondent had failed to perform their obligation in

this case. Learned counsel further submitted that the first respondent, who

is the direct contractor with the Southern Railways, approached the Delhi

High Court and filed an application under Section 9 of the Act seeking

for an injunction against the Railways from invoking the Bank Guarantee

and the interim injunction was also granted in favour of the first

respondent. Therefore, when the first respondent has obtained an order of

interim injunction, there is no reason as to why the Bank Guarantee

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

issued by the applicant has to be invoked.

14. This Court has already taken into consideration the limited

grounds on which an order of interim injunction can be granted against

invocation of Bank Guarantee. On carefully reading the affidavit filed in

support of the applicant, this Court finds that it is bereft of details. None

of the documents produced before this Court can be looked into by this

Court without the same being supported by necessary averments made in

the affidavit. The affidavit does not speak about the delay in obtaining the

labour license. The affidavit does not speak about the various

communications sent by the first respondent and the letters written by the

applicant to the first respondent. All these documents are emerging as this

case was progressing before this Court. A Court while deciding an

application under Section 9 of the Act cannot decide the same based on

mere documents unless it is supported by necessary averments in the

affidavit filed in support of the application.

15. The sum and substance of the dispute between the applicant

and the first respondent pertains to a claim made by the applicant for the

work already done and that without making this payment, an attempt is

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

being made by the first respondent to invoke the Bank Guarantee.

16. Per contra, the first respondent is making a counter claim

against the applicant and specific allegations have been made in the

counter to the effect that the applicant failed to perform their obligations

and the repeated notices sent did not yield any response and therefore, it

ended in a termination notice dated 13.08.2025 issued by the first

respondent to the applicant.

17. The above dispute between the applicant and the first

respondent cannot be a ground for passing an order of interim injunction

restraining the invocation of the Bank Guarantee unless it is vitiated by

fraud. There is not even a single averment in the affidavit to the effect

that the agreement between the parties is vitiated by fraud. One ground

raised on the side of the applicant is that there is a special equity in favour

of the applicant since the first respondent has obtained an order of interim

injunction against the Southern Railways and therefore, the first

respondent should not, in turn, invoke the Bank Guarantee issued by the

applicant.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

18. In the considered view of this Court, the above ground

raised on the side of the applicant is bereft of merits. The special equities

raised on the side of the applicant must be predicated with a case of fraud,

which has not been raised in this case. Therefore, the settled principles of

law insofar as restraining the invocation of Bank Guarantee has not been

satisfied in the case in hand. That apart, the very basis on which the

interim order was passed by this Court on 14.08.2025, is now found to be

unsustainable based on the documents that have now been presented

before this Court and the averments made in the counter affidavit filed by

the first respondent. Hence, the interim order cannot continue and this

application has to be necessarily dismissed.

19. Learned counsel for the applicant submitted that already

termination notice has been issued by the first respondent and therefore,

the dispute has to be resolved by referring the matter to the Arbitral

Tribunal.

20. Learned counsel for the first respondent submitted that the

first respondent will not have any objection if this Court appoints an

Arbitrator and refer the dispute.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

21. The agreement between the parties is borne out by the

tender conditions and Clause 4.35 of the tender conditions deals with

referring the dispute to an Arbitrator. The agreement specifies the Sole

Arbitrator, who will be appointed for this purpose. Such unilateral

appointment is not sustainable as per the judgment of the Apex Court in

Central Organisation for Railway Electrification v. ECI SPIC SMO

MCML (JV) A Joint Venture Company [(2025) 4 SCC 641]. Therefore,

on the basis of consent given by both sides, this Court is inclined to

appoint a Sole Arbitrator to resolve the dispute between the parties. It is

also made clear that it is left open to the applicant and the first respondent

to move necessary interlocutory applications under Section 17 of the Act

before the Sole Arbitrator, if and when they seek for any interim

protection.

N.ANAND VENKATESH, J.

gm

In the result, this Original Application is dismissed. This Court

appoints Mrs.Chitra Sampath, Senior Advocate, No.14/1,

Kamatchipuram, 1st Street, West Mambalam, Chennai - 600 033 [Mobile

No.9962085956] as the sole Arbitrator and the Hon'ble sole Arbitrator is

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm ) Original Application No.824 of 2025

requested to adjudicate the arbitral disputes that had arisen between the

parties and render arbitral award by holding sittings in the 'Madras High

Court Arbitration Centre under the aegis of this Court' (MHCAC) as per

Madras High Court Arbitration Proceedings Rules 2017 and fee of

Hon'ble sole Arbitrator shall be in accordance with the Madras High

Court Arbitration Centre (MHCAC) (Administrative Cost and Arbitrator's

Fees) Rules 2017.

06.10.2025 NCC:Yes/No Index:Yes/No Speaking Order/Non-speaking Order gm

Original Application No.824 of 2025

https://www.mhc.tn.gov.in/judis ( Uploaded on: 07/10/2025 03:16:07 pm )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter