Citation : 2025 Latest Caselaw 2796 Mad
Judgement Date : 14 February, 2025
A.S.(MD)No.16 of 2015
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT
DATED : 14.02.2025
CORAM
THE HONOURABLE MR.JUSTICE P.VELMURUGAN
AND
THE HONOURABLE MR.JUSTICE K.K.RAMAKRISHNAN
A.S.(MD)No.16 of 2015
and
M.P.(MD)No.1 of 2015
1.Shri Mahavir Ferro Alloys Pvt. Ltd.,
A Company registered under the Indian Companies Act,
Vide Registration No.U27320R1996PTC004602,
Rep. by its Managing Director,
Vicky Jain having its Registered Office at
L/10, Civil Township,
Rourkela - 769 004.
2.Vicky Jain
3.Suresh Chand Jain
4.Sudhansu Pati
5.Manish Kumar ...Appellants
vs.
M/s.Veesons Energy Systems Pvt. Ltd.,
A Company Registered under the Indian Companies Act,
Rep. by its Managing Director V.Ramakrishnan,
S/o.V.K.N.P.Venkatachalam,
Having its registered Officer at
C-14/2, Industrial Estate, Thuvakudi,
Tiruchirappalli - 620 015. ... Respondent
Page 1 of 41
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
A.S.(MD)No.16 of 2015
Prayer: Appeal Suit filed under Section 96 of the Civil Procedure Code
praying to allow this appeal by setting aside the Judgment and decree
dated 27.06.2014 in O.S.No.116 of 2009 on the file of the I Additional
District Judge (PCR), Tiruchirappalli.
For Appellants : Mr.M.Vallinayagam
Senior Counsel
for Mr.M.Palaramasamy
For Respondent : Mr.D.Srinivasaragavan
JUDGMENT
(Judgment of the Court was delivered by P.VELMURUGAN, J.)
The respondent is the plaintiff who filed the suit in O.S.No.116 of
2009 before the Principal District Court, Thiruchirappali and the same
was made over to the I Additional District Judge (PCR), Tiruchirappalli
for disposal in accordance with law. The learned I Additional District
Judge dealt with the matter and decreed the suit in favour of the
respondent and directed the first defendant therein to pay a sum of Rs.
57,28,702/- with subsequent interest thereon at the rate of 6% per annum
from the date of the plaint till the date of realization. Aggrieved over the
same, the defendants have filed the present appeal.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
2. The parties are referred to as per their ranking before this Court.
3. The brief facts of the case of the respondent is that the first
appellant placed a purchase order with them on 12.06.2008 for supply of
one number 10 TPH capacity, 67 ata, 515 + 5°c WHRB [Waste Heat
Recovery Boiler] for their power plant project, for which, a sum of Rs.
1,00,000/- was paid as advance by way of Demand Draft dated
12.06.2008 by the first appellant to the respondent. The total value of
purchase order is Rs.2,23,00,000/-. The supply of boiler ought to be
made from 01.08.2008 and to be completed before 31.10.2008. All the
sub delivery items purchased by the respondent from the outside vendors
will have to be supplied to the first appellant before 31.12.2008. The
first appellant agreed to disburse 30% of the purchase order value on
production of a bank guarantee by the respondent. The balance 65% of
the payment was agreed to be paid by way of Demand Draft, on readiness
of materials, including all taxes and duties on pro rata basis against
proforma invoice. A sum of 5% of the basic value would be retained by
the first appellant from each proforma invoice of the respondent against
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
performance bank guarantee. Accordingly, a bank guarantee was also
furnished by the respondent. On receipt of bank guarantee, the first
appellant released 30% of the advance payment to the respondent (less
Rs.1,00,001/-) already paid. On receipt of 30% of the advance amount
on the total value of the purchase order, the respondent started
manufacturing the boiler as per the specifications given by the first
appellant on war footing basis. The respondent prepared designs and
drawings for the manufacture of boiler and its components as per the
specifications given by the first appellant. As much as 223 drawings
have to be made for manufacturing the boiler in question. If that work is
given to an outside agency, the normal cost that may be incurred for
preparation of drawings and designs would come around Rs.30,00,000/-.
Therefore, the respondent on its own prepared the drawings and designs
by spending lot of time and energy. The said designs and drawings were
sent to Indian Boiler Regulation Authority [hereinafter referred as 'IBR
Authority'] having its headquarters at Chennai for approval. IBR
Authority also verified the designs and drawings submitted by the
respondent in this regard and approved the same. For getting approval of
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
each component involved in the process of manufacturing of boiler in
question, the respondent paid the necessary fees, which alone came to
Rs.40,970/-. After getting approval, the respondent started to
manufacture the boiler for the first appellant on war footing basis by
procuring the materials at huge cost, by spending its own fund at all
levels. Almost, all the employees of the respondent were involved in
manufacturing the boiler in question for the first appellant by giving top
priority. The respondent did not evince any interest in any other projects
or other new work. Other pending works of the respondent got delayed.
The respondent not only incurred loss, but also incurred wrath of their
other valuable customers. After completion of manufacturing of boiler in
question, the same was informed to the first appellant and also IBR
Authority for Inspection. On receipt of the information, the first
appellant sent an e-mail on 21.07.2008 informing the respondent that one
of their staffs by name Mr.Hasan would come and inspect the boiler in
question soon. On 01.08.2008, Mr.Hasan came to the respondent
Company, inspected the boiler and gave an Inspection Report to the first
appellant recommending the release of payment to the respondent.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
Meanwhile, the first appellant gave reply on 07.08.2008 informing that
the payment would be released on or before 10.08.2008. The respondent
was awaiting to receive the payment and to dispatch the manufactured
items to the first appellant. However, to their shock and surprise, the first
appellant sent an e-mail on 12.08.2008 informing the respondent that
they are unable to lift the materials as the market is dull and due to
shortage of fund. The first appellant also stated that they would lift the
materials once their financial position improves. The respondent
invested a huge amount of Rs.1,11,75,614/- in the project in question.
However, after completing all the manufacturing process, the first
appellant refused to lift the boiler. On account of the breach committed
by the first appellant, the respondent suffered huge financial loss and
huge funds of the respondent got dumped in the project in question. The
difficulty faced by the respondent can be easily visualized from the
above said narrations. Thereafter, the first appellant gave lame excuses
for not honouring the commitment made by them. Subsequently, the
respondent issued notice on 28.02.2009 calling upon the first appellant to
pay 40% of value of three proforma invoices raised by them together
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
with interest at the rate of 24% per annum. The second appellant is the
Managing Director, appellants 3, 4 and 5 are the Directors of the
appellant Company. They are also equally, jointly and severally liable to
pay the claim of the respondent. After receiving the notice dated
28.02.2009, the appellants did not send any reply or pay the said amount.
Therefore, the respondent was constrained to file the suit claiming
damages for the loss incurred by them.
4. The brief facts of the case of the appellants is that the appellants
faxed an e-mail reply to the mail received from the respondent dated
16.06.2008 asking for specific date for submission of order acceptance,
specific date for submission of drawings for approval and requesting to
expedite submission of the advance bank guarantee, showing their
healthy approach to the purchase order. The remainder for submission of
the purchase order acceptance was again sent on 22.08.2008, 17.09.2008,
06.10.2008 and 08.11.2008. The respondent sent e-mail dated
27.08.2008 stating that they are going through the purchase order and
that they would submit their comments shortly. Thereafter, the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
respondent deliberately delayed the submission of order acceptance by
asking various clarifications in the purchase order. The first appellant
regularly clarified the points raised by the respondent. The designs and
drawings being sent to IBR Authority and got approved after payment of
fees of Rs.40,970/- is not concerned by the appellants since the same was
neither sent to the appellants for confirmation nor sent to IBR Authority
through the appellants. By the letter dated 23.07.2008, the Managing
Director of the respondent Company stated that they plan to divert the
boiler which was already under manufacture for the some other client to
the appellants. That boiler is not a tailor made product and the technical
data of different users may vary. Hence, the diverted boiler would not
meet the specific requirements of the appellants. The respondent starting
the work of manufacturing of boiler for the first appellant on war footing
basis by procuring materials at a huge cost and by spending their own
funds is false and denied. As per PGMA list, the value of the materials
procured and utilized for the manufacturing of boiler and its components
in question alone comes to Rs.46,12,511.11/- is false and denied as the
boiler was manufactured for a different customer and not for appellants.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
Mr.Hasan was sent to the respondent Company to follow the order for
release of drawings, for acceptance of the purchase order. During his
visit, he was shown some parts / components that were manufactured for
some other customers and planned to be diverted to the appellants. The
reason for the diversion is best known to the respondent. Mr.Hasan in
his competency issued a Report to consider as to whether the parts /
components inspected, meet out the technical requirements of the first
appellant. The respondent played fraud upon the appellants and
compelled them to withdraw the bank guarantee. The first appellant
sending an e-mail on 12.08.2008 informing the respondent that they are
unable to lift the materials as the market is dull and due to shortage of
funds is false and denied. The respondent investing a huge amount of
Rs.1,11,75,614/- in the project in question is false and denied. Though
the first appellant has placed its purchase order on 12.06.2008, the
respondent attempted to deliver a boiler that was manufactured before
the placement of the purchase order, which reflects in their letter also.
The appellants have not committed any breach of the terms and
conditions of the contractual agreement. The appellants giving lame
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
excuses, that too, at the time of dispatching the boiler is false and denied.
It is true that on 16.06.2008, the first appellant sent a mail to the
respondent asking for specific date for submission of order acceptance,
specific date for submission of drawings for approval and requesting to
expedite submission of the advance bank guarantee. As per the
conditions of purchase order, on 16.06.2008, the respondent sent a bank
guarantee for Rs.66,90,000/-. On 02.07.2008, the first appellant sent a
sum of Rs.65,89,999/- vide cheque No.442324 dated 26.08.2008 against
the bank guarantee which is 30% of the total cost of the boiler. But, on
11.07.2008, the first appellant received billing breakup sent by the
respondent, wherein, they did not send acceptance order or any drawings
as per the terms and conditions of the purchase order. In the same
manner, on 16.07.2008, the first appellant received two proforma
invoices for a sum of Rs.82,47,646/-. The respondent pressurized the
first appellant to release the payment without the acceptance order and
drawings and they tried to sell the boiler manufactured for some other
party which may not fulfill the requirements and technical specifications
of the first appellant. The first appellant sent an e-mail demanding the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
acceptance order. But the respondent without issuing the acceptance
order, raised clarification after clarification, which the first appellant
always clarified point by point. Even then, the respondent did not issue
the acceptance order and drawings as required and kept silent. It took the
respondent four months to go through the purchase order which was the
basis of the contract. The letter dated 28.10.2008 sent by the respondent
and the e-mail dated 08.11.2008 sent by the first appellant demanding the
respondent for acceptance order proved that the demand of the first
appellant became invalid. Though six months time had elapsed from the
date of placement of purchase order, the respondent did not submit
acceptance of purchase order to the first appellant. As per the terms and
conditions of the purchase order, the respondent ought to submit the
drawings and acceptance order to the first appellant within a period of
two weeks of placing of the order. The first appellant exercised their
right in safeguarding the terms and conditions of the project and wrote a
letter dated 22.12.2008 to the Axis Bank for revocation of the bank
guarantee and to adjust the advance paid to the respondent. The advance
bank guarantee was given to safeguard the appellants' advance and to
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
take care of any eventuality when the purchase order's terms and
conditions are violated. The appellant did not recover the money that
was lost in pursing the purchase order and the opportunity cost of the
project. It is denied the respondent spent enormous time in preparation
of designs and drawings for the proposed manufacture of boiler. The
respondent obtaining purchase order for proposed manufacture of boiler
from the first appellant itself proves that the boiler was not manufactured
as required by the appellants. The purchase order was obtained by the
respondent only to grab money illegally from the first appellant without
any basis. The first appellant quite unexpectedly invoked the advance
bank guarantee and the respondent was left in lurch is false and denied.
The respondent could not use the finished products for other purpose and
has to simply dismantle the manufactured items and thus, the respondent
is deceived by the first appellant and the first appellant committed the
breach of terms and conditions of the contractual agreement is false and
denied. The guarantee was invoked by the first appellant on their own
whims and fancies without any jurisdiction and defrauded the respondent
is false and denied. The respondent is not entitled to claim a single pie
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
from the first appellant. After issuance of notice by the respondent, the
first appellant contacted them over phone and they informed that it is
only a formality and hence, no reply was given. The Directors of the
appellant Company and the first appellant are not jointly and severally
liable to pay any amount much less than the suit claim. The suit is not
maintainable and the respondent suppressed all the material facts. There
was no breach of contract committed by the appellants. Neither the
respondent obtained approval of the drawings and designs of the boiler
from the appellant or IBR Authority nor they manufactured the boiler as
per the specification of the appellants. The respondent tried to sell the
boiler which was manufactured for some other parties to the appellants.
Therefore, the respondent is not entitled to get the suit claim and the suit
is liable to be dismissed.
5.1. Based on the pleadings, oral and documentary evidence
adduced by the parties, the following issues were framed by the Trial
Court.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
"(i) Whether the plaintiff is entitled for the suit amount at 12% interest as prayed for?
(ii) What other relief?"
5.2. After receipt of the additional written statement and reply
statement, the trial Court framed the following additional issues.
"(i) Whether the Court has jurisdiction to entertain the suit?
(ii) Whether the plaintiff is entitled for the suit amount at 12% interest as prayed for?
(iii) What other relief?"
6. On the side of the plaintiff, Ex.A1 to Ex.A20 were marked and
PW1 was examined. On the side of the defendants, Ex.B1 to Ex.B11
were marked and DW1 was examined.
7. After completion of the trial and hearing the arguments
advanced on either side, the Trial Court found that the suit claim made by
the plaintiff therein was proved and decreed the suit. Aggrieved over the
same, the defendants therein have filed the present appeal.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
8.1. The learned senior counsel appearing for the appellants would
submit that the suit itself is not maintainable on account of the arbitration
clause in the contract between the parties. The suit document is
Ex.A2/Ex.B1. Clause No.16 in the purchase order in Ex.A2/Ex.B1 refers
to the resolution of disputes between the parties in respect of the
contract. It states that the purchaser and the supplier will make every
effort to resolve amicably by direct informal negotiation any
disagreement or dispute arising between them under or in connection
with the order. If after 30 days from the commencement of such informal
negotiations, the purchaser and the supplier were unable to resolve
amicably an order dispute, the dispute will be referred for resolution by
arbitration as per the Indian Arbitration Act, 1996. When such
arbitration clause is embodied in the agreement between parties, then the
Civil Court should not entertain any suit arising out of the dispute
between the parties regarding the contract. The learned senior counsel
drew the attention of this Court to Section 5 of the Arbitration and
Conciliation Act, 1996 [hereinafter referred to as 'the Act'] which states
that notwithstanding anything contained in any other law for the time
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
being in force, in matters governed by this part, no judicial authority
shall except where so provided in this Part. By relying on Section 9 of
the Code of Civil Procedure, the learned counsel would submit that the
bar to file a Civil Suit may be express or implied.
8.2. He relied on the Judgement of the Apex Court in the case of
N.D.M.C vs. Satish Chand (deceased) by Lr Ram Chand reported in AIR
2003 Supreme Court 3187, wherein, it is held that bar to file a Civil Suit
may be express or implied. An express bar is where a statute itself
contains a provision that the jurisdiction of a civil Court is barred. The
learned counsel from a conjoint reading of Section 9 of the Code of Civil
Procedure, Section 5 of the Act and the above cited Judgment of Apex
Court, submits that jurisdiction of the Civil Court is ousted.
8.3. The contract between the parties to this suit has been filed
along with the plaint itself and thus the existence of the arbitration clause
is well known to the Trial court. In case a party suppresses or in case the
Trial Court at the first instance did not notice the availability of
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
arbitration clause and entertained suit, then the opposite party i.e., the
defendant can invoke Section 8 of the Act read with section 5 of the Act,
for the purpose of bringing the existence of arbitration clause in
agreement to the knowledge of the Court. In the present case, in
paragraph no.17 of the written statement, the appellants have brought the
existence of the arbitration clause to the knowledge of the Court. Under
such circumstances, he would submit that the suit is not maintainable.
8.4. It is well settled by the Apex Court and High Courts, by catena
of Judgements, that the jurisdiction of the Civil Court if expressly or
impliedly excluded, then entire suit proceedings is barred in the eye of
law, and they have to be set aside by the Appellate court without going
into the merits of the case. On knowing about the existence of arbitration
clause in the agreement upon which suit is filed, it is obligatory on the
part of the Court to refer the matter to Arbitration and the jurisdiction of
the Court to deal with the case on merits perishes or ceased. Such is the
position of law, the merits of the case dealt by the Trial court ought not
have been deliberated by the Appellate court.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
8.5. The Apex Court in the case of Ravi Prakash Goel vs. Chandra
Prakash Goel and another reported in 2008(13) SCC page 667 has held
that when a dispute is referable to arbitration, parties cannot be
compelled to take recourse in the Civil court. While so, the Appellate
Court ought not have deliberated the merits of the case.
8.6. In support of his contentions, the learned counsel for the
appellants relied on the following Judgements also.
(i) Judgement of the Madras High Court in the case of
G.Rajarajan vs. Aig Consumer Financial Services reported in 2012(4)
LW 155.
(ii) Judgment of the Delhi High Court in the case of Sharad
P.Jagtiani vs. Mis.Edel Weiss Securities Limited.
8.7. The learned senior counsel would submit that in the case on
hand, the respondent relied upon Exs.A8, A10, A11 in order to establish
their case and the appellants rely upon Ex.B3, communication sent by the
respondent dated 23.07.2008. In Ex.B3, the respondent has disclosed
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
that they are diverting the boiler, which was manufactured for some other
customer. For converting or altering the boiler manufactured for some
other customer, the respondent had applied for approval from IBR
Authority under Exs.A14 and A15. However, no such approval was
obtained from IBR Authority for manufacturing the boiler. The
respondent has not also marked any document to prove that they have
obtained IBR Authority approval for manufacturing the subject boiler.
Therefore, since it is obvious that the respondent is substituting another
contract in the place of original contract, the original contract Ex.A2
need not be performed by the appellant. In this context, the learned
senior counsel referred to Section 62 of the Indian Contract Act, 1872
which reads that, if the parties to a contract agree to substitute a new
contract for it, or to rescind or alter it, the original contract, need not be
performed. Therefore, he submitted that on this ground itself, the suit is
liable to be dismissed.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
8.8. He would also add that it is well proved that the respondent
herein has not honored to the terms of the contract and has attempted to
supply the boiler, which was meant for third party, without providing
requisite drawings and the required approval of IBR Authority.
Therefore, any party, which has not adhered to the terms of the contract,
is not entitled for any compensation in form of damages under Section 73
of the Indian Contract Act, 1872. On this ground also, the suit is liable to
be dismissed.
8.9. Furthermore, he would submit that, absolutely, there is no
pleading regarding the diversion of the boiler manufactured for other
customer in the place of original boiler ordered by the appellants under
Ex.A2 and any evidence without pleading is useless in the eye of law.
8.10. According to the senior counsel, when there is an arbitration
clause, apart from dismissing the suit, it is obligatory on the part of the
Court, to direct the parties to approach the Arbitrator and resolve their
dispute through Arbitration. He also would submit that if this case is
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
referred to Arbitration, the appellants would co-operate with the
proceedings of the Arbitration and prayed to set aside the judgment and
decree of the trial court and refer the matter to Arbitration Tribunal.
9. The learned counsel appearing for the respondent would submit
that the respondent did not attempt to divert the boiler of any third party
to the first appellant. The respondent has given bank guarantee and
started manufacturing the boiler. The first appellant has paid 30% value
of the purchase order after receiving the bank guarantee. The first
appellant sent their man Mr.Hasan for Inspection, who had conducted
inspection and made a report. Subsequently, the appellants have
promised to lift the boiler. Hence, both the parties acted upon the
contract. The respondent has proved beyond doubt the cost of
preparation of designs and drawings, payments made to IBR Authority
and the cost of raw materials. The respondent restricted their claim to
40% alone and prayed for the decree. The appellants have not denied the
purchase order. Though the respondent sent a legal notice, the first
appellant did not send any reply. Only thereafter, the respondent filed the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
suit. The Civil Court has got jurisdiction to decide the issue. After filing
of the suit, the appellants sought for several adjournments to file written
statement and they filed the written statement very belatedly. After
consuming considerable time more than the statutory period, the
appellants have not filed any application under Section 8 of the Act for
referring the matter to Arbitration and they have not also invoked Section
8 of the Act before filing the first written statement. Even though the
appellants have averred in the written statement about the arbitration
clause mentioned in the agreement, they have neither invoked Section 8
of the Act and made any application nor submitted a copy of either the
original agreement or certified copy of the agreement and requested the
Court to refer the matter to Arbitration. The appellants did not take any
sincere effort for referring the matter to Arbitration and no issue in this
regard was framed. The respondent has proved their case through oral
and documentary evidence and there is no civil remedy barred either
under Section 9 of the Civil Procedure Code or under Section 8 or 5 of
the Act. Since the appellants have not filed any application under
Section 8 of the Act initially, they cannot take that defence at a latter
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
point of time, that too, at the appeallate stage. They ought to have taken
this stand either at the stage of Interlocutory Application or at the stage
of filing written statement and before deciding the suit. Since there are
no materials to show that the appellants invoked Section 8 of the Act
during the pendency of the suit, they cannot take that defence at the
appellate stage. The trial Court rightly appreciated the oral and
documentary evidence on both sides and rightly decreed the suit. There
are no merits in the appeal and hence, the appeal is liable to be
dismissed.
10. Heard both sides and perused the materials available before
this Court.
11. Considering the above narrated facts and circumstances of the
case, the following points are taken for consideration.
(i) Whether the suit is maintainable before the Civil Court?
(ii) Whether mere taking defence in the written statement about the
arbitration clause is enough for the Trial Court to refer the matter to
arbitration.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
(iii) Whether the Judgment and decree passed by the trial Court is
liable to be set aside.
All the points are being discussed together, the findings are
given as follows:-
12. The respondent has specifically stated that the first appellant
placed a purchase order with them on 12.06.2008 for supply of one
number 10 TPH capacity, 67 ata, 515 + 5°c WHRB. The purchase order
placed by the first appellant is marked as Ex.A2. The first appellant has
not denied the same. Admittedly, the total value of the purchase order is
Rs.2,23,00,000/-. There is a specific period stipulated in the purchase
order for delivery of boiler. While so, the drawings were sent to IBR
Authority having its headquarters at Chennai for approval. IBR
Authority verified the designs and drawings submitted by the respondent
and approved the same. For getting approval, the respondent paid Rs.
40,970/- as fees and the same was also intimated to the appellants. Only
thereafter, the respondent started to manufacture the boiler. The
respondent spent their own funds in the process of manufacturing of
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
boiler at all levels, which alone would come to Rs.46,12,511.11. Almost
all the employees of the respondent Company were involved in the
process of manufacturing the boiler in question for the first appellant
Company by giving top priority. The respondent manufactured the
components for the boiler in question and after completion, raised three
proforma invoices Ex.A4, Ex.A5 and Ex.A9. In pursuance thereof, the
first appellant sent an e-mail on 21.07.2008 informing the respondent
that one of their staffs by name Mr.Hasan would come and inspect the
boiler in question. For better clarity, the said e-mail dated 21.07.2008,
marked as Ex.A6 is extracted hereunder.
"Dear Mr.K.N.Venkatakrishnan, This is to inform you that out Mr.Hasan will be coming to your works for inspection of the materials. Once the inspection of materials is over, we will be releasing the your payment as per the proforma invoice raised by you. You may coordinate with Mr.Hasan about his visit plans to your works."
Accordingly, the first appellant sent their staff Mr.Hasan for Inspection,
who in turn inspected the boiler in question and sent a report. The
respondent also sent an e-mail to the first appellant along with the copy
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
of the Inspection Report. Even after seeing the e-mail, the appellants did
not raise any objection and they promised to take delivery. The e-mail
sent by the first appellant in this regard dated 06.08.2008, marked as
Ex.A10 is extracted hereunder.
"From: Abdul Hasan Ref: /[email protected]/ Date 06.08.08 To Veesons Energy System Pvt.
C-14/2, Industrial Estate, Tiruchirapalli - 620 015. Kind Attn: Mr.Ramakrishna (Director) Sub: Regarding payment of 3rd. WHRB.
Dear Sir, We have received your mail/fax no-VCOM/VWH022/89 10/1, dated 06.08.08 regarding release of payment against PI-01, 02 and 03 of our PO no-SMFAPL/08-09/P/MA5/42, dated 12.06.2008. In this regards this already has been clarified that the payment due on account of material ready for dispatch have been cleared by us to the bank. Since the bank takes two or there days time to process the payment. This is likely released to you on or before 10th August, 2008."
Only thereafter, the first appellant informed the respondent that they are
in financial crunch and once they recover from the same, they would lift
the boiler in question. For better appreciation of facts, the e-mail sent by
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
the first appellant in this regard dated 12.08.2008, marked as Ex.A11 is
extracted hereunder.
"Mr Venkatakrishnan, This has our reference to our PO for 10 TPH WHRB on you. Please note that since there is problem of fund in this month due to dullness in market, we will not be in a position to lift the materials for the WHRB as of now. As and when the fund position improves, we will be in a position to lift the materials.
We are extremely sorry for the inconvinience but would request you to bear with us till then."
Reading of the above facts would clearly demonstrate that the first
appellant has not lifted the boiler in question due to shortage of funds
and dullness in market. While that being so, they cannot now take a
different stand that the boiler in question was not manufactured as per
their specifications and the boiler manufactured for a third party was
planned to be diverted to them. In fact, the first appellant has nowhere
communicated to the respondent that the boiler was not up to their
standard or not manufactured as per their specifications. In that case, at a
later point of time, they cannot say that the boiler manufactured by the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
respondent did not meet out their requirements or boiler manufactured
for some other client was planned to be diverted to them. It is pertinent
to note that the first appellant did not even give any reply to the notice
issued by the respondent dated 28.02.2009 calling upon them to pay 40%
value of the proforma invoices raised by the respondent together with
interest at the rate of 24% per annum.
13. Though the learned senior counsel for the appellants submitted
that the manufacturing of boiler in question was not as per the
specifications of the first appellant and even without getting approval
from IBR Authority, the respondent tried to extract money from them, as
stated above, the appellants did not even give any reply to the pre-suit
notice. Further, the appellants have not denied the purchase order,
payment of 30% value of purchase order as advance, receipt of e-mails,
sending of their man Mr.Hasan for inspection and the Inspection Report.
Since the purchase order Ex.A2 and payment of 30% of the amount as
advance are admitted, failing to take delivery of the boiler is also
admitted. Therefore, the questions that arise are (i) whether the boiler in
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
question was manufactured as per the specifications of the first appellant
or not? and (ii) whether the respondent sustained any damages or not?
The said questions can be very well decided by the Civil Court. The
presence of arbitration clause in the purchase order does not mean that
the Civil Court has got no jurisdiction.
14. In the instant case, the suit was presented on 17.08.2009 and
Mr.I.M.Lal, learned counsel undertook before the Trial Court to file
vakalath on behalf of the appellants (defendants) on 12.01.2010 itself.
However, the appellants (defendants) filed their first written statement
only on 30.11.2010. Either after receipt of suit summons and before
filing of the written statement or even at the time of filing the written
statement, the appellants have not filed any application under Section 8
of the Act to refer the matter to Arbitration.
15. The contention of the learned senior counsel for the appellants
is that in paragraph 17 of the written statement, there is a mention about
the existence of arbitration clause in the agreement and when such clause
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
is available in the purchase order, the respondent erred by filing the
above suit and by not taking legal recourse through Arbitration.
Therefore, the learned counsel contended that the suit is not maintainable
and the Civil Court has no jurisdiction to decide the issue on hand.
16. Mere reading of Section 8 of the Act, clearly shows that there
is no bar for the Civil Court to decide this issue. Therefore, Section 5 of
the Arbitration and Conciliation Act, 1996 would not be applicable to
the present case. When the appellants admitted the purchase order,
payment of 30% value of purchase order as advance, receipt of e-mails
and legal notice, they cannot say that the Civil Court has got no
jurisdiction. A combined reading of Sections 8 and 5 of the Act shows
that the intention of the legislature is not totally ousting the jurisdiction
of civil Court. If one of the parties approached the Civil Court for legal
remedy and if the subject contract or agreement provides arbitration
clause, then, it is option for the other party to resolve the dispute through
arbitration by invoking Section 8 of the Act. In case, the other party /
defendant has not opted for arbitration by invoking Section 8 of the Act,
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
then, Civil Court can proceed with the suit. Therefore, in the present
case, neither Section 8 of the Act nor Section 5 of the Act would bar the
jurisdiction of the Civil Court. Considering the nature of transaction
between the parties and dispute between the parties, this Court finds that
even though the purchase order provides arbitration clause, when the
respondent sent a legal notice, the appellant has not opted to avail the
same and even when the respondent filed the suit, the appellant has not
filed any application under Section 8 of the Act before filing the first
written statement. Mere referring the arbitration clause in one of the
paragraphs of the written statement is not enough to ouster the
jurisdiction of the Civil Court. Therefore, under these circumstances,
considering the pleadings, oral and documentary evidence, this Court
finds that the trial Court has got jurisdiction to entertain the suit.
17. Admittedly, the respondent filed the suit based on the purchase
order Ex.A2 and there is an arbitration clause provided in clause 16 of
the purchase order. Admittedly, prior to the filing of the suit, the
respondent sent pre-suit notice, for which, the appellants did not give any
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
reply. Hence, the respondent filed the suit claiming damages, which they
incurred on account of the breach committed by the first appellant by
violating the contractual agreement dated 12.06.2008.
18. The learned senior counsel for the appellants contended that
there is no need to file separate application under Section 8 of the Act.
Since there is a specific averment in the written statement, the trial Court,
itself, could have referred the matter to arbitration. Therefore, the
learned senior counsel contended that the jurisdiction of the Trial Court
is ousted and hence the Judgment and Decree passed by the trial Court is
liable to be set aside. In support of his contentions he made reliance on
number of Judgements which are mentioned above. Though the learned
counsel for the appellants (defendants) undertook before the Trial Court
to file vakalath on 12.01.2010, he filed vakalath only on 01.04.2010.
The filing of the suit by the respondent came to the knowledge of the
appellants way back on 12.01.2010 itself. However, the appellants did
not file their written statement either immediately within a period of 30
days or within a period of 90 days from the date of receipt of summons.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
Though the learned counsel undertook to file vakalath on 12.01.2010
itself, written statement was filed only on 30.11.2010. The appellants
have not chosen to file any application under Section 8 of the Act even
on 30.11.2010 or prior to that.
19. For the sake of convenience, Section 8 of the Act is extracted
hereunder.
"Power to refer parties to arbitration where there is an arbitration agreement.
(1) A judicial authority, before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party to the arbitration agreement or any person claiming through or under him, so applies not later than the date of submitting his first statement on the substance of the dispute, then, notwithstanding any judgment, decree or order of the Supreme court or any Court, refer the parties to arbitration unless it finds that prima facie no valid arbitration agreement exists.
(2) The application referred to in sub-section (1) shall not be entertained unless it is accompanied by the original arbitration agreement or a duly certified copy thereof:
[Provided that where the original arbitration agreement or a certified copy thereof is not available with the party applying for reference to arbitration under sub-section (1), and the said agreement or certified copy is retained by the other party to that agreement, then, the party so applying shall file such application along with a copy of the arbitration agreement and a petition
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
praying the Court to call upon the other party to produce the original arbitration agreement or its duly certified copy before that Court]
(3) Notwithstanding that an application has been made under sub- section(1) and that the issue is pending before the judicial authority, an arbitration may be commenced or continued and an arbitral award made."
20. According to the learned counsel for the appellants, a formal
application under Section 8(1) of the Act is not required and mere
reference of arbitration clause in the written statement is enough for the
Trial Court to refer the matter to arbitration. We are not accepting the
said contention for the reason that Section 8 (1) uses the term 'so applies',
which would mean that a party is required to make a formal application
for referring the dispute to arbitration. The implied timeline fixed under
Section 8(1) persumes filing of an application and for the application to
be made before filing of the first written statement on the substance of
the dispute. Construing the words 'so applies' in Section 8(1) in any
other manner would render the express time-frame completely
meaningless. Section 8(2) refers to the application in Section 8(1) and
the requirement of filing such an application in a proper form. The
requirement of filing a separate application under Section 8(1) is
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
distinctive to and independence of the first statement to the substance of
the dispute. A reference to the arbitration clause in the written statement,
simpliciter, does not satisfy the rigour of Section 8(1) of the Act in terms
of making a separate application for referring the parties to arbitration.
21. The appellants have simply referred to the arbitration clause in
the written statement and objected to the maintainability of the suit.
However, the objection would not absolve the appellants from the
discipline of filing of an application under Section 8 of the Act. Though
the learned senior counsel for the appellants would submit that mere
bringing to the knowledge of the Court about the existence of the
arbitration clause is enough; Trial Court cannot proceed with the matter
further; and it is mandatory to refer the matter to arbitration, a reading of
Section 8 of the Act states otherwise. Therefore, under these
circumstances, the contention of the learned senior counsel for the
appellants is not acceptable. Even otherwise, it is seen from the records
that the respondent sent a legal notice regarding their claim and the first
appellant did not send any reply and thereafter only, the respondent filed
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
the suit. Even though the filing of the suit was well within the
knowledge of the appellants (defendants) on 12.01.2010 itself, they took
10 months time for filing of the first written statement.
22. In this context, it is pertinent to extract Order 8 Rule 1 of the
Code of Civil Procedure.
1. Written Statement.—The Defendant shall, within thirty days from the date of service of summons on him, present a written statement of his defence:
Provided that where the defendant fails to file the written statement within the said period of thirty days, he shall be allowed to file the same on such other day, as may be specified by the Court, for reasons to be recorded in writing, but which shall not be later than ninety days from the date of service of summons.
[Provided that where the defendant fails to file the written statement within the said period of thirty days, he shall be allowed to file the written statement on such other day, as may be specified by the Court, for reasons to be recorded in writing and on payment of such costs as the Court deems fit, but which shall not be later than one hundred twenty days from the date of service of summons and on expiry of one hundred twenty days from the date of service of summons, the defendant shall forfeit the right to file the written statement and the Court shall not allow the written statement to be taken on record.]
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
23. From a reading of the above, it is clear that within 30 days
from the date of service of summons, the defendant has to file the written
statement. Proviso clause states that the defendant could file the written
statement with the permission of the Court within 90 days, and thereafter
the defendant cannot file the written statement, though there is no
forfeiture clause as in the Commercial Courts Act, 2015. However, if at
all the appellants wanted to exercise the arbitration clause, they ought to
have filed the application under Section 8 of the Act immediately or even
otherwise at the worst case, they ought to have filed such an application
along with the written statement. However, they have not done so. They
have simply averred about the arbitration clause in the written statement
and objected to the maintainability of suit. They have taken no sincere
efforts to refer the matter to Arbitration by producing the original
Agreement or Certified copy of the Agreement. Even otherwise, they
have not filed any application to decide the preliminary issue regarding
the jurisdiction of the Trial Court or maintainability of the suit or filed an
application under Order 7 Rule 11 for rejection of plaint. Knowing fully
well the consequences, the appellants have not tried to resolve the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
dispute through Arbitration by invoking the arbitration clause. The scope
and object of the arbitration clause itself is for speedy disposal of the
matter. The conduct of the appellants shows that their intention is not to
resolve the dispute through Arbitration, but only to evade and protract
the suit. Under these circumstances, this Court finds that the appellants
have not come to the Court with clean hands and the above points are
answered accordingly. The Trial Court has also elaborately discussed the
pleadings, oral and documentary evidence. This Court as a final Court of
fact finding, after perusal of the claim of the respondent in the plaint,
written submissions of the appellants, oral and documentary and
evidence produced on both sides, finds that the respondent have proved
their claim. The citations relied on by the learned senior counsel
appearing for the appellants is not applicable to the case on hand, as they
are distinguishable on facts. Therefore, the Trial Court rightly
appreciated the oral and documentary evidence and decreed the suit in
favour of the respondent herein. There are no merits in the appeal.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
24. Accordingly, the Appeal Suit appeal is dismissed. No costs.
Consequently, connected Miscellaneous Petition is closed.
(P.V., J.) (K.K.R.K., J.)
14.02.2025 NCC:Yes/No Index:Yes/No Speaking/Non-speaking order
mbi
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
To
1.The I Additional District Judge (PCR), Tiruchirappalli.
2.The Section Officer, Vernacular Records Section, Madurai Bench of Madras High Court, Madurai.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
P.VELMURUGAN, J.
and K.K.RAMAKRISHNAN, J.
mbi
and
14.02.2025
https://www.mhc.tn.gov.in/judis ( Uploaded on: 20/03/2025 10:51:42 am )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!