Wednesday, 06, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

K.C.Thangavel vs Tamilnadu Newsprint And Papers Limited
2024 Latest Caselaw 20049 Mad

Citation : 2024 Latest Caselaw 20049 Mad
Judgement Date : 24 October, 2024

Madras High Court

K.C.Thangavel vs Tamilnadu Newsprint And Papers Limited on 24 October, 2024

                                                             C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

                          BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT

                                                     Dated : 24.10.2024

                                                          CORAM :

                            THE HONOURABLE MR.JUSTICE SUNDER MOHAN

                             C.M.A(MD)Nos. 1193 to 1202, 1289 to 1293 of 2024
                       and C.M.P(MD)Nos. 13887 to 13890, 13778 to 13782, 12532, 12533,
                           12535 to 12537, 12541, 12543 to 12545 and 12547 of 2024

                     In CMA(MD)No.1193 of 2024:
                     K.C.Thangavel                               ... Appellant/1st Respondent

                                                              Vs.

                     Tamilnadu Newsprint and Papers Limited,
                     (A Government of Tamil Nadu Enterprise),
                     Kagithapuram – 639 136
                     Karur District                     ... Respondent/Petitioner


                      PRAYER: Civil Miscellaneous Appeal is filed under Section 37 of the

                     Arbitration and Conciliation Act, 1996, against fair and decreetal order

                     dated 23.02.2023 passed in Arbitration O.P.No.71 of 2021 on the file of

                     the Principal District Judge, Karur.

                                       In all the appeals:
                                       For Appellant       : Mrs.P.Jessi Jeeva Priya
                                       For Respondent : Mr.AR.L.Sundaresan
                                                             Senior Counsel
                                                             for Mr.M.P.Senthil




https://www.mhc.tn.gov.in/judis
                     Page No.1 of 12
                                                               C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

                                                   C O M M ON O R D E R


The appeals have been filed under Section 37 of the the Arbitration

and Conciliation Act, 1996, challenging the orders passed under Section

34 of the Arbitration Act.

2. The issue involved in all the appeals is one and the same and

therefore, all the appeals are taken up together.

3. The facts leading to the filing of these appeals are as follows:

a) The appellants had entered into a lease agreement with the

respondent on various dates in the years 2011 and 2012, by which, they

agreed to hand over the land for lease to the respondent for a period of

six years;

b) As per the agreement, during the period of lease, the respondent

would be permitted to plant eucalyptus/pulp trees; and the appellants

would be entitled to a lease rent of Rs.4,000/- (Rupees four thousand

only) per annum for an acre of land;

c) The respondent could not adhere to the terms of the agreement

as they could not cultivate the land for certain reasons, and hence, they

terminated the agreement unilaterally even before the expiry of six years.

https://www.mhc.tn.gov.in/judis

C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

The appellants were aggrieved by the said action.

d)The agreement contains an arbitration clause. Therefore, the

appellants sought for appointment of an Arbitrator and the Arbitrator was

appointed by this Court.

e)The Arbitrator found that the respondent had committed breach

of contract and directed the respondent to pay damages equivalent to the

lease rent for the balance lease period, damages for the loss caused since

the appellants had no opportunity to plant the second crop and towards

expenses incurred for plucking out and removal of roots and flattening

the land.

f) The respondent challenged the Arbitrator's award before the

District Court under Section 34 of the Arbitration Act. The District Court

found that the award is liable to be set aside in respect of compensation

under two heads (ie) towards damages caused due to the inability to plant

second crop and towards expenses for plucking out and removal of roots

as it was against the basic notions of justice. However, the District Court

confirmed the award as regards the direction to pay the lease rent for the

balance lease period.

g) The instant appeals have been filed challenging the said order

passed under Section 34 of the Arbitration Act by the District Court.

https://www.mhc.tn.gov.in/judis

C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

4.a) Mrs.Jessi Jeeva Priya, learned counsel for the appellants

would submit that the award of the Arbitrator is in accordance with law;

that in any case, it is neither perverse, illegal or opposed to public policy

and therefore ought not to have been interfered with under Section 34 of

the Arbitration Act.

4.b) The learned counsel submitted that as per the agreement, the

respondent was bound to maintain the land in such a manner, so that at

the end of the lease period, the appellants are able to cultivate the land;

that because of non-maintenance, they could not cultivate the land and

lost the opportunity to plant the second crop; and therefore, the

compensation awarded by the Arbitrator cannot be called perverse or

opposed to public policy and hence the District Court under Section 34

of the Arbitration Act ought not to have set aside the award under two

heads.

4.c) The learned counsel further submitted that the Arbitrator had

awarded the compensation by invoking the provisions of the Contract

Act and not as per the terms of the agreement as erroneously found by

the District Court and therefore, the order under Section 34 of the

https://www.mhc.tn.gov.in/judis

C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

Arbitration Act is liable to be set aside.

5. Mr.AR.L.Sundaresan, learned Senior Counsel appearing for the

respondent, per contra, submitted that under the lease agreement, the

appellants would at the best be entitled to the lease rent for a period of

six years; that even assuming that the respondent committed a breach, the

appellants would be entitled to damages equivalent to the rent for the

balance lease period left after the termination, which has been rightly

ordered by the Arbitrator; that the Arbitrator had awarded the

compensation under the other heads (ie) loss towards the second crop

and loss due to the expenses incurred for flattening the land, which were

neither contemplated under the agreement nor in law; and that therefore,

the District Court was right in setting aside the award under those two

heads; and hence the appeals deserve to be dismissed.

6. This Court gave its anxious consideration to the submissions

made on either side and carefully perused the materials available on

record.

7. The admitted facts are that the appellants and the respondent

https://www.mhc.tn.gov.in/judis

C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

entered into a lease agreement for a period of six years. As per the terms

of agreement, the respondent was permitted to plant eucalyptus/pulp trees

and entitled to remove it at the end of the lease period and the lease

period could be extended for a further period of six years, if there is a

mutual agreement. The fact that the respondent terminated the lease

agreement before the expiry of the agreement unilaterally is not in

dispute.

8. The only question is as to what would be the compensation

payable to the appellants for the said breach. As per the agreement, the

appellants are not entitled to receive any amount from the respondent at

the end of the lease period except for the lease amount. However, this

clause cannot be pressed into service because the lease was terminated

even before the lease period. Hence, the appellants would certainly be

entitled to the compensation for the breach under Section 73 of the

Contract Act. As per the terms of the agreement, if the lease had

continued for the entire period contemplated under the appellants, the

appellants would have been entitled to lease rent of Rs.4000/- (Rupees

four thousand only) per annum for six years. This has been awarded by

the Arbitrator as damages after deducting the lease amount paid already

https://www.mhc.tn.gov.in/judis

C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

and has been rightly confirmed by the District Court.

9. However, in addition to the said compensation, the Arbitrator

had also awarded an additional sum towards the loss that had been

purportedly caused due to the denial of opportunity to plant and harvest

the second crop. The agreement does not contemplate payment of

damages for the said reason. The agreement would state that during the

period of lease, the respondent has to maintain the land in the best

possible manner and hand it over at the end of the period of six years.

The award of compensation towards denial of opportunity to plant the

second crop is based on an erroneous appreciation of the evidence and

contrary to Section 73 of the Contract Act. The terms of the agreement

does not guarantee any such right or opportunity to the appellants.

Section 73 of the Contract reads as follows:

''73.Compensation for loss or damage caused by breach of contract.—When a contract has been broken, the party who suffers by such breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it.

Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the https://www.mhc.tn.gov.in/judis

C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

breach''.

The above provision makes it clear that the compensation cannot be

given for any remote or indirect loss or damage sustained by reason of

the breach even assuming that the appellants would have suffered a

remote or indirect loss. The possession of the land was handed over

before the expiry of the lease period and the appellants were also

awarded the lease amount for the total period of six years. Therefore, this

Court is of the view that apart from the lease rent, the appellants had not

suffered any other loss and the award passed by the Arbitrator suffered

from patent illegality. Therefore, the District Court was right in setting

aside the compensation under the said head in an application under

Section 34 of the Arbitration Act as it was vitiated by an illegality

apparent on the face of the award.

10. As rightly pointed out by the learned Senior Counsel, this

would not amount to modification of the award. The law in the regard is

well settled that if the award is passed under one or more heads,

compensation under anyone of those heads can be set aside and it would

not amount to modification.

https://www.mhc.tn.gov.in/judis

C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

11. The District Court had set aside the award under another head

namely, the expenses incurred by the appellants for plucking and

removing the roots and flattening the land and building of the bunds. The

award under the said head by the Arbitrator is not perverse or opposed to

public policy. Therefore, the District Court had no jurisdiction to set

aside the award under that head under Section 34 of the Arbitration Act.

The appellants are therefore entitled to compensation awarded under the

head towards plucking and removing of roots and flattening the land.

12. In paragraph No.51 of the award, the Arbitrator has given a

tabulation of the heads of compensation under which the appellants are

entitled to. Out of the three heads mentioned, the appellants are entitled

to compensation mentioned in S.Nos.1 and 3, which relates to the lease

amount and expenses towards plucking and removal of roots and

flattening of land. The damages for loss caused because of inability to

plant second crop is mentioned in S.No.2, which is set aside by the

District Court and confirmed by this Court. Therefore, the appellants are

not entitled to compensation under the said head.

13. This Court by an earlier order dated 26.09.2024 directed the

https://www.mhc.tn.gov.in/judis

C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

respondent to pay their admitted liability, which pertains to the lease rent

payable to the appellants within a period of three weeks. However, it is

reported that the respondent has not paid the said amount even as on

date. The learned counsel for the respondent expressed difficulty in

complying with the said order. There cannot be any excuse for delaying

the said payment and hence that portion of the amount shall be paid on or

before 05.11.2024. As regards the compensation towards plucking out,

removal of roots and flattening the land, which is the other head of the

compensation to which the appellants are entitled to, the respondent shall

pay the same within a period of three weeks from the date of receipt of a

copy of this order.

14. In fine, these appeals are partly allowed. No costs.

Consequently, connected miscellaneous petitions are closed.





                                                                               24.10.2024
                     Index               : Yes / No
                     Neutral Citation : Yes / No
                     CM

Note: Registry is directed to upload this judgment in the official web-site on 29.10.2024

https://www.mhc.tn.gov.in/judis

C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

To

1. The Principal District Judge, Karur.

2. The Section Officer, V.R.Section, Madurai Bench of Madras High Court, Madurai.

https://www.mhc.tn.gov.in/judis

C.M.A.(MD)Nos.1193 to 1202, 1289 to 1293 of 2024

SUNDER MOHAN, J.

CM

Judgment made in C.M.A(MD)Nos. 1193 to 1202, 1289 to 1293 of 2024 and C.M.P(MD)Nos. 13887 to 13890, 13778 to 13782, 12532, 12533, 12535 to 12537, 12541, 12543 to 12545 and 12547 of 2024

24.10.2024

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter