Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Mecon Limited vs The Government Of Tamil Nadu
2025 Latest Caselaw 1606 Mad

Citation : 2025 Latest Caselaw 1606 Mad
Judgement Date : 8 January, 2025

Madras High Court

M/S.Mecon Limited vs The Government Of Tamil Nadu on 8 January, 2025

Author: G.K.Ilanthiraiyan
Bench: G.K.Ilanthiraiyan
                                                                        W.P(MD)No.25242 of 2023


                          BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT

                                     RESERVED ON           :   06.01.2025

                                    PRONOUNCED ON         :    08.01.2025

                                                  CORAM

                              THE HONOURABLE MR.JUSTICE G.K.ILANTHIRAIYAN

                                        W.P(MD)No.25242 of 2023
                                                 and
                                       W.M.P(MD)No.21430 of 2023

                     M/s.Mecon Limited,
                     Represented by its General Manager,
                     89, South End Road,
                     Basavanakudi,
                     Bangalore – 560 004.                           ... Petitioner

                                                     Vs

                     1.The Government of Tamil Nadu,
                       Represented by its Principal Secretary to Government,
                       Municipal Administration and Water Supply
                         Department and Chairman,
                       TWAD Board,
                       Chennai – 600 009.

                     2.The Managing Director,
                       TWAD Board,
                       31, Kamarajar Salai,
                       Chepauk,
                       Chennai – 600 005.

                     3.The Chief Engineer (EE),
                       TWAD Board,
                       Ganesh Nagar,
                       Mattuthavani Bus Stand,
                       Madurai.




https://www.mhc.tn.gov.in/judis
                     1/14
                                                                         W.P(MD)No.25242 of 2023


                     4.The Executive Engineer (EE),
                       TWAD Board, RWS, Division,
                       Ex-Serviceman Building,
                       1st Floor, Collectorate Complex,
                       Ramanathapuram,
                       Tamil Nadu – 623 501.                         ... Respondents


                     PRAYER: Writ Petition filed under Article 226 of Constitution of
                     India, to issue a writ of Mandamus directing the TWAD board to
                     permit the petitioner to raise an invoice for the work done under the
                     Contract Agreement signed on 18.12.2019 and consequently direct
                     the TWAD Board to make payments which are due for the
                     completed services to the petitioner within a reasonable period to
                     be determined by this Court.


                                  For Petitioner    : Mr.N.Dilip Kumar

                                  For R – 1         : Mr.S.Shanmugavel
                                                      Additional Government Pleader


                                  For RR 2 to 4     : Mr.B.Vijay Karthikeyan


                                                     ORDER

This Writ Petition has been filed by the petitioner for a

direction directing the respondents to permit the petitioner to raise

an invoice for the work done under the contract agreement dated

18.12.2019 and disburse the payments which are due for the

completed services.

https://www.mhc.tn.gov.in/judis

2.The petitioner is a public sector company undertaking

under the Government of India. It is a frontline engineering,

consultancy and contracting organization, offering a full range of

services required for setting up projects from concept to

commissioning. While being so, the respondents were entrusted

with the development of Water Supply and Sewerage facilities in the

State of Tamil Nadu, except in the Chennai Metropolitan

Development areas. The petitioner was being the lowest bidder in

the auction, the respondents had accepted the petitioner as the

qualified tender and issued a work order dated 15.11.2019 and the

contract agreement was signed on 18.12.2019. As per the

agreement, the consultancy services to conduct a demand study,

pre-feasibility studies including environmental feasibility,

preparation of a detailed project report, detailed engineering and

bid documents for the Installation of 4.00 MLD capacity

containerized sea water reverse osmosis desalination plant at

Narippaiyur in Ramanathapuram District including the operation and

maintenance of the plant and allied units for a period of 5 years

from the date of installation. The total value of the contract was

1.16 crores. The completion of the project was 3 months from the

date of the agreement. The payment details as per the contract

agreement are as follows:

https://www.mhc.tn.gov.in/judis

Sl.No. Schedule Payment 1.0 On submission and acceptance of 20% of contract inception report with a detailed amount work plan 2.0 On submission and acceptance of 25% of contract the interim report amount 3.0 On submission and acceptance of 25% of contract detailed project report and after amount technical sanction 4.0 On submission and acceptance of 25% of contract the final report along with the final amount bid document and approved by the Board As per the contract, upto 95% of the payment will be made to the consultant on submission and acceptance of the final report. The balance amount of 5% will be retained as a Performance Guarantee which will be paid to the consultant (without interest) after obtaining approval from the funding agency/concerned authority for approval of DPR.

3.Accordingly, the inception report was submitted to the

respondents dated 19.12.2020 followed by the interim report dated

18.02.2020. As per Clause No.4.4 of the contract agreement, the

Review Committee has to furnish necessary comments within a

period of 7 days from the date of submission of the report and

acceptance of the final report within 10 days. The petitioner also

submitted reminders dated 22.01.2020 and 18.02.2020. The

petitioner was advised by the notices dated 04.03.2020 and

09.03.2020 to obtain Coastal Regulation Zone clearance before

finalization of the DPR and bid document. Thereafter, the petitioner

https://www.mhc.tn.gov.in/judis

submitted a revised inception report. The Review Committee

submitted comments on the inception and interim report during

COVID-19. Therefore, the petitioner requested the respondents to

extend the time of the contract till 30.12.2020. It was granted on

06.07.2020 valid up to 30.12.2020 and further extension was also

granted on 17.03.2021 up to 30.09.2021 and on 12.04.2022 valid

up to 30.09.2022. The petitioner submitted a detailed project

report. Subsequently, after the completion of environmental studies,

the reports were prepared and submitted to The Tamil Nadu

Pollution Control Board, Ramanathapuram for Coastal Regulation

Zone clearance on 28.09.2022. While being so, by the

communication dated 17.11.2022, the respondents suspended the

project citing administrative reasons. Further, by the communication

dated 17.08.2023, the entire contract itself was closed by the State

Level Technical Committee by its meeting dated 03.11.2022 for the

preparation of a new multi-Village scheme for Ramanathapuram

District with the river Cauvery as source by including all the 117

rural habitations in Kamuthi Union of Ramanathapuram District.

Accordingly, the respondents decided to call upon the project of

desalination itself. Therefore, the petitioner submitted a

representation requesting to finalize its due i.e., release of 5%

withheld amount for the already released payment amounting to Rs.

https://www.mhc.tn.gov.in/judis

3,67,886.00/- and also to allow the petitioner to raise the invoice

against the third milestone amounting to Rs.34,34,980.00/- and

also to release the Bank Guarantee to the tune of Rs.2,61,000.00/-.

4.The learned counsel appearing for the petitioner would

submit that as per Clause 2.9.1(f) of the contract agreement, if the

client, in its sole discretion and for any reason whatsoever decides

to terminate the contract, the termination can be invoked.

Therefore, by invoking Clause 2.9.1 of the contract agreement, the

respondents informed the petitioner to furnish consent for the

termination of the contract as per Clause 2.9.1(f) of the contract

agreement. Further, the petitioner was requested not to initiate any

further activities related to the contract work and furnished the

work done details as on date by communication dated 17.11.2022.

Therefore, the petitioner is entitled to raise invoice for the work

already done ie., on submission and acceptance of the detailed

project report and after technical sanction, the petitioner is entitled

for a further 25% of the contract work.

5.Heard the learned counsel appearing on either side

and perused the materials placed before this Court. https://www.mhc.tn.gov.in/judis

6.On perusal of the counter-affidavit filed by the second

respondent and on the submissions made by the learned counsel

appearing for the respondents 2 to 4 would reveal that the

petitioner was issued work order and entered into a contract

agreement dated 18.12.2019 to conduct pre-feasibility studies

including environmental feasibility, preparation of detailed project

report, detailed engineering including processing for sanction and

bid documents for the installation of 4.00 Million Litres per Day

capacity containerized Sea Water Reverse Osmosis Desalination

plant at Narippaiyur Union in Ramanathapuram District including the

operation and maintenance of the plant and allied units for a period

of 5 years. The said project was crucial for providing potable water

to drought hit 117 habitations of Kamuthi Union in

Ramanathapuram District. The petitioner was given 90 days time to

complete the project. However, subsequently, on three occasions,

the petitioner was granted extensions only based on the petitioner's

request. According to the respondents, the petitioner failed to

submit the inception report and interim report within the stipulated

time frames. The final revised inception report and interim report

were submitted on 18.03.2021. Accordingly, the payment was

released for stages 1 and 2. As per the inception report, the

petitioner had faced challenges in demarcating the Coastal

https://www.mhc.tn.gov.in/judis

Regulation Zone concerning the 4.00 Million Litres per Day Sea

Water Reverse Osmosis Plant. Therefore, the respondents by their

minutes of the meeting dated 05.02.2020 identified certain remarks

in the inception report and accordingly instructed the petitioner to

complete the entire work on or before 17.03.2020. Even then, the

petitioner delayed the work. As per the contract agreement, the

petitioner has to obtain all clearances including Coastal Regulation

Zone clearance. However, the detailed project report of the Sea

Water Reverse Osmosis Desalination Plant at Narippaiyur was

received on 17.03.2022 that too without the necessary field data.

Further, the petitioner failed to provide a complete Environmental

Impact assessment study, including impact assessments, as

required. Finally, the petitioner submitted the final revised inception

report for stage 1 on 18.03.2021. Only after clearance from the

Coastal Regulation Zone, a detailed project report can be

proceeded. Further, the petitioner was also informed by the Tamil

Nadu Pollution Control Board that the proposed 4.00 Million Litres

per Day Containerized Sea Water Reverse Osmosis Desalination

plant at Narippaiyur falls under non-permissible activity as per

Coastal Regulation Zone Notification, 2011. Therefore, the failure on

the part of the petitioner to obtain Coastal Regulation Zone

clearance in a timely manner, the State Level Technical Committee

https://www.mhc.tn.gov.in/judis

of Tamil Nadu Water Supply and Drainage (TWAD) Board deferred

the proposal. Therefore, the third milestone payment could not be

released due to various reasons, including the deferred detailed

project report and technical sanction. Therefore, the issues involved

in this Writ Petition are disputed questions of facts and they cannot

be gone into in this Writ Petition that too under Article 226 of the

Constitution of India.

7.In this regard, the learned counsel appearing for the

respondents 2 to 4 relied upon the Judgment of the Hon'ble

Supreme Court of India reported in AIR 2024 SC 2855 in the case

of Municipal Committee Katra and others Vs. Ashwani Kumar,

wherein it is held as follows:

“22.Furthermore, the relief which was sought by the respondent in the writ petition was purely by way of damages. By no stretch of imagination, such relief could have been subject matter of extra ordinary writ jurisdiction of the High Court under Article 226 of the Constitution of India. The quantification of the damages would require entering into disputed questions of facts and hence, the High Court ought to have relegated the writ petitioner(respondent herein) to the competent Court for claiming damages, if so advised.

https://www.mhc.tn.gov.in/judis

23. Law is well settled that disputes arising out of purely contractual obligations cannot be entertained by the High Court in exercise of the extra ordinary writ jurisdiction. In the case of Union of India and Ors. v. Puna Hinda reported in (2021) 10 SCC 690, this Court held as follows:

“24. Therefore, the dispute could not be raised by way of a writ petition on the disputed questions of fact. Though, the jurisdiction of the High Court is wide but in respect of pure contractual matters in the field of private law, having no statutory flavour, are better adjudicated upon by the forum agreed to by the parties. The dispute as to whether the amount is payable or not and/or how much amount is payable are disputed questions of facts. There is no admission on the part of the appellants to infer that the amount stands crystallised.”

Therefore, in the absence of any acceptance of joint survey report by the competent authority, no right would accrue to the writ petitioner only because measurements cannot be undertaken after passage of time. Maybe, the resurvey cannot take place but the measurement books of the work executed from time to time would form a reasonable basis for assessing the amount due and payable to the writ petitioner, but such process could be undertaken only by the agreed forum i.e. arbitration and not by the writ court as it does not have the expertise in respect of measurements or construction of roads.”

https://www.mhc.tn.gov.in/judis

8.The above Judgment is squarely applicable to the case

on hand since the contractual obligations cannot be entertained in

the Writ Petition exercising the extra-ordinary writ jurisdiction under

Article 226 of the constitution of India.

9.The learned counsel appearing for the petitioner also

relied upon the Judgment of the Hon'ble Supreme Court of India

reported in (2008) 3 SCC 440 in the case of Food Corporation of

India and another Vs. Seil Limited and others, in which the

Hon'ble Supreme Court India held that contractual disputes

involving public law elements are amenable to writ jurisdiction.

Though the dispute is related to the public law element in this Writ

Petition the contractual obligations cannot be entertained by way of

Writ Petition. Therefore, the Judgment relied upon by the petitioner

is not helpful to the case on hand.

10.That apart, as per the contract agreement Clause 8

says about 'Settlement of Disputes'. Accordingly, in order to ensure

a dispute redressal mechanism, a Committee headed by the

https://www.mhc.tn.gov.in/judis

Managing Director / Joint Managing Director and consisting of

Engineering Director, Tamil Nadu Water Supply and Drainage Board

and Engineering Director, CMWSS Board as Member, will comprise

the 'Disputes Redressal Committee' for each package in order to

resolve any disputes between the client / Engineer-in-charge

concerned and the consultants. In the event of non-settlement of

any dispute by the Disputes Redressal Committee, the parties are at

liberty to approach the jurisdictional civil Court for appropriate

relief. Therefore, the direction sought for in this Writ Petition cannot

be considered and the Writ Petition itself is liable to be dismissed.

Accordingly, this Writ Petition is dismissed. There shall be no order

as to costs. Consequently, connected Miscellaneous Petition is

closed.





                                                                           08.01.2025
                     NCC          : Yes / No
                     Index        : Yes / No
                     Internet     : Yes
                     ps




https://www.mhc.tn.gov.in/judis






                     To

                     1.The Government of Tamil Nadu,

Represented by its Principal Secretary to Government, Municipal Administration and Water Supply Department and Chairman, TWAD Board, Chennai – 600 009.

2.The Managing Director, TWAD Board, 31, Kamarajar Salai, Chepauk, Chennai – 600 005.

3.The Chief Engineer (EE), TWAD Board, Ganesh Nagar, Mattuthavani Bus Stand, Madurai.

4.The Executive Engineer (EE), TWAD Board, RWS, Division, Ex-Serviceman Building, 1st Floor, Collectorate Complex, Ramanathapuram, Tamil Nadu – 623 501.

https://www.mhc.tn.gov.in/judis

G.K.ILANTHIRAIYAN, J.

ps

Order made in

08.01.2025

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter